Cabinet, Tuesday 21 January 2025 at 1.30pm

8

Approved Executive 6 papers

Cabinet approved this item on Tuesday 21 January 2025. Below is the council's own wording, with the papers it was decided on.

Item8:

Resolved

RESOLVED - 1) That in regard to the Combined Museum & Gallery, Phase 2 RIBA 3, authority be delegated to the Executive Director of Place in consultation with the Leader and the Portfolio Holder for Finance & Regeneration to approve the Royal Institute of British Architects stage 3 design (RIBA 3) for the museum and gallery. 2) That in regard to the Combined Museum & Gallery, Phase 2 Gateway 4 Budget, the museum and gallery construction budget be noted and funding to progress from this Gateway 3 to Phase 2 Gateway 4 be approved. 3) That in regard to the Construction Partner, Phase 2, Pre Construction Services Agreement (PCSA) authority be delegated to the Executive Director of Place in consultation with the Portfolio Holder for Finance & Regeneration, the Director of Legal Governance & Commissioning, the Service Director Finance and the Head of Procurement to make the decision to enter into the Pre-PCSA, and subsequently award the PCSA and instruct any surveys and enabling works that may be necessary prior to the contract sum being agreed subject to compliance with Contract Procedure Rules. 4) That in regard to SDP, Architect and Engineer Services, Phase 2 Gateway 3 to Gateway 4, subject to agreement on fees, compliance with the procurement process and Contract Procedure Rules, approval be given to continue the services being provided by the Client delivery team (SDP, architect and the engineer) to progress from this Gateway 3 to Phase 2 to Gateway 4. 5) That in regard to Construction Capital Development Council Resources approval be given to the allocation of necessary council staff and resources to support the construction programme and it be noted that, in the absence of sufficient internal resources, additional external resources will be sourced from the existing appointments and/or from existing/future framework agreements, subject to compliance with procurement process and the Contract Procedure Rules. 6) That in regard to the Construction Budget, Phase 1 Gateway 5, Phase 2 Gateway 4 & Master Plan Allowances, approval be given to the further drawdown of £5.663m (Phase 2, £5.413m & Master Plan, £250k) thereby increasing the committed funding for the programme from £73.329m to £78.992m. 7) That in regard to the reallocation of budget to the Combined Museum and Gallery Service Pre-opening Capital Costs, approval be given, subject to no other sources of funding being available, the reallocation of funding from the Our Cultural Heart construction budget future phases to fund the museum and gallery pre-opening capital costs including the fit out of the building. 8) That in regard to the reallocation of budget to operational services, approval be given, subject to no other sources of funding being available, the reallocation of funding from the Our Cultural Heart construction budget future phases to fund the West Yorkshire Archive Service (£371k) and the Events team (£50k) pre-opening capital costs. 9) That authority be delegated to the Executive Director of Place, in consultation with the Portfolio Holder for Finance & Regeneration, the Service Director for Culture and Visitor Economy and the Service Director Finance to explore ways ... :
Word for word from the decision Kirklees published for this meeting. Source: democracy.kirklees.gov.uk

Follow this further

Built from Kirklees's papers

What the report saysPro

Report to Cabinet, 21 pages

Purpose of report

The purpose of this report is to seek approval and delegations to progress the design and pre-construction works for Phase 2 (combined museum & art gallery, public realm and basement) from Gateway 3 to Gateway 4.

There is also an update on Phase 1 (library, food hall, events square/public realm and basement) now that construction has started on site, and an overview of the remaining phases within the rest of the master plan.

With regard to the Capital Development Budget for design and construction (construction budget) of £262m allocated in the councils capital plan the report outlines reallocation of some of this budget.

In addition to the construction activity there is an early update on the budgets for pre and post-opening costs being developed by the councils operational and support services involved in preparing for the opening of, and ongoing operation of the facilities within Our Cultural Heart. These costs will continue to be reviewed and refined as update reports are brought to Cabinet.

The programme has previously been considered by the Cabinet on five separate occasions with the last report being in December 2023 (Phase 1 Gateway 4). Similarly, the programme has been the subject of consideration at the Growth and Regeneration Scrutiny Panel on several occasions, with the last report being considered in September 2024. Members of the Scrutiny Panel also attended a site visit on Monday the 4th November 2024.

The previous approved Cabinets reports are available through the links in Section 8 of this report. Recommendations:

1. Combined Museum & Gallery, Phase 2 RIBA 3 To delegate authority to the Executive Director of Place in consultation with the Leader and the Portfolio Holder for Finance & Regeneration to approve the Royal Institute of British Architects stage 3 design (RIBA 3) for the museum and gallery.

1 2. Combined Museum & Gallery, Phase 2 Gateway 4 Budget To note the museum and gallery construction budget and to agree to approve the funding to progress from this Gateway 3 to Phase 2 Gateway 4.

3. Construction Partner, Phase 2, Pre Construction Services Agreement (PCSA) To agree to delegate authority to the Executive Director of Place in consultation with the Portfolio Holder for Finance & Regeneration, the Director of Legal Governance & Commissioning, the Service Director Finance and the Head of Procurement to make the decision to enter into the Pre-PCSA and subsequently award the PCSA and instruct any surveys and enabling works that may be necessary prior to the contract sum being agreed subject to compliance with Contract Procedure Rules.

4. SDP, Architect and Engineer Services, Phase 2 Gateway 3 to Gateway 4 Subject to agreement on fees and in line with our procurement process and Contract Procedure Rules to agree to continue the services being provided by the Client delivery team (SDP, architect and the engineer) to progress from this Gateway 3 to Phase 2 to Gateway 4. The same delivery team is providing the necessary services on Phase 1 and the rest of the master plan.

5. Construction Capital Development Council Resources To allocate the necessary council staff and resources to support the construction programme and to note that in the absence of sufficient internal resources that additional external resources will be sourced from the existing appointments and/or from existing/future framework agreements subject to compliance with procurement process and the Contract Procedure Rules.

6. Construction Budget, Phase 1 Gateway 5, Phase 2 Gateway 4 & Master Plan Allowances To approve subject to approval of the recommendations above the further drawdown of £5.663m (Phase 2, £5.413m & Master Plan, £250k) thereby increasing the committed funding for the programme from £73.329m to £78.992m.

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
App 1. Phase 1 red line boundary plan (public) :Appendix 1 pages Download
PDF
App 3. Phase 1 Services Additional Budgets (public) :Appendix 1 pages Download
PDF
App 4. Phase 2 red line boundary plan (public) :Appendix 1 pages Download
PDF
App 5. Phase 2 Summary of RIBA 3 Design Report (public) :Appendix 13 pages Download
PDF
App 8. Phase 2 Service Additional Budget (public) :Appendix 1 pages Download
PDF
Our Cultural Heart, part of the Huddersfield Blueprint: Phase 2 Gateway 3Report 21 pages DownloadRead as text

At this meeting

Whole meeting

More from Kirklees Cabinet

All decisions
MeetingDecisionOutcome
3 Nov 2026 8RESOLVED – 1) That the outcome of the Regulator of Social Housing inspection be noted. 2) That the Regulatory Improve... Noted Open
3 Nov 2026 10RESOLVED – 1) That the rent and service charge policy be approved. 2) That authority be granted to the Executive Dire... Approved Open
3 Nov 2026 12RESOLVED – 1) That approval be given to the Kirklees Employment Skills Framework 2026-2030 as the district-wide strat... Approved Open
6 Oct 2026 8RESOLVED – That the report be referred to the Meeting of Council on 21 October 2026 with the recommendations that Cou... Noted Open
6 Oct 2026 9RESOLVED 1) That approval be given to the disposal of the land and property within the Capital Receipts Schedule Octo... Approved Open