Resolved
That approval be given to the release of £735k to enable works at Cherry Trees Respite to be progressed.
Cabinet approved this item on Tuesday 14 January 2020. Below is the council's own wording, with the papers it was decided on.
Resolved
That approval be given to the release of £735k to enable works at Cherry Trees Respite to be progressed.
1.1Cherry Trees in an 8 bedded learning disabilities respite unit in Shepley, Huddersfield (Kirkburton Ward). The unit is owned and managed by Kirklees Council and provides respite services mainly for those residing in South Kirklees.
1.2The initial outline business case was approved at Cabinet in February 2019 for inclusion in Strategic Priorities ‘Day Services Support for Vulnerable Adults’ Capital Budget 2019/20 to 2024/25 (Independent theme).
1.3The project is also programmed to include corporate Fire Prevention Works to be funded from alternative corporate funding, which will be carried out simultaneously.
1.4During the building works, the service will relocate to alternative premises in Heckmondwike. This has been agreed with staff, unions, carers and families.
2. Information required to take a decision
2.1Detailed design has identified an estimated outturn cost of £735k (excluding £115k for fire safety works). Cabinet approval is now requested to agree and release the sum of £735k sum in order that appropriate tenders can be sought and the works progress.
2.2The Full Business Case relating to this capital scheme is attached as Appendix 1. This details the proposed level of works involved and the supportive reasons for this development.
2.3The Design and Assess Statement relating to this scheme is attached as Appendix 2.
2.4Planning approval has been applied for.
2.5Members are reminded that before making any decisions that they have a legal duty to consider the Equality Act 2010, Section 149 introduced a public sector equality duty that the Council must in the exercise of their functions, have due regard to the need to (a) eliminate discrimination, harassment, victimisation; (b) advance equality of opportunity between persons who share a relevant protected characteristic and persons who do not share it; (c) foster good relations between persons who share a relevant protected characteristic and persons who do not share it. Protected characteristics are: age, disability, gender reassignment, marriage and civil partnership, pregnancy and maternity, race, religion or belief, sex and sexual orientation.
2.6Members should have due regard to the Integrated Impact assessment screening tool at Appendix 3 which shows no adverse effect on the above protected groups.
3. Implications for the Council
3.1The Council’s capital budget plans support the overall delivery of the following Council objectives and priorities within available resources:
i) Well ii) Independent iii) Safe and cohesive iv) Clean and Green v) Efficient and Effective 3.2 Working with People There will be a positive impact on both the people that use the service, their families/carers and also for staff.
3.3Working with Partners There will be a positive impact for relevant health partners.
3.4Place Based Working Neutral.
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
PDF |
Capital Scheme: Cherry Trees RespiteReport | 189 KB | DownloadRead as text |
PDF |
Item 8a Cherrytrees Full Business Case to ET Cabinet :Report | 256 KB | Download |
PDF |
Item 8b Appendix A benefits table :Appendix | 83 KB | Download |
PDF |
Item 8c DAS Cherry Trees :Report | 6.2 MB | Download |
PDF |
Item 8d integrated-impact-assessment-stage-1- Cherry Trees :Report | 102 KB | Download |
Follow Cabinet at Kirklees and we tell you when its next papers are published, before the meeting rather than after it.
| Meeting | Decision | Outcome | |
|---|---|---|---|
| 3 Nov 2026 | 8RESOLVED – 1) That the outcome of the Regulator of Social Housing inspection be noted. 2) That the Regulatory Improve... | Noted | Open |
| 3 Nov 2026 | 10RESOLVED – 1) That the rent and service charge policy be approved. 2) That authority be granted to the Executive Dire... | Approved | Open |
| 3 Nov 2026 | 12RESOLVED – 1) That approval be given to the Kirklees Employment Skills Framework 2026-2030 as the district-wide strat... | Approved | Open |
| 6 Oct 2026 | 8RESOLVED – That the report be referred to the Meeting of Council on 21 October 2026 with the recommendations that Cou... | Noted | Open |
| 6 Oct 2026 | 9RESOLVED 1) That approval be given to the disposal of the land and property within the Capital Receipts Schedule Octo... | Approved | Open |
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Keeps you signed in and runs your free-paper allowance. Always on.
Counts visits and which pages are used. First-party only, no advertising, never shared.