1) That the approach as outlined within the report be endorsed in order to bring Council owned land within the Central Gateway of the Dewsbury Riverside site forward as the first phases of development. 2) That approval be given for the Council to acquire 11.5 hectares of land currently owned by Leeds Diocese, subject to the parameters as set out at the (exempt) appendix to the report. 3) That approval be given for the Council to acquire land interests within the Dewsbury Riverside within the cap, subject to the parameters as set out at the (exempt) appendix to the report. 4) That approval be given to capital expenditure of up to £1,050,000 in the 2020/2021 and 2021/2022 financial years in order to (i) facilitate the relocation of the Council owned Ravenshall allotments (ii) procure the preparation of a detailed and costed delivery plan for the development of Council owned land within the Dewsbury Riverside site and (iii) prepare detailed designs and invite tenders for the construction of the Forge Lane junction, spine road and associated drainage.
Word for word from the decision Kirklees published for this meeting.Source: democracy.kirklees.gov.uk
Name of meeting: Cabinet Date: 25th February 2020 Title of report: Dewsbury Riverside Development Strategy
Purpose of report: This report seeks:
1. Endorsement of the approach outlined in the report to bring Council owned land in the Central Gateway of the Dewsbury Riverside site forward as first phases of development.
2. Approval for the Council to acquire 11.5 hectares of land currently owned by the Leeds Diocese subject to the parameters set out in the private appendix.
3. Approval for the Council to acquire land interests within the Dewsbury Riverside site within the cap and subject to the parameters set out in the private appendix.
4. Approval of capital expenditure of up to £1,050,000 in the 2020/21 and 2021/22 financial years to: ▪ Facilitate the relocation of the Council owned Ravenshall allotments ▪ Procure the preparation of a detailed and costed delivery plan for the development of Council owned land within the Dewsbury Riverside site ▪ Prepare detailed designs and invite tenders for the construction of the Forge Lane junction, spine road and associated drainage.
Key Decision - Is it likely to result in spending or Yes saving £250k or more, or to have a significant effect on two or more electoral wards? If yes give the reason why Affects two wards and likely to result in expenditure of over £250,000
Key Decision - Is it in the Key Decision – Yes Council’s Forward Plan (key decisions and private reports)? Private Report/Private Appendix – Yes Private Appendices 1 and 2
The Appendices are recommended for consideration in private in accordance with Schedule 12A of the Local Government Act 1972 namely it contains information relating to the financial and business affairs of the Council and third parties. It is considered that disclosure of the information would adversely affect negotiations with third party landowners and therefore the public interest in maintaining the exemption, which would protect the rights of an individual or the council, outweighs the public interest in disclosing the information and providing greater openness in the council’s decision making.
The Decision - Is it eligible for call in by Scrutiny? Yes
Date signed off by Strategic Director Karl Battersby - 13.02.2020
Is it also signed off by the Service Director for Eamonn Croston - 13.02.2020 Finance IT and Transactional Services?
Is it also signed off by the Service Director for Julie Muscroft - 17.02.2020 Legal Governance and Commissioning Support? Cabinet member portfolio Councillor McBride - Regeneration Councillor Scott - Housing and Democracy Councillor Turner - Corporate
Electoral wards affected: Dewsbury South and Mirfield
Ward councillors consulted: Cllr Ahmed, Cllr Asif, Cllr Dad (Dewsbury South); Cllr Bolt, Cllr Lees-Hamilton, Cllr Taylor (Mirfield)
Public or private: Public with private appendices Has GDPR been considered? Yes 1. Summary
1.1Dewsbury Riverside is a key site within the North Kirklees Growth Zone which is identified as a spatial priority area for housing growth in the Leeds City Region Strategic Economic Plan. The site is allocated for housing in the recently adopted Kirklees Local Plan with capacity for up to 4000 homes, of which approximately 1869 are proposed to be developed within the Local Plan period up to 2031.
1.2The vision for Dewsbury Riverside is to create a sustainable urban extension that will deliver social, environmental and economic benefits, provide a mix of high quality homes of different tenures together with community infrastructure to create a sustainable, vibrant mixed community; and to retain, expand and enhance existing green infrastructure, connecting new and existing communities to healthy lifestyle opportunities. The scale of the development is intended to be large enough to allow a degree of “market repositioning” and thereby to act as a catalyst for the regeneration of the wider area.
1.3On the 19th March 2019 the Council’s Cabinet:
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.