Resolved
Delegate to the Head of Planning and Development to approve as detailed in the considered report and the planning update.
Strategic Planning Committee approved this item on Thursday 24 February 2022. Below is the council's own wording, with the papers it was decided on.
Resolved
Delegate to the Head of Planning and Development to approve as detailed in the considered report and the planning update.
Originator: RichardA Gilbert
Tel: 01484 221000
Report of the Head of Planning and Development
STRATEGIC PLANNING COMMITTEE
Date: 24-Feb-2022
Subject: Planning Application 2021/94337 Erection of construction facility to facilitate the construction works for the section of the TRU between Huddersfield and Westtown (Dewsbury), provision of strategic construction compound including open storage, trackworks and overhead line equipment (OLE) assembly and associated welfare facilities, construction of a retaining wall, environmental mitigation measures (noise attenuation) and provision of temporary platform for use during works at Huddersfield Station with associated access, utilities/drainage works Operational railway land, Hillhouses Yard, Alder Street, Huddersfield
APPLICANT Tony Rivero, Network Rail
DATE VALID TARGET DATE EXTENSION EXPIRY DATE 16-Nov-2021 15-Feb-2022
Please click the following link for guidance notes on public speaking at planning committees, including how to pre-register your intention to speak. link to public speaking at committee
LOCATION PLAN
Map not to scale – for identification purposes only Electoral wards affected: Greenhead and Ashbrow
Ward Councillors consulted: Yes
Public or private: Public
DELEGATE approval of the application and the issuing of the decision notice to the Head of Planning and Development in order to complete the list of conditions including those contained within this report subject to removal of the objection from Yorkshire Water.
In the event that the objection from Yorkshire Water is not removed within 3 months of the date of the Committee’s resolution, then the Head of Planning and Development shall consider whether permission should be refused on these grounds; if so, the Head of Planning and Development is authorised to determine the application and impose appropriate reasons for refusal under Delegated Powers.
1.00INTRODUCTION:
1.01This is an application seeking full planning permission for erection of a construction facility to facilitate the construction works for the section of the TRU between Huddersfield and Westtown (Dewsbury). The proposed development is to include provision of a strategic construction compound constituted of open storage, trackworks and overhead line equipment (OLE – electrification cables and gantries) assembly and associated welfare facilities, as well as the construction of a retaining wall, environmental mitigation measures (noise attenuation) and provision of temporary platform for use during works at Huddersfield Station with associated access, utilities/drainage works.
1.02A Transport and Works Act Order (TWAO) for the Huddersfield and Westtown (Dewsbury) section of the TRU was submitted to the Secretary of State for Transport on 31 March 2021 (The Network Rail (Huddersfield to Westtown (Dewsbury) Improvements) Order). The TWAO was subject to a Public Inquiry between November and December 2021 and the Secretary of State’s decision is now awaited. The planned upgrade of the railway between Huddersfield and Westtown (Dewsbury) is key to delivering passenger benefits along the Trans- Pennine railway.
1.03The development of the former railway sidings at Hillhouse railway yard into a construction facility for the TRU is included within the Order application. However, in advance of The Network Rail (Huddersfield to Westtown (Dewsbury) Improvements) Order being determined, Network Rail (NR) is submitting a standalone planning application under the Town and Country Planning Act 1990 to facilitate the use of the Hillhouse Construction Compound site as advanced works to the Order.
1.04The application is presented to the Strategic Planning Committee as the proposed development is a large-scale major application with a site area in excess 0.5HA whilst also interpreted as being under the definition of ‘major infrastructure’. 2.00 SITE, SURROUNDINGS & CONTEXT:
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
PDF |
Planning Application: Application No: 2021/94337Report | 446 KB | DownloadRead as text |
Follow Strategic Planning Committee at Kirklees and we tell you when its next papers are published, before the meeting rather than after it.
| Meeting | Decision | Outcome | |
|---|---|---|---|
| 8 Oct 2026 | Planning Application - Application No: Planning Application 2021/93621Application approved (delegated). | Approved | Open |
| 23 Jul 2026 | Planning Application - Application No: 2025/92713Application approved (delegated). | Approved | Open |
| 11 Jun 2026 | Minutes of the Previous MeetingRESOLVED – The Minutes of the meeting held on 2 April 2026 be considered at the next meeting for approval. | Approved | Open |
| 11 Jun 2026 | Planning Application - Application No: 2025/92713Deferred. | Deferred | Open |
| 11 Jun 2026 | Planning Application - Application No: 2023/91907Approval delegated. | Approved | Open |
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Keeps you signed in and runs your free-paper allowance. Always on.
Counts visits and which pages are used. First-party only, no advertising, never shared.