1) That approval be given to the next tranche of town centres (Batley, Cleckheaton , Holmfirth, Heckmondwike ) to benefit from an additional allocation of £1.5m per centre as part of the Council’s Capital Plan. 2) That the requirements to access funding, as set out at para 2.8 to 2.13. be approved and that authority be delegated to the Strategic Director (Growth and Regeneration) to approve individual plans and projects in consultation with the Cabinet Member (Regeneration). 3) That approval be given to the generic list of project/programme types that funding can be used towards, as detailed at para 2.14 to 2.16. 4) That approval be given to the availability of £1.5m per centre, as detailed at para. 2.17 to 2.18. 5) That the indicative timeframe for delivery be noted, subject to the progress of projects and programmes. 6) That a further report be submitted to Cabinet with regards to the residual investment as referred to at para. 2.19. 7) That approval be given to staffing resources to support the initiative and the mechanism as set out at para. 2.20. 8) That it be noted that the Town Centre Programme Board will oversee and monitor the delivery of the projects and capital investment programme in small town centres.
Word for word from the decision Kirklees published for this meeting.Source: democracy.kirklees.gov.uk
Purpose of report: To set out and agree an approach for developing programmes to support smaller town centres across Kirklees. This report sets out the first phase of this requirement; the conditions for implementation; the resources required and seeks approval to commence the programme of engagement, plan development as well as identification and delivery of projects.
Key Decision - Is it likely to result in spending Yes or saving £250k or more, or to have a significant effect on two or more electoral wards? Key Decision - Is it in the Council’s Forward Key Decision – Yes Plan (key decisions and private reports)? Private Report/Private Appendix – No
The Decision - Is it eligible for call in by Yes Scrutiny?
Date signed off by Strategic Director & name David Shepherd – 24th February 2021
Is it also signed off by the Service Director for Eamonn Croston - 1st March 2021 Finance?
Is it also signed off by the Service Director for Julie Muscroft – 1st March 2021 Legal Governance and Commissioning?
Cabinet member portfolio Cllr Peter McBride – Regeneration
Electoral wards affected:
Batley East, Batley West, Cleckheaton, Heckmondwike, Holme Valley South
Ward councillors consulted: Ward Members from Batley, Cleckheaton, Heckmondwike and Holmfirth have been consulted between 11th January 2021 and 11th February 2021.
Public or private: Public.
Has GDPR been considered?
GDPR is applicable to the Town Centre Programmes and will be considered within the development of programmes, projects, and related stakeholder engagement plans. 1. Summary
1.1This report is presented to Cabinet for the reasons set out below:
a. To set out, for consideration and agreement, the first tranche of town centres to benefit from additional funding allocated as part of the Council’s Capital Plan. (See para: 2.4 - 2.7). b. To identify, and agree with Cabinet, the requirements needed to access the funding. (See para: 2.8 - 2.13). c. To agree project or programme types that funding can be used towards. (See para: 2.14 - 2.16). d. To agree the amounts of funding to be made available. (See para: 2.17 - 2.19). To agree the Council resources to support this initiative. (See para: 2.20) e. To highlight an indicative timeframe for delivery, subject to projects being developed. (See para: 2.21 - 2.22). f. If report agreed, to authorise the Strategic Director for Growth and Regeneration to commence engagement, plan development and identification of projects stages and authorise the subsequent implementation of individual programmes in consultation with the portfolio holder for Regeneration.
2. Information required to take a decision
a. Introduction
2.1We are already underway with a programme of work in the two principal town centres of Huddersfield and Dewsbury. The aim here is to create modern, thriving, and exciting town centres that everyone wants to visit and use. However, our ambition should not end there. We have many important centres outside of these which will require support and investment over the next few years to ensure they remain vibrant places for the communities they serve. We should recognise that these centres can play an important local role and are part of a strategy which allows local people to access a wider range of local services and contributes to a more sustainable way of living which embraces our climate change agenda.
The Impact of the Pandemic on Local Centres
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.