CouncilMonitor
194 principal councils 228,996 meetings since 2000 2.8 million official papers archived Straight from each council's own publication system
Kirklees Council
Cabinet, Tuesday 16 June 2020 at 3.00pm

8

Approved Executive 1 paper

Cabinet approved this item on Tuesday 16 June 2020. Below is the council's own wording, with the papers it was decided on.

Item8:

Resolved

1) That approval be given to the capital allocation of £402k for the provision of modular accommodation for Brambles Primary Academy to ensure that there is sufficient space for September 2020 intake. 2) That approval be given to the capital allocation of £5.25m for the implementation of new build and remodelling works at King James’s School to enable the provision of 150 additional secondary school places. 3) That approval be given to the capital allocation of £275k for the implementation of a package of works required to ensure that the Greenside Building at Almondbury Community School (Primary) is fit for purpose for a 210 place primary school. 4) That approval be given to the capital allocations of £200k for the implementation of a package of works to enable the existing accommodation at Netherhall Learning Campus High School to be adapted to accommodate increased pupil numbers and implement a PAN increase of 15 places. 5) That approval be given to capital allocations of £151k for the conversion of the former Thornhill Lees Library and Information Centre to a post 16 centre for Ravenshall Special School. 6) That the progress and expenditure incurred to date on the development of an SEN Masterplan to deliver additional specialist SEND places across the system in Kirklees be noted and that approval be given to the expenditure of £150k of further development funds to enable the masterplan to move into a phase 2 study. 7) That approval be given to the proposed use of Section 106 funds to implement a package of works at Scissett Middle School at a cost of £210k to enable its PAN to increase from 195 to 200.
Word for word from the decision Kirklees published for this meeting. Source: democracy.kirklees.gov.uk

Follow this further

Built from Kirklees's papers

What the report saysPro

Report to Cabinet

Purpose of report

This report will identify potential schools’ projects, for Member approval, to be funded from the 2020/21 to 2024/25 Achieve and Aspire Strategic Priorities and Basic Need funding sections of the Council’s Capital Plan

Key Decision - Is it likely to result in Yes - this will result in capital expenditure spending or saving £250k or more, or to significantly in excess of £250K have a significant effect on two or more electoral wards? Key Decision - Is it in the Council’s Key Decision - Yes Forward Plan (key decisions and private reports)? Public Report

The Decision - Is it eligible for call in by Yes Scrutiny?

Date signed off by Strategic Director & Mel Meggs - 4 June 2020 name

Is it also signed off by the Service Eamonn Croston - 3 June 2020 Director for Finance?

Is it also signed off by the Service Julie Muscroft - 4 June 2020 Director for Legal Governance and Commissioning?

Cabinet member portfolio Cllr Viv Kendrick - Children (Statutory Responsibility for Children) Cllr Carole Pattison - Learning, Aspiration & Communities Cllr Graham Turner - Corporate

Electoral wards affected: Almondbury/Dalton/Denby Dale/ Dewsbury South/Greenhead

Ward councillors consulted: Yes

Public or private: Public

Has GDPR been considered? There are no GDPR implications arising from this report. 1 1. Summary

1.1This report will provide information relating to specific individual school related capital projects identified to be funded from the Directorate for Children’s Services Achieve and Aspire Section of the Council’s Five Year Capital Plan, which was approved by Council on 12th February 2020.

1.2Members will be asked to consider and approve the projects identified in the report, along with the highlighted capital allocation for each scheme.

2. Information required to take a decision

(i) Brambles Primary Academy – Temporary Modular Accommodation for September 2020 Intake

2.1Members will be aware of the enforced delays to the start of construction of the new build Brambles Primary Academy on Clare Hill playing fields due to protracted legal challenges from a small group of residents. These issues continue to be worked through the appropriate legal and planning processes to resolution though some delay is now being experienced due to the ongoing COVID-19 pandemic which is impacting on Court and Government decision making.

2.2Work on the new school has now begun in the meantime with the creation of a temporary car park currently on site through the Council’s Highways Service. The new build school has been retendered, with submissions currently being evaluated with a view to contract award in July/August and a start on site in September 2020. The completed school would be available for occupation from September 2021.

2.3It is important to note that whilst the new build school has been delayed, Brambles Primary Academy itself opened as a new school in September 2018 in temporary modular accommodation within the grounds of Highfields Adult Day Centre. Additional modular accommodation was added in 2019 and regrettably the ongoing delay means that further temporary accommodation will need to be provided for the September 2020 intake. Hopefully, this will be the last occasion on which this needs to occur.

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
2020/21 to 2024/25 Council Capital Plan: Proposed Allocation of Capital Funding from the Directorate for Children’s Achieve & Aspire Strategic Priorities and Basic Need Baseline Funding Sections of the Capital PlanReport 224 KB DownloadRead as text

At this meeting

Whole meeting

More from Kirklees Cabinet

All decisions
MeetingDecisionOutcome
3 Nov 2026 8RESOLVED – 1) That the outcome of the Regulator of Social Housing inspection be noted. 2) That the Regulatory Improve... Noted Open
3 Nov 2026 10RESOLVED – 1) That the rent and service charge policy be approved. 2) That authority be granted to the Executive Dire... Approved Open
3 Nov 2026 12RESOLVED – 1) That approval be given to the Kirklees Employment Skills Framework 2026-2030 as the district-wide strat... Approved Open
6 Oct 2026 8RESOLVED – That the report be referred to the Meeting of Council on 21 October 2026 with the recommendations that Cou... Noted Open
6 Oct 2026 9RESOLVED 1) That approval be given to the disposal of the land and property within the Capital Receipts Schedule Octo... Approved Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies