RESOLVED – 1) That in relation to the interim arrangements, they be extended for a further three years with the contract expiry to be reprofiled to March 2028 under the Heads of Terms agreement with Suez and that a deed of variation be developed. 2) That approval be given to the revised procurement strategy based on a fully integrated contract to include household waste recycling centres. 3) That in Autumn 2026 further consideration be given to a full business case to approve the appointment of the preferred contractor prior to the commencement of a new contract. 4) That authority be delegated to the Strategic Director Growth and Regeneration, Service Director Legal Governance and Commissioning and Service Director for Finance to: - (i) Sign off and implement the required contract deed of variation and draw down the approved Capital and Revenue expenditure for extending the interim arrangements. (ii) Commence a procurement process from December 2024 and to draw down the approved Capital and Revenue expenditure. (iii) Take a decision following a further review to identify if efficiency opportunities could be made by mothballing the Kirklees Materials Recovery Facility and using a third party facility and/or changes to household waste recycling centre services. (iv) Sign off and implement the required Deed of Variation to cover the Network Raise Infrastructure Limited replacement of the Weaving Lane Household Waste Recycling Centre.
Word for word from the decision Kirklees published for this meeting.Source: democracy.kirklees.gov.uk
1. Information on Policy Changes and Project Dependencies To provide information on the significant number of matters that have arisen since publishing the waste disposal procurement outline business case (OBC) in 2022. The affect they have had on identifying future requirements and decision making, has resulted in a need to extend the existing interim contract arrangements by a further 3 years.
2. Update on the Waste Disposal Contract Procurement Strategy To provide an update on the progress made on preparations for expiry of the current Waste PFI contract and development of the procurement strategy for the future Operation and Maintenance (O&M) of the Council’s waste infrastructure. This includes the Energy from Waste Facility (EfW), Materials Recovery Facility (MRF), 2 Waste Transfer Stations (WTS) and the Household Waste Recycling Centres (HWRC).
3. Decision on Officer Recommendations Several officer recommended options are proposed for Cabinet approval, including areas of the (OBC) that required further analysis to confirm the final structure of the future waste contract, identifying the infrastructure and investment required to implement, and deliver the required changes to statutory waste services.
Cabinet are asked to approve the revised procurement strategy timeline that extends the expiry date of the current contract by 3 years, and continues the existing interim arrangements to prepare for the new contract.
Approval is also sought for a future delegated officer decision to progress with any potential further efficiency opportunities, such as HWRC and MRF operations, and the Network Rail Infrastructure Limited (NRIL) replacement of the Weaving Lane HWRC. Recommendations
Extension of the Existing Interim Arrangements
The current interim arrangements are extended for a further 3 years and the contract expiry is reprofiled to March 2028 under the Heads of Terms agreement with Suez and a deed of variation (DoV2) is developed.
Procurement Strategy
1 The revised procurement Strategy is approved based on the recommended option of a fully integrated contract including HWRCs.
A full business case is presented to Cabinet in Autumn 2026 to approve the appointment of the preferred contractor prior to commencement of the new contract.
Delegated Authority
Delegated authority is given to the Strategic Director (Growth & Regeneration), and Service Director for Legal, Governance and Commissioning and Service Director for Finance to:
Sign off and implement the required contract deed of variation (DoV2) and draw down the approved Capital and Revenue expenditure for extending the interim arrangements.
Commence a procurement process from December 2024 and to draw down the approved Capital and Revenue expenditure.
Take a decision following a further review to identify if efficiency opportunities can be made by mothballing the Kirklees MRF and using a 3rd party facility and/or changes to HWRC services.
Sign off and implement the required Deed of Variation to cover the NRIL replacement of the Weaving Lane HWRC.
Reasons for recommendations
The officers’ recommendations are in order to achieve value for money, align the current contract with the Council’s and national strategy and allow critical time to prepare for the re- procurement of the waste disposal services.
Resource Implications:
Internal requirements of a waste programme office and technical team, and support from: procurement; legal; finance and external advisors for: legal, technical and financial issues.
Date signed off by Strategic Director & David Shepherd, Strategic Director, (Growth name & Regeneration) – 15/03/2024
Is it also signed off by the Service Isabel Brittain, Service Director - Finance Director for Finance? (S151 Officer) – 27/03/2024
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.