Resolved

1) That approval be given to the adoption of the Huddersfield Town Centre Blueprint Supplemental Planning Document, as set out at Appendix 2 of the considered report. 2) That Cabinet recognise the importance of the Penistone line to Kirklees, in terms of the connectivity that it provides to the Sheffield City Region, and that the importance of this infrastructure and the benefits that it provides for accessibility and the economy should be recognised within the Masterplan. 3) That Officers be authorised to carry out the necessary formal procedures for the adoption of the Huddersfield Town Centre Blueprint Supplemental Planning Document. 4) That authority be delegated to the Strategic Director (Economy and Infrastructure) to make any further non-material additional modifications to the Huddersfield Town Centre Blueprint Supplemental Planning Document that arise as part of the adoption process.
Word for word from the decision Kirklees published for this meeting. Source: democracy.kirklees.gov.uk

Follow this further

Built from Kirklees's papers

What the report saysPro

Report to Cabinet

Purpose of report

To seek approval to the adoption of the Huddersfield Town Centre Blueprint Supplementary Planning Document.

Key Decision - Is it likely to result in Yes Expenditure>£250,000 and affects spending or saving £250k or more, or to more than 1 ward (Newsome, Greenhead have a significant effect on two or more and Dalton) electoral wards?

Key Decision - Is it in the Council’s Yes Forward Plan (key decisions and private reports)?

The Decision - Is it eligible for call in by Yes Scrutiny?

Date signed off by Strategic Director & Karl Battersby - 09.04.20 name

Is it also signed off by the Service Director for Finance? Eamonn Croston - 13.05.20

Is it also signed off by the Service Director for Legal Governance and Commissioning? Julie Muscroft - 14.05.20

Cabinet member portfolio Cllr McBride

Electoral wards affected: All

Ward councillors consulted:

A Member workshop was held 23rd October 2018 to shape the Blueprint document and a briefing session prior to the launch of the Blueprint in June 2019.

Public or private: Public

Has GDPR been considered? The report does not contain any personal data. The storage of information collected in response to the proposed consultation on the SPD in March will be in accordance with the Planning Policy Privacy Note. 1. Summary Supplementary Planning Documents are produced to add clarity in relation to the application of planning policies set out in the Local Plan. The benefit of converting the Huddersfield Blueprint to a Supplementary Planning Document is that its weight as a planning tool will add greater support to the delivery of Huddersfield Town Centre Regeneration Programme including potential funding applications for the delivery of key sites and transport schemes identified in the Huddersfield Blueprint.

The Huddersfield Blueprint has already been used to share ambitions with partners and funders in order to secure delivery of key projects. Since the last report to Cabinet on 25 February 2020, the council has agreed to acquire the George Hotel, and this will be subject to a separate Cabinet Report,and is continuing to work with partners on key projects.

This Supplemental Planning Document can be used to support any Compulsory Purchase Orders in Huddersfield Town Centre which the council may undertake in the future.

2. Information required to take a decision The Huddersfield Town Centre Blueprint Supplementary Planning Document (SPD) was subject to a four-week public consultation commencing on 2nd March 2020, running until 30th March 2020 including all statutory consultees and interested stakeholders.

Some minor changes are proposed to the SPD as a result of the consultation. A schedule of comments received and proposed changes are outlined at Appendix 1.

Summary of main changes included: • Updating of key projects; • Additional references to council’s climate emergency including references to council’s target of 2038 for the district to achieve net zero carbon emissions, updating of text on Heat and Power network and benefits of addressing climate change; and • Additional references to support Huddersfield as an inclusive, family friendly town.

Many comments received requested that the SPD contain additional detail on the design and implementation of schemes. This level of detail is not proposed to be included in the SPD. The intention is that the SPD will be supported by a suite of planning tools including the Huddersfield Town Centre Area Action Plan (AAP), design guidance and, where appropriate, design briefs. The comments received will be used to inform these pieces of work.

The revised SPD is attached at Appendix 2.

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
Appendix 1Appendix 1 502 KB Download
PDF
Appendix 2Appendix 2 36 MB Download
PDF
Huddersfield Town Centre Blueprint: Supplementary Planning DocumentSupplementary 167 KB DownloadRead as text

At this meeting

Whole meeting

More from Kirklees Cabinet

All decisions
MeetingDecisionOutcome
3 Nov 2026 8RESOLVED – 1) That the outcome of the Regulator of Social Housing inspection be noted. 2) That the Regulatory Improve... Noted Open
3 Nov 2026 10RESOLVED – 1) That the rent and service charge policy be approved. 2) That authority be granted to the Executive Dire... Approved Open
3 Nov 2026 12RESOLVED – 1) That approval be given to the Kirklees Employment Skills Framework 2026-2030 as the district-wide strat... Approved Open
6 Oct 2026 8RESOLVED – That the report be referred to the Meeting of Council on 21 October 2026 with the recommendations that Cou... Noted Open
6 Oct 2026 9RESOLVED 1) That approval be given to the disposal of the land and property within the Capital Receipts Schedule Octo... Approved Open