Resolved
RESOLVED- That the District Heating – Request for Officer Attendance be noted.
Corporate Governance and Audit Committee noted this item on Friday 27 September 2024. Below is the council's own wording, with the papers it was decided on.
Resolved
RESOLVED- That the District Heating – Request for Officer Attendance be noted.
The findings of the internal audit into the district heating schemes published in June 2024, has accelerated the work we are doing to resolve the historic issues relating to our district heating schemes and has highlighted some important priority areas that we are addressing with urgency.
We have responded proactively to the audit findings by forming an internal project group, creating an action plan to address each area of concern, and maintaining oversight at a senior level of the progress being made.
This audit followed a previous internal audit review of the district heating schemes which was undertaken in October 2019 which highlighted several weaknesses: The scheme not achieving break- even, the need to prepare to renew the contract for support services and the management of the vulnerability criteria. These have not been addressed due to there being no inhouse technical capabilities to develop and manage an energy strategy that would inform the decisions around heat networks in Kirklees.
In accordance with the 2023/24 Internal Audit Plan, a review of the processes around District Heating Schemes across the Homes and Neighbourhoods housing stock was undertaken in March/April 2024, followed by a report published in June 2024.
The scope of the audit was to review and evaluate the systems and procedures in place to ascertain whether they are sufficiently robust in relation to overall arrangements for District Heating Schemes. Audit testing identified that the processes surrounding the District Heating Schemes have significantly broken down in relation to some key controls.
District heating, also known as a heat network, is a system that uses a singular central heat source to distribute hot water through a network of insulated pipes to multiple individual dwellings. The structure is usually used to fulfil heating and hot water requirements in apartment complexes.
The current provider provides the end-to-end heat management service. This contract expired in January 2023. Therefore, Kirklees is currently out of contact, however an exemption to continue to use the current provider until 31st December 2024 was granted by the Strategic Director of Homes and Neighbourhoods and the Head of Procurement.
The current Contract requires consideration for a further 12-month extension, due to the requirement of an Energy Strategy that will include our heat networks. Linking in the boiler improvement programme, reaching our net zero targets across Homes and Neighbourhoods and understand the impact of the current district heating renewal programme. To achieve this, we need to procure a technical specialist to write the specifications for the metering and billing contract and the completion of the procurement for a new supplier of heat meters and a contract with a billing provider.
The contract for the PV dashboard has also expired and the above procurement will include the provision of a new provider.
Kirklees residents that use district heating have a pre-payment meter provided by the current provider who also collect the income from the meters. For the 2023/24 financial year, the expenditure was approximately £787K against income of approximately £191k. This represents a shortfall of £596k (in 2022/23 the shortfall was approximately £1m) this is currently being subsidised from the HRA.
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
PDF |
2. District Heating -PublicReport | 6 pages | DownloadRead as text |
PDF |
District Heating: Request for Officer attendanceReport | 4 pages | Download |
Follow Corporate Governance and Audit Committee at Kirklees and we tell you when its next papers are published, before the meeting rather than after it.
| Meeting | Decision | Outcome | |
|---|---|---|---|
| 9 Oct 2026 | Minutes of Previous MeetingRESOLVED – That the Minutes of the meeting held on 25 th September 2026 be approved as a correct record. | Approved | Open |
| 9 Oct 2026 | National Scheme of Delegation - PlanningRESOLVED- 1) That the committee recommends to Council to: i) Note the introduction of the Town and Country Planning (... | Noted | Open |
| 25 Sep 2026 | Minutes of Previous MeetingRESOLVED – That the Minutes of the meeting held on 7 th August 2026 be approved as a correct record. | Approved | Open |
| 25 Sep 2026 | Annual Report on Bad Debt Write-offs 2025/26RESOLVED- That the Annual Report on Bad Debt Write Off’s 2025/26 be noted. | Noted | Open |
| 25 Sep 2026 | Information Governance Annual Report 2025/26RESOLVED – That the Information Governance Annual Report 2025/26 be noted. | Noted | Open |
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Keeps you signed in and runs your free-paper allowance. Always on.
Counts visits and which pages are used. First-party only, no advertising, never shared.