Resolved
RESOLVED - That approval be given to (i) the re-profile of service capital monies in order to allow adequate funds to meet revised anticipated costs and (ii) that the schemes progress to tender process.
Cabinet approved this item on Tuesday 21 September 2021. Below is the council's own wording, with the papers it was decided on.
Resolved
RESOLVED - That approval be given to (i) the re-profile of service capital monies in order to allow adequate funds to meet revised anticipated costs and (ii) that the schemes progress to tender process.
Name of meeting: Cabinet Date: 21st September 2021 Title of report: Adult Social Care Capital Programme – Knowl Park House and The Homestead Capital Schemes
Purpose of report: Re-profile of Service capital monies to meet increased cost of above schemes Key Decision - Is it likely to result in spending or Yes saving £250k or more, or to have a significant effect on two or more electoral wards? Spending over £250k
Key Decision - Is it in the Council’s Forward Plan Key Decision – Yes (key decisions and private reports)? Private Report/Private Appendix – No The Decision - Is it eligible for call in by Yes Scrutiny?
Date signed off by Strategic Director & name Richard Parry on 11/8/21
Is it also signed off by the Service Director for Eamonn Croston on 11/8/21 Finance?
Is it also signed off by the Service Director for Julie Muscroft on 11/8/21 Legal Governance and Commissioning?
Cabinet member portfolio Cllr M Khan on 11/8/21
Electoral wards affected: Mirfield and Almondbury
Ward councillors consulted: Mirfield Cllrs (Cllr Vivien Lees-Hamilton, Cllr Kath Taylor, Cllr Martyn Bolt) and Almondbury Ward Cllrs (Cllr Alison Munroe, Cllr Bernard McGuin, Cllr Paola Davies) have been kept updated on both schemes.
Public or private: Public
Has GDPR been considered? Yes, there are no GDPR implications. 1. Summary
This report sets out the reprofiling of capital monies required to progress with the 2 schemes, Knowl Park House (Mirfield Ward) and The Homestead (Almondbury Ward). This will confirm adequate funds from the agreed Adult Social Care Capital Allocation to meet the revised anticipated costs following detailed feasibility and also approve the move to tender.
Relocation plans are currently in place to vacate both sites by the Autumn 2021 to allow intrusive surveys pending demolition.
Amendments to the budget allocations will then be included in Quartile 2 report to Cabinet.
2. Information required to take a decision
2.1As part of the Council’s capital programme Adult Services have an agreed capital budget of £25.4m (£22.470m for Day Care Support for Vulnerable Adults and £2.913m for One Off Projects)
2.2This report relates to 2 schemes within the programme namely the re-provision of the council’s two existing 25 place Dementia Day facilities at Knowl Park House, Mirfield, and the Homestead, Almondbury.
2.3The initial outline business case for reprovision of day services buildings was approved at Cabinet in January 2019 and was included in the Strategic Priorities Capital Budget (Independent theme).
2.4At that time of the initial bid indicative capital estimates of £5m for Knowl Park House (including a centre of excellence facility) and £3m for the Homestead were set aside. Both outline estimates were exclusive of furniture replacement and capitalised salaries relating to the service capital team.
2.5A report was approved at Cabinet on 29th June 2020 to appoint Lead Consultant Architects for both schemes. Following a tendering exercise Frank Shaw Associates were appointed and detailed feasibility has now been completed for both schemes.
2.6The detailed feasibilities have identified costs will exceed their nominal original allocations. Knowl Park House is now estimated at around £6.3m and The Homestead at £4.7m. These increases are mainly due to:
significant rises in construction materials associated with Covid and Brexit increased transport costs an increase in the building footprints to ensure best practice design and learning from Covid the absorption of demolition costs increases in Architecture fees due to the increased size of the buildings unforeseen issues relating to necessary groundworks the cost of enabling works to the premises required for temporary decant.
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
PDF |
Adult Social Care Capital Programme: Knowl Park House and The Homestead Capital SchemesReport | 6 pages | DownloadRead as text |
Follow Cabinet at Kirklees and we tell you when its next papers are published, before the meeting rather than after it.
| Meeting | Decision | Outcome | |
|---|---|---|---|
| 3 Nov 2026 | 8RESOLVED – 1) That the outcome of the Regulator of Social Housing inspection be noted. 2) That the Regulatory Improve... | Noted | Open |
| 3 Nov 2026 | 10RESOLVED – 1) That the rent and service charge policy be approved. 2) That authority be granted to the Executive Dire... | Approved | Open |
| 3 Nov 2026 | 12RESOLVED – 1) That approval be given to the Kirklees Employment Skills Framework 2026-2030 as the district-wide strat... | Approved | Open |
| 6 Oct 2026 | 8RESOLVED – That the report be referred to the Meeting of Council on 21 October 2026 with the recommendations that Cou... | Noted | Open |
| 6 Oct 2026 | 9RESOLVED 1) That approval be given to the disposal of the land and property within the Capital Receipts Schedule Octo... | Approved | Open |
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Keeps you signed in and runs your free-paper allowance. Always on.
Counts visits and which pages are used. First-party only, no advertising, never shared.