1) That the projects and status of the budgets for the town centre programmes as set out in section 2.5, 2.6 and Appendix 1 of the considered report be noted. 2) That the Council’s current contribution to the identified projects, as set out at para. 2.7, be approved. 3) That the agreed sums of match funding, as set out at para. 2.7, be approved and drawn into the capital plan, and that Officers be authorised to incur expenditure on the working up of plans and proposals for the project/s. 4) That approval be given to utilising up to £1m of town centre capital to develop and deliver a town centre programme of public realm improvements across both towns (para. 2.10 refers). 5) That approval be given to accepting appropriate development funds for projects as set out at para. 2.19, for use by Kirklees Council and its agents, and that Officers be authorised to enter into grant and other agreements, where necessary, and to incur expenditure on the working up of plans and proposals for the projects.
Word for word from the decision Kirklees published for this meeting.Source: democracy.kirklees.gov.uk
Name of meeting: Cabinet Date: 22nd September 2020 Title of report: Huddersfield and Dewsbury Town Centre Finance Report
Purpose of report: To inform the Cabinet of the current status of the Blueprint Programmes in terms of finance and to make a decision to enter projects within the programme onto the Kirklees Capital Plan. A further update is provided on grant funding for town centre projects.
Key Decision - Is it likely to result in spending Yes or saving £250k or more, or to have a significant effect on two or more electoral wards? Key Decision - Is it in the Council’s Forward Key Decision – Yes Plan (key decisions and private reports)? Private Report/Private Appendix – No
The Decision - Is it eligible for call in by Yes Scrutiny?
Date signed off by Strategic Director & name Karl Battersby - 9th September 2020
Is it also signed off by the Service Director for Eamonn Croston - 9th September 2020 Finance?
Is it also signed off by the Service Director for Julie Muscroft - 9th September 2020 Legal Governance and Commissioning?
Cabinet member portfolio Cllr Peter McBride - Regeneration
Electoral wards affected:
Newsome, Dewsbury East, South and West
Ward councillors consulted:
None
Public or private: Public.
Has GDPR been considered?
GDPR is applicable to the TCF Programme and has been considered within the development of the business cases and related stakeholder engagement plans.
g:\dsmt\cabinet reporting\2020 - cabinet meetings\virtual cabinet - 22 september\town centre finance\town centre cabinet report - final version.doc.docx 1. Summary
1.1This report is presented to cabinet for four reasons. These are set out below:
a. To set out, for information, the current capital programme as it relates to the two Blue Prints for Huddersfield and Dewsbury. b. To identify, and agree with Cabinet, projects that require capital funding and to enter those projects onto the Kirklees Capital Plan for development and delivery. c. To identify and agree future match funding and d. Where external grant funding related to town centre programmes is secured agree for officers to draw this into the capital plan and in cases where grant monies have been obtained to fund the costs of working up plans and proposals for town centre programmes to authorise the spending of that grant on the working up of plans and proposals for the identified project
2. Information required to take a decision
Current Allocations
2.1A summary of the budget available for Huddersfield and Dewsbury is listed below showing each element agreed in the Council’s Capital Plan and any additional funding that has been agreed
Huddersfield
Split of Original Town Centre Action plan budget £30,000,000 Sound Space £35,000,000 Market Hall Multi Storey Car Park £10,000,000 £75,000,000 Dewsbury Split of Original Town Centre Action plan budget £15,000,000 Dewsbury Staff move & Regeneration £8,500,000 Leeds City Region Grant for Acquisitions £400,000 Highways - contribution to Spring Clean 2019 £240,000 HAZ Acquisition budget - from Housing Regen budget £431,000 £24,571,000
Total allocation £99,571,000
2.2In addition to the above a further £12.5m has been allocated as part of the budget process as a strategic acquisitions fund across the Blueprint towns.
2.3£10m has also been allocated to small centres whilst smaller amounts have been set aside to deal with issues at Huddersfield Library and Lawrence Batley Theatre.
2.4The revitalisation of town centres, in particular through the delivery of the projects identified in the Blueprint programmes represent Huddersfield and Dewsbury town centres’ contribution to the overall economic recovery of the district as articulated by the Economic Recovery Plan.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.