Approved Executive 1 paper

Cabinet approved this item on Thursday 21 December 2023. Below is the council's own wording, with the papers it was decided on.

Item9:

Resolved

RESOLVED – 1) That approval be given to providing a HLRS grant to B&M Properties of £610.5k towards replacement shop fronts to 19-33a John William Street, as detailed within the report and Appendix 1 (exempt), and that Officers publish details of the subsidy on the national transparency database. 2) That authority be delegated to the Strategic Director (Growth and Regeneration) in conjunction with the Service Director (Legal, Governance and Commissioning) to agree and complete the grant agreement and other documentation necessary to enable the project to proceed and that the Service Director (Legal, Governance and Commissioning) be authorised to enter into the aforementioned documentation on behalf of the Council. 3) That, in the event that costs change, authority be delegated to the Strategic Director (Growth and Regeneration) in consultation with the Cabinet Member (Finance and Regeneration) the ability to vary the amount of grant subject to the funds being found from within existing grant scheme resources.
Word for word from the decision Kirklees published for this meeting. Source: democracy.kirklees.gov.uk

Follow this further

Built from Kirklees's papers

What the report saysPro

Report to Cabinet, 21 pages

Purpose of report

To agree grant support from the Huddersfield Heritage Led Regeneration Grant Scheme for properties at 19-33a John William Street, Huddersfield.

Key Decision - Is it likely to result in Yes spending or saving £500k or more, or to have a significant effect on two or more electoral wards? Key Decision - Is it in the Council’s Forward Yes Plan (key decisions and private reports?) The Decision - Is it eligible for call in by Yes Scrutiny?

Date signed off by Strategic Director & David Shepherd Yes 28th November 2023 name

Is it also signed off by the Service Director Yes for Finance?

Is it also signed off by the Service Director Yes for Legal Governance and Commissioning? Cabinet member portfolio Cllr Graham Turner Regeneration Portfolio Holder

Electoral wards affected: Newsome Ward councillors consulted: Cllrs Cooper, Allison and Lee-Richards

Public report with private Appendices (Appendices 1 and 2) .

(Have you considered GDPR?) Yes.

Public with private appendix 6 in accordance with Schedule 12A Local Government Act 1972, as amended by the Local Government (Access to Information) (Variation) Order 2006 namely it contains information relating to the financial and business affairs of third parties (including the Authority holding that information). It is considered that the disclosure of the information would adversely prejudice those third parties’ commercial interests including the Authority and therefore the public interest in maintaining the exemption, which would protect the rights of an individual or the Authority, outweighs the public interest in disclosing the information and providing greater openness and transparency in relation to public expenditure in the Authority’s decision making. 1. Summary

1.1The freeholder, B&M Properties, of this terrace are seeking grant support of £610.5K for 19 to 33a John William Street from the Huddersfield Heritage Led Regeneration Scheme (HLRS), a capital grant scheme, which seeks to improve shop fronts, including building frontages, and provide new uses for empty properties within the Huddersfield Town Centre Conservation Area. The HLRS is funded from the original £1.2m allocation from the Capital Plan and offers grants of up to 80% of the cost of repair and refurbishment and 100% of the costs for professional services such as an architect and structural engineers.

1.219 to 33a John William Street is a terrace of 3 storey stone fronted buildings situated on John William Street opposite the junction with Church Street. The upper two floors have been converted into residential with the ground floor having retail units, comprising of hot food takeaways, newsagents and grocery stores. The existing shop fronts are of poor quality, modern in design and are not felt appropriate for these historic buildings.

1.3The buildings are listed Grade 2 by the Secretary of State due to their significant architectural and historic interest. The buildings occupy a prominent position within the Huddersfield Town Centre Conservation Area, is within the Huddersfield High Street Heritage Action Zone (HSHAZ) and the Heritage Led Regeneration (HLRS) priority Area. The buildings occupy a key location within the town centre due to the use of John Willliam Street.

Background

1.4The HLRS, which was approved by Cabinet in February 2019, is aiding the regeneration of the town centre by improving the historic buildings and creating new uses for empty properties thereby improving Huddersfield as a place to visit, shop and live. The scheme has now been running since April 2019 but due to the impact of Covid the scheme struggled to attract applicants. However, applicants are now coming forward so much so that the allocation of £1.2m has now been either paid to successful schemes or committed to schemes that will be underway shortly.

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
19-33a John William Street, Huddersfield: Huddersfield Heritage Led Regeneration Grant Scheme (HLR) Grant offerReport 21 pages DownloadRead as text

At this meeting

Whole meeting

More from Kirklees Cabinet

All decisions
MeetingDecisionOutcome
3 Nov 2026 8RESOLVED – 1) That the outcome of the Regulator of Social Housing inspection be noted. 2) That the Regulatory Improve... Noted Open
3 Nov 2026 10RESOLVED – 1) That the rent and service charge policy be approved. 2) That authority be granted to the Executive Dire... Approved Open
3 Nov 2026 12RESOLVED – 1) That approval be given to the Kirklees Employment Skills Framework 2026-2030 as the district-wide strat... Approved Open
6 Oct 2026 8RESOLVED – That the report be referred to the Meeting of Council on 21 October 2026 with the recommendations that Cou... Noted Open
6 Oct 2026 9RESOLVED 1) That approval be given to the disposal of the land and property within the Capital Receipts Schedule Octo... Approved Open