CouncilMonitor
194 principal councils 228,996 meetings since 2000 2.8 million official papers archived Straight from each council's own publication system
Kirklees Council
Dewsbury Neighbourhood Board, Thursday 12 February 2026 at 4.00pm

Pride in Place Update

Noted Committee 1 paper

AI summaryDewsbury Neighbourhood Board notes Pride in Place update as MHCLG approval of the 10-year Regeneration Plan is awaited by end of February 2026, with four working groups to lead the next phase.

AI summaryIn plain English

Written from the decision and the officer reportPDF Pro
OutcomeNotedBoard noted progress on Regeneration Plan submission and Working Groups
Money£20 million over ten yearsDewsbury's share of Long-term Plan for Towns funding
What happens nextFinal MHCLG approval expected end of February 2026. Funding release anticipated April 2026
Who it affectsDewsbury residents and businessesCommunity-led regeneration via four thematic working groups

What was decided

The Board noted the progress on the Regeneration Plan submission, the establishment of Working Groups as core delivery mechanisms, and that Board member participation will be required to support and lead these workstreams. Report P3

Why

The Pride in Place programme needs to remain community led, with refreshed Working Groups shaping the next phase of detailed intervention design, delivery plans and success measures, consistent with the 4-year Investment Plan. Report P17, P18

The programme evolved from the 2023 Long-term Plan for Towns, was rebranded as the Plan for Neighbourhoods in March 2025 and now sits within MHCLG's Pride in Place Strategy introduced in September 2025. Report P7, P8

What happens next

A final MHCLG approval decision on the submitted Regeneration Plan is expected by the end of February 2026, with funding anticipated to be released in April 2026 so project activity can begin. Report P12, P14

Four Working Groups (Safety and Security, Place, Creativity and Cultural Events / Creative Economy, and Business Support) will be chaired by Board members and supported by stakeholders to design interventions, KPIs and success measures. Report 3.3, 3.4, 3.5, 3.6, P19

A risk and opportunity register will be actively managed, with an Integrated Impact Assessment to be undertaken during project development if required. Report P36

The money

  • £20 million over ten years Dewsbury's funding allocation under the Long-term Plan for Towns, rebranded as the Plan for Neighbourhoods and now part of MHCLG's Pride in Place Strategy Report P7, P8

Options considered

  • Rejected: No alternative options considered. The report states that options are not applicable for this update item Report P40

Implications

  • Other: Continued engagement is planned with communities including groups identified as harder to reach such as young people, businesses and South Asian communities. Report P27, P38
  • Climate: Interventions brought forward within the Plan will consider how they can help to tackle the climate emergency, reduce emissions and improve air quality. Report P32
  • Risk: A risk and opportunity register will be actively managed to mitigate potential risks on the programme. Report P36
  • Other: The Plan is intended to help improve outcomes for children and create a long-lasting legacy for future generations. Report P34
  • Equalities: An Integrated Impact Assessment will be undertaken during the development of projects if required. Report P36

Who and where

  • Dewsbury residents, including young people and South Asian communities identified as harder to reach Report P27
  • Local businesses in Dewsbury, to be supported via the Business Support Working Group Report 3.6
  • Neighbourhood Board members, who are expected to chair and lead the four Working Groups Report P19, 3.3, 3.4, 3.5, 3.6
  • Cultural and creative sector organisations in Dewsbury, via the Creativity and Cultural Events / Creative Economy Working Group Report 3.5

Timeline

  • September 2023: UK government launched the Long-term Plan for Towns, naming Dewsbury as a recipient of £20 million over ten years Report P7
  • March 2025: The programme was rebranded as the Plan for Neighbourhoods (PfN) with updated guidance issued Report P8
  • April 2025: Dewsbury Town Board evolved into the Neighbourhood Board Report P8
  • 1 May 2025: Previous Dewsbury Town Board meeting (background paper for this item) Report P42, P43
  • September 2025: MHCLG introduced its Pride in Place Strategy, within which this programme now sits Report P8
  • 27 November 2025: Dewsbury's Regeneration Plan was formally submitted to MHCLG following Board approval Report P11
  • Early January 2026: Officers received a clarification request from MHCLG; all requested information was submitted promptly Report P12
  • End of February 2026: Final approval outcome on the Regeneration Plan is expected from MHCLG Report P12
  • 12 February 2026: Dewsbury Neighbourhood Board meeting at which this update was noted
  • April 2026: Funding is anticipated to be released so that project activity can commence Report P14

Plain English for the jargon

  • MHCLG: Ministry of Housing, Communities and Local Government, the UK government department overseeing the Pride in Place programme
  • Pride in Place Strategy: A UK government strategy introduced in September 2025 within which the Plan for Neighbourhoods programme for Dewsbury now sits
  • Plan for Neighbourhoods (PfN): The rebranded name from March 2025 for the previous Long-term Plan for Towns programme covering Dewsbury
  • Neighbourhood Board: The body that evolved from the Dewsbury Town Board in April 2025, responsible for overseeing community-led regeneration in Dewsbury
  • KPI: Key Performance Indicator, a measurable value used to assess the success of an intervention or project
What was decided, why, and what happens next

Pro reads every officer report for you and explains each decision in plain English: the money, the options, the risks, the timeline, each with the paragraph it came from.

Written by AI from the council's published papers. AI can get things wrong: the council's own wording below is the record.Report a problem
Item40

Resolved

RESOLVED – That the be noted.
Word for word from the decision Kirklees published for this meeting. Source: democracy.kirklees.gov.uk

Follow this further

Built from Kirklees's papers

What the report saysPro

Report to Dewsbury Neighbourhood Board, 5 pages

Purpose of report

To update the Board on the latest position of the Pride in Place programme for Dewsbury and to outline progress in establishing Working Groups that will lead the next phase of community led programme development.

Officer recommendation and reasons:

Recommendation

The Board is asked to: 1. Note the progress on the Regeneration Plan submission and the expected approval timeline. 2. Note the establishment of Working Groups as core delivery mechanisms. 3. Recognise that Board member participation will be required to support and lead these workstreams.

Public or private: Public

Has GDPR been considered? Yes

2. Information required to take a decision

Background

In September 2023, the UK government launched the Long-term Plan for Towns, naming Dewsbury as one of the towns to receive £20 million over ten years. Following the release of initial guidance in December 2023, Dewsbury’s Town Deal Board evolved into a new Town Board, which began community engagement to shape investment priorities.

Progress paused during the 2024 general election and spending review, but the Budget confirmed the programme's continuation. In March 2025, it was rebranded as the Plan for Neighbourhoods (PfN), with updated guidance issued. Subsequently in September 2025 MHCLG have introduced their Pride in Place Strategy where this programme falls within. The government required the creation of a Neighbourhood Board, which had evolved from Dewsbury Town Board to the Neighbourhood Board in April 2025, and has worked with communities and Kirklees Council to co-produce:

• A 10-year Regeneration Plan • A 4-year Investment Plan

2.2Submission Progress and MHCLG Response

Since the last Board meeting Dewsbury’s Regeneration plan was formally submitted to the Ministry of Housing, Communities and Local Government (MHCLG) on 27 November 2025, following Board approval, consistent with the timeline set out in the previous board paper.

• Receipt Acknowledged: MHCLG confirmed receipt of the submission shortly after submission. • Initial Triage Passed: A follow up email confirmed that the plan had successfully passed the government's initial triage stage, indicating no disqualifying issues and that the submission met baseline requirements. • Clarification Stage: In early January 2026, officers received a clarification request from MHCLG. All requested information and updates were submitted promptly. • Final Decision: A final approval outcome is expected by the end of February 2026.

2.3Readiness for Mobilisation

In anticipation of approval, intervention development, monitoring frameworks, and evaluation models are being drafted, ensuring that once funding is released in April 2026, project activity can commence as soon as possible.

3. Working Groups – Establishment and Purpose

3.1Context and Rationale

To ensure the Pride in Place programme remains community led, and consistent with earlier engagement and Board led thematic development, a refreshed set of Working Groups have been established. This directly builds on the approach outlined in the 4-year Investment Plan, which emphasised Board led thematic working groups shaping local priorities.

These groups will: • Lead the next phase of detailed intervention design • Shape delivery plans and identify Key Performance Indicators (KPIs) and success measures • Ensure continued alignment with community priorities and feedback

Each working group will be chaired by a Board member and supported by a range of key stakeholders drawn from a range of expertise, experience and community insight.

3.2Working Group Priorities Based on community engagement, the yet to be approved interventions, working groups will lead early programme activity.

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
Pride in Place UpdateReport 5 pages DownloadRead as text

At this meeting

Whole meeting

On this subject at Kirklees

Search all
  1. Pride in Place UpdateThis decision
  2. Pride in Place UpdateNoted
  3. Dewsbury Arts & Culture, Strategic Thinking - Pride in PlaceNoted

More from Kirklees Dewsbury Neighbourhood Board

All decisions
MeetingDecisionOutcome
18 Jun 2026 Membership of Dewsbury Neighbourhood BoardRESOLVED - David Wildman, Service Director for Skills and Regeneration at Kirklees Council, was appointed to the Boar... Decided Open
18 Jun 2026 Declaration of InterestsSophie Johnson, Peter Mason, Fara Butt, Andi Eccles, Jackie Ramsay and Martin Walsh, declared an interest as sharehol... Decided Open
18 Jun 2026 Minutes of Previous Meeting and Action TrackerRESOLVED - 1) That the minutes of the meeting held on 12 th February 2026 be approved as a correct record. 2) That th... Approved Open
18 Jun 2026 Chair's UpdateRESOLVED – That the Chair’s Update be noted. Noted Open
18 Jun 2026 Terms of ReferenceRESOLVED – That the updated for Dewsbury Neighbourhood Board be approved. Approved Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies