RESOLVED – 1) That approval be given for the virement of £2 million Heritage Action Zone Capital funding from the George Hotel to the Estate Buildings. 2) That delegated authority be given to the Strategic Director of Growth and Regeneration in conjunction with the Service Director for Finance, Section 151 Officer, to apportion further funds if required up to 25% over the pre-tender estimate of £3.5 million.
Word for word from the decision Kirklees published for this meeting.Source: democracy.kirklees.gov.uk
1.1The Council’s Capital programme includes £11,345,000 for the delivery of Kirklees’ Heritage Action Zone (HAZ) programme. This includes £1,920,000 from Historic England, and £7.95 million from the Council capital programme. Kirklees Council secured an added £1.365 million from the Getting Building Fund for development of the George Hotel.
1.2The Council directed £7.5 million of HAZ funding to the George Hotel, and £3.85 million to the Estate Buildings. Phase one works, the focus of the HAZ programme, deliver essential repairs and restoration of heritage features to make the buildings safe, watertight, and investment ready. Phase two for the George is the construction of a new Hotel. Phase two for the Estate Buildings is residential.
1.3Work on phase one of the George is underway, and once completed, total expenditure will be £5.4 million, leaving a surplus of £2,016,000. Following completion of all survey works, the projected costs of delivery of phase one for the Estate Buildings is £5.556 million. Set against a capital allocation of £3.85 million, there is a potential budget shortfall of £2 million. This discrepancy arises because:
The extent of damage to the building is far greater than expected. Construction costs across the sector have escalated and continue to rise in a contracted market. A limited pool of available contractors with the correct skills. Projected costs are pre-tender estimates and include high contingencies. The Council distributed funding to the two projects based on high-level surveys, since clarified.
1.4This report sets out a way to deliver both projects within the existing HAZ budget, and HAZ programme timescale. The report recommends Cabinet vires approved funding within the HAZ programme, from the George Hotel to the Estate Buildings, to enable completion of essential remedial works for both buildings.
2. Information required to take a decision
Background
2.1.1.The Grade two Listed Estate Buildings, owned by Kirklees Council, include 52,000 sq. ft. of space. Positioned in the commercial centre of Huddersfield directly opposite Huddersfield Railway Station and next to St. George's Square, Estate buildings are only a short walk to a wide range of independent and larger multiple retailers and the University of Huddersfield campus.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.