Strategic Planning Committee, Thursday 19 February 2026 at 1.00pm

Cooper Bridge Improvement Scheme - Acceptance of delegated non-executive functions from Calderdale MBC to Kirklees MBC (Reference to Council)

Noted Planning 4 papers

AI summaryStrategic Planning Committee noted and referred to Full Council a proposal for Kirklees to accept delegated non-executive planning and highways powers from Calderdale for the £53.5m Cooper Bridge junction scheme, with Full Council to decide on 11 March 2026.

AI summaryIn plain English

Written from the decision and the officer reportPDF Pro
OutcomeNotedReferred to Full Council meeting on 11 March 2026
Money£53.5 millionScheme projected cost, funded by WYCA
What happens nextFull Council 11 March 2026Decision on accepting delegation of non-executive functions
Who it affectsTwo Kirklees wards plus CalderdaleLiversedge and Gomersal, Mirfield and Ashbrow wards

What was decided

The committee noted the report and referred it to Full Council on 11 March 2026 for a decision on accepting the delegation of non-executive functions from Calderdale MBC. Report P1, P2, P24

Why

Kirklees needs delegated non-executive powers from Calderdale to lawfully determine a single planning application and monitor its implementation across land in both authorities. Report P3, P4

Without delegation, the authorities risk inconsistent approaches to determining the application and discharging conditions, causing confusion and delays. Report P4, P55

A single application by Kirklees avoids duplicated work, halves internal governance steps, and reassures residents, WYCA and third-party landowners. Report P47, P98, P99

What happens next

Full Council on 11 March 2026 to consider accepting the delegated non-executive functions; Kirklees Cabinet on 24 March 2026 to consider executive functions. Report P24, P102, P104, P105

If approved, drafting and completion of the delegation agreement between the two authorities, then further public consultation in summer 2026. Report P101, P91, P105

Subject to approvals, planning application submitted autumn 2026, Full Business Case approval early 2027, construction early 2028 to late 2029. Report P43, P106

The money

  • £53.5 million Projected cost of the Cooper Bridge Scheme, funded by WYCA Report P36, P108
  • £75.1m Previous WYTF programme allocation, reduced after September 2024 change request to phase the works Report P86, P108

Options considered

  • Rejected: Option 1: separate and distinct planning applications submitted to each authority for the part of the scheme in their boundary. High risk of duplicated work and cost, stakeholder confusion, resource shortfalls, inconsistency and potential delay risking WYCA funding Report P95, P97
  • Chosen: Option 2: single planning application to Kirklees for the whole scheme, with Calderdale as statutory consultee, following delegation of functions. Most efficient use of public funds, expedites consent, halves internal governance steps, avoids inconsistency, provides clarity to the public and landowners Report P96, P98, P99

Implications

  • Financial: Kirklees is the sole contracting party with WYCA and bears any financial risk; if scheme costs exceed the defined WYCA allocation there is no guarantee the shortfall will be funded. Report P9, P66, P80
  • Financial: Kirklees will cover Calderdale's professional costs in negotiating and completing the delegation agreement; costs sit within the overall scheme cost. Report P8, P39, P40
  • Legal: Delegation relies on Section 101 of the Local Government Act 1972 and Section 9EA of the Local Government Act 2000; Section 8 of the Highways Act 1980 may also be used. Report P69, P72
  • Legal: Calderdale's Constitution Article 11.4(a) permits the delegation; Kirklees' Constitution Article 11.4(c) permits accepting it. Report P73
  • Risk: Without delegation the scheme is not deliverable without significant additional resources and may be delayed, which could affect WYCA funding. Report P55, P79
  • Equalities: Decision has no impact on protected characteristic groups under the Public Sector Equality Duty, so no Integrated Impact Assessment was produced. Report P84
  • Climate: Decision has no direct impact on climate change or air quality. Report P75
  • Other: Supports delivery of 31,140 new homes target in Kirklees' Local Plan by unlocking housing and employment land near Cooper Bridge. Report P58, 3.1

Who and where

  • Residents of Liversedge and Gomersal ward Report P12
  • Residents of Mirfield and Ashbrow ward Report P12
  • Residents of the part of Calderdale crossed by the scheme Report P17, P19
  • Third-party landowners whose land is needed north of the existing highway boundary Report P31, P32
  • Bus, walking and cycling users of the A62/A644 corridor Report P17, P29

Timeline

  • 09/02/26: Calderdale Cabinet approved transfer of executive functions Report P103
  • 11/02/26: Calderdale Full Council decision on non-executive functions Report P103
  • 11 March 2026: Kirklees Full Council to consider accepting delegation of non-executive functions Report P24, P105
  • 24 March 2026: Kirklees Cabinet to consider executive functions Report P104
  • Summer 2026: Further public consultation on the preferred option Report P43, P91, P105
  • Autumn 2026: Submission of planning application Report P43, P106
  • Early 2027: Approval to proceed to Full Business Case (subject to WYCA assurance) Report P43, P106
  • Early 2028 to late 2029: Construction, subject to WYCA approval through the assurance process Report P43, P106

Plain English for the jargon

  • KMBC: Kirklees Metropolitan Borough Council
  • CMBC: Calderdale Metropolitan Borough Council
  • WYCA: West Yorkshire Combined Authority, which is funding the scheme
  • TCPA 1990: Town and Country Planning Act 1990
  • HA 1980: Highways Act 1980
  • HOTs: Heads of Terms, used to inform the formal delegation agreement
  • OBC: Outline Business Case, the current stage of the WYCA assurance process
  • ECI: Early Contractor Involvement, used to give cost assurance at design stage
  • LGA 2000: Local Government Act 2000, which governs executive and non-executive functions
  • WYTF: West Yorkshire Transport Fund, the earlier funding programme from which the scheme was originally allocated £75.1m
What was decided, why, and what happens next

Pro reads every officer report for you and explains each decision in plain English: the money, the options, the risks, the timeline, each with the paragraph it came from.

Written by AI from the council's published papers. AI can get things wrong: the council's own wording below is the record.Report a problem
Item59

Resolved

That the report be noted and referred to the meeting of Council on 11 March 2026.
Word for word from the decision Kirklees published for this meeting. Source: democracy.kirklees.gov.uk

Follow this further

Built from Kirklees's papers

What the report saysPro

Report to Strategic Planning Committee, 13 pages

Recommendations

It is recommended that Strategic Planning Committee:

1. Note the contents of this report and the attached appendices which include: Appendix A: Executive and non-executive functions Appendix B: Preferred option Appendix C: Cabinet Report (January 2024)

Reasons for recommendations

To enable KMBC to determine the planning application for both KMBC and CMBC and subsequently monitor the implementation of the planning permission for the Scheme in its entirety within both Authority’s land, in a lawful manner, KMBC requires particular non-executive powers and functions to be delegated from CMBC.

As discussed later within this report, having considered the options available to deliver the Scheme in an efficient and timely manner, both Authorities agree that it will be more efficient for KMBC to determine a single planning application for the entirety of the Scheme, despite it falling within both Authorities’ boundaries. This report provides information so that SPC can comment before the decision goes to Full Council for approval. If Full Council do not accept the delegation of non- executive functions, there would remain a significant risk of the Authorities taking inconsistent approaches when determining the planning application and discharging its conditions, which is 1 likely to lead to confusion for both public stakeholders and officers of each Authority and result in consequent delays. The associated risks are detailed within Section 3.5.

A separate report is being taken to Cabinet in relation to approving the acceptance of executive functions being delegated by CMBC to KMBC, and Members can review these executive functions in Appendix A for information purposes if necessary. In summary, they relate to executive functions under the TCPA 1990, HA 1980 and Road Traffic Regulation Act 1984.

Resource Implication:

KMBC are the lead Council for the Scheme and responsible for progressing the various stages in the process, including preparing the business case, the joint planning application and the design, securing funding and managing all associated costs.

The additional resources required for the delegation of non-executive powers from CMBC to KMBC includes time spent by the Authorities in appointing and instructing external solicitors for the provision of legal advice and the drafting and negotiation of the Agreement. KMBC will cover CMBC’s professional costs in connection with negotiation and completion of the Agreement.

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
Appendix AAppendix A 3 pages Download
PDF
Appendix BAppendix B 1 pages Download
PDF
Appendix CAppendix C 14 pages Download
PDF
Cooper Bridge Improvement Scheme: Acceptance of delegated non-executive functions from Calderdale MBC to Kirklees MBC (Reference to Council)Report 13 pages DownloadRead as text

At this meeting

Whole meeting
53Minutes of the Previous MeetingApproved 55Admission of the PublicOn the agenda
59Cooper Bridge Improvement Scheme - Acceptance of delegated non-executive functions from Calderdale MBC to Kirklees MBC (Reference to Council)This decision
60Planning Application - Application No: 2024/93494Approved 61Planning Application - Application No: 2025/92728Approved

On this subject at Kirklees

Search all
  1. Cooper Bridge Improvement Scheme - Acceptance of delegated non-executive functions from Calderdale MBC to Kirklees MBC (Reference to Council)This decision
  2. Cooper Bridge Improvement Scheme – Acceptance of delegated non-executive functions from Calderdale MBC to Kirklees MBC (Reference from Strategic Planning Committee)Approved
  3. Call-In of Cabinet Decision in relation to the A62 to Cooper Bridge Corridor Improvement SchemeApproved

More from Kirklees Strategic Planning Committee

All decisions
MeetingDecisionOutcome
8 Oct 2026 Planning Application - Application No: Planning Application 2021/93621Application approved (delegated). Approved Open
23 Jul 2026 Planning Application - Application No: 2025/92713Application approved (delegated). Approved Open
11 Jun 2026 Minutes of the Previous MeetingRESOLVED – The Minutes of the meeting held on 2 April 2026 be considered at the next meeting for approval. Approved Open
11 Jun 2026 Planning Application - Application No: 2025/92713Deferred. Deferred Open
11 Jun 2026 Planning Application - Application No: 2023/91907Approval delegated. Approved Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies