Resolved
RESOLVED – 1) That the Board thank [name removed] for his presentation. 2) That the Board note the progress on current and future projects.
Dewsbury Neighbourhood Board noted this item on Thursday 30 June 2022. Below is the council's own wording, with the papers it was decided on.
Resolved
RESOLVED – 1) That the Board thank [name removed] for his presentation. 2) That the Board note the progress on current and future projects.
May slip/ May slip slipped with Complete On track non material material impact
Overall Project update (May 2022) – Dewsbury Revival Grant Scheme RAG Amber
PROJECT STATUS: Delivering Year 1 – 1st Grant Year 2 – Scheme Year 3 – 5 grants Year 4 – 5 grants Year 5 – 5 grants Year 6 – 3 grants Greenwoods Covid Hit due to complete target to complete target to complete target to complete completes
20 – 21 21 - 22 22 - 23 23 - 24 24 - 25 25 - 26 Summary Key risks and mitigation The Dewsbury Revival Grant Scheme ‘DRGS’ – follows • Lack of owner / tenant engagement • Progress 3 active applications: on from the successful Heritage Lottery / Council • Increased costs - former Principal - Northgate funded Townscape Heritage Initiative (THI) and aims to • Private Contribution becomes unaffordable - 6-10 Westgate (Synergy Solicitors) halt and reverse the decline of heritage assets, through • Decline of local property market - Popps – Northgate promoting the quality of its environment to encourage • Lack of staff resources investment and growth. • Lack of local conservation skills Develop 5 current enquiries: Timescale/Programme • Unexpected additional works during delivery - Former Coral Unit – Crackenedge Lane Start on site 2021, - Wesco – 22 Westgate Completion 2026 Any issues to report: - Kingsway Chambers – Kingsway Arcade • The scheme currently has a good level of enquiries in the - The former registry office pipeline, including current applications. However, additional - The Old post office Budget/Funding staff resource will be required in order to deliver the projects £6.4m - TF £3.15, Kirklees Council £1.25m, Private £2m effectively and within timescale.
Outputs (MHCLG KPIs) Activities completed last six months period & underway 16 Shop fronts improved • 1 grant completed – Greenwoods 36 Residential Units / 3,781 m2 • Currently on site with 2 Grants – Cocoa Lounge and 14 Commercial units / 1,124 m2 Homeworld Item Last Current Trend period period - 2 Derelict buildings refurbishment 15 Heritage buildings restoration Activities due next six months Programme Amber Green • Approve 3 pending grants: Resourcing Red Amber - Northgate House – Angus Showrooms Dependencies: - 23 Foundry Street – Kashmir Travel Stakeholders Green Green
Dewsbury Town Investment Plan - Creative Craft Centre – Union Street Outputs Amber Green Private Sector contribution OVERALL Amber Green Planning Permissions
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
PDF |
Update on the Building Revival Scheme 5:45pm: 6:00pmReport | 120 KB | DownloadRead as text |
Follow Dewsbury Neighbourhood Board at Kirklees and we tell you when its next papers are published, before the meeting rather than after it.
| Meeting | Decision | Outcome | |
|---|---|---|---|
| 18 Jun 2026 | Membership of Dewsbury Neighbourhood BoardRESOLVED - David Wildman, Service Director for Skills and Regeneration at Kirklees Council, was appointed to the Boar... | Decided | Open |
| 18 Jun 2026 | Declaration of InterestsSophie Johnson, Peter Mason, Fara Butt, Andi Eccles, Jackie Ramsay and Martin Walsh, declared an interest as sharehol... | Decided | Open |
| 18 Jun 2026 | Minutes of Previous Meeting and Action TrackerRESOLVED - 1) That the minutes of the meeting held on 12 th February 2026 be approved as a correct record. 2) That th... | Approved | Open |
| 18 Jun 2026 | Chair's UpdateRESOLVED – That the Chair’s Update be noted. | Noted | Open |
| 18 Jun 2026 | Terms of ReferenceRESOLVED – That the updated for Dewsbury Neighbourhood Board be approved. | Approved | Open |
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Keeps you signed in and runs your free-paper allowance. Always on.
Counts visits and which pages are used. First-party only, no advertising, never shared.