Kirklees Council
Cabinet, Tuesday 24 March 2026 at 1.30pm

10

Agreed Executive 3 papers

AI summaryKirklees Cabinet approved a further £3.0m for the Our Cultural Heart food hall fit-out in Huddersfield and delegated authority to officers to choose between a lease, management agreement or direct operation, with the venue now expected to open in spring 2027.

AI summaryIn plain English

Written from the decision and the officer reportPDF Pro
OutcomeAgreedSix delegations and funding approved
Money£3.0m additional drawdownFrom Phase 5 of OCH programme
What happens nextOpen spring 2027Library and public square open summer 2026
Who it affectsNewsome ward, HuddersfieldStrategic importance to all Kirklees wards

What was decided

Cabinet approved a further £3.0m drawdown from later phases of the Our Cultural Heart programme, taking Phase 1 committed spend from £58.370m to £61.370m and overall programme spend from £136.983m to £139.983m. Report P6

Cabinet delegated authority to the Executive Director of Place, with named consultees, to conclude the food hall tenant or operator selection (lease, management agreement or direct operation), award the concession or management contract, and procure the fit-out works. Report P2, P3, P4

Cabinet approved extension of the existing Strategic Delivery Partner, architect and engineer appointments to progress the Phase 1 food hall fit-out, subject to fee agreement and procurement rules. Report P5

Why

To maintain programme progress and select the operating model so the Phase 1 food hall can become operational in a timely manner as an integral part of the master plan. Report P9

Market engagement found operators are unwilling to commit capital, expect the landlord to take on more cost and risk, and a traditional lease is now harder to secure, so the council must fund and carry out the fit-out whichever model is chosen. Report P49, P75, P132

The original £1m council share of fit-out costs is no longer enough; negotiations now require the council to fund the full fit-out, increasing the council's contribution to up to £4m. Report P49, P96, P97

What happens next

Officers will conclude the operating model selection during spring 2026 so fit-out design and procurement can run in parallel with the final stages of Phase 1 construction. Report P139

The library hub, West Yorkshire Archive service and public square are expected to open in late summer 2026, with the food hall targeted to open in spring 2027 across all three operating model options. Report P138, P139, P79, P80

A feasibility study of management agreement and direct operation models will continue, with a final report on commercial terms prepared by Milligan for due diligence and decision. Report P50, P61, P101

The money

  • £3.0m Additional drawdown from Phase 5 of OCH programme to fund the food hall fit-out Report P6, P12
  • £58.370m Current approved Phase 1 construction budget (rising to £61.370m) Report P6, P104
  • £61.370m New Phase 1 construction budget after £3.0m addition Report P6, P104
  • £136.983m Previously approved overall programme committed construction expenditure (rising to £139.983m) Report P106
  • £139.983m New overall programme committed construction expenditure after £3.0m addition Report P6, P106
  • £1m Previously included council share of food hall fit-out costs in Phase 1 capital budget Report P49, P96
  • £4m Total estimated council cost for the food hall fit-out under the new proposal Report P97, P133

Options considered

  • Chosen: Lease with an experienced food hall tenant/operator. Preferred model endorsed by Cabinet in September 2025; transfers day-to-day operating risk; least delay; minimises immediate reputational risk Report P47, P65, P67, P135
  • Rejected: Management agreement with a specialist operator. Fallback option being developed if the lease is not viable; council still carries most financial risk; likely to delay opening Report P50, P67, P80, P135
  • Rejected: Direct operation by the council. Fallback option; council runs the food hall and takes all costs and risks; feasibility study underway Report P50, P67, P101

Implications

  • Financial: Increased capital cost and brought-forward borrowing; revenue impacts must be reflected in the refresh of the Medium Term Financial Strategy and future budgets. Report P13, P95, P97, P99
  • Financial: Reallocation of £3.0m from Phase 5 of the Construction Budget reduces funding available for the venue and any associated car parking in the wider master plan. Report P12, P100, P123
  • Legal: Any lease at undervalue must be assessed under section 123 Local Government Act 1972 and the General Disposal Consent 2003 (undervalue threshold £2m). Report P115
  • Legal: Procurement must comply with the Procurement Act 2023, Public Contracts Regulations 2015, Contract Procedure Rules, Best Value duty, Public Services (Social Value) Act 2012, Subsidy Control Act 2022 and the Public Sector Equality duty. Report P108, P109, P110, P111, P113, P114
  • Equalities: Integrated Impact Assessment from Gateway 3 (June 2023) is considered appropriate for this report and is included as a public appendix. Report P126, P127, P128
  • Climate: Sustainability strategy includes the council's 2038 carbon neutral vision, no gas on site, reduced rainwater run-off, and a BREEAM Excellent target for the built environment. Report P86, P117
  • Risk: There is a significant risk that the food hall will require long-term base budget funding from the council regardless of the operating model chosen. Report P122, P124
  • Other: The food hall is not expected to generate a profit for the council until the medium to long term. Report P75

Who and where

  • Residents and visitors of Newsome ward, Huddersfield town centre Report P18, P27, P28
  • All Kirklees wards (strategic importance of the programme) Report P18
  • Existing town centre businesses and prospective new investment Report P29, P31
  • Aspiring food hall traders, SMEs and local job seekers (social value outcomes) Report P91
  • BAM Construction Limited (Phase 1 design and build contractor) Report P42, P90
  • Turner & Townsend, FCB and Arup (client construction delivery team) Report P82, P83
  • Milligan (food hall operator selection advisor) Report P58, P59, P61

Timeline

  • mid-2023: BAM Construction Limited appointed under Pre Construction Services Agreement Report P42
  • August 2024: BAM awarded JCT construction contract for Phase 1 Report P42
  • September 2025: Cabinet last considered Our Cultural Heart at Phase 2 Gateway 4 Report P152
  • 16.03.2026: Report signed off by Executive Director for Place, Service Director Finance, Service Director Legal Governance and Commissioning Report P15, P16, P17
  • 24 March 2026: Cabinet decision
  • spring 2026: Operating model to be concluded and Heads of Terms finalised Report P78, P139
  • late summer 2026: Library Hub, West Yorkshire Archive and public square to open Report P42, P138
  • July 2026: Phase 1 construction completion due Report P42
  • later 2026: Food hall fit-out works to commence (subject to operating model) Report P139
  • spring 2027: Food hall targeted to be operational (earliest under all three options) Report P42, P79, P80, P139
  • 2038: Council carbon neutral target Report P86

Plain English for the jargon

  • OCH: Our Cultural Heart, the Huddersfield town centre regeneration programme
  • SDP: Strategic Delivery Partner, currently Turner & Townsend, managing project, design and construction delivery
  • PCSA: Pre Construction Services Agreement
  • PWLB: Public Works Loan Board, the government body from which councils borrow
  • BREEAM Excellent: High sustainability rating under the Building Research Establishment Environmental Assessment Method
  • IIA: Integrated Impact Assessment, covering equality, environmental and socio-economic impacts
  • F&B: Food and beverage
  • CPO: Compulsory Purchase Order (referenced via earlier Cabinet history, not the subject of this decision)
  • SV: Social Value, measured through the Social Value Portal
  • BAM: BAM Construction Limited, the Phase 1 design and build contractor
  • JCT: Joint Contracts Tribunal, a standard form of building contract used in the UK
What was decided, why, and what happens next

Pro reads every officer report for you and explains each decision in plain English: the money, the options, the risks, the timeline, each with the paragraph it came from.

Written by AI from the council's published papers. AI can get things wrong: the council's own wording below is the record.Report a problem
Item10:

Resolved

RESOLVED - 1) That in relation to the Phase 1 Food Hall Tenant/Operator authority be delegated to the Executive Director of Place, in consultation with the Service Director Finance, the Service Director Legal, Governance and Commissioning and the Portfolio Holder for Finance & Regeneration to conclude the food hall tenant/operator selection process (options are lease, management agreement or direct operation by the council) to determine the best outcome for the council. Where third parties are to be used under a lease to negotiate and agree the terms of the lease or if there is a management agreement procure (for a management agreement), negotiate the contract terms and award the contract(s). This delegation shall include any grant of a lease at an undervalue if appropriate. 2) That in relation to the Phase 1 Food Hall Contract authority be delegated to the Executive Director or Place, in consultation with the Service Director Legal, Governance and Commissioning and the Portfolio Holder for Finance and Regeneration to approve the commencement and award of a concession contract or a management services contract under the Procurement Act 2023 in accordance with the Council’s Procedure Rules. 3) That in relation to the Phase 1 Food Hall Fit Out authority be delegated to the Executive Director of Place, in consultation with the Service Director Finance, the Service Director – Legal, Governance and Commissioning and the Portfolio Holder for Finance & Regeneration to procure and award the necessary contract(s) to complete the food hall fit out. 4) That in relation to the SDP, Architect and Engineer Services, Extension of Appointments, subject to agreement on fees and in line with the council’s procurement process and Contract Procedure Rules, approval be given to the extension of the services being provided by the external Client construction delivery team (SDP, architect and the engineer) to progress the Phase 1 food hall fit out. The same delivery team is Our Cultural Heart, part of the Huddersfield Blueprint, Phase 1 Food Hall 2 providing the necessary services on Phase 1, Phase 2, the retail demolition and the rest of the feasibility work on the master plan. 5) That in relation to Our Cultural Heart Committed Expenditure (i) approval be given to the further draw down of £3.0m from later phases of the OCH programme to fund the food hall fit out thereby increasing the committed expenditure for Phase 1 from £58.370m to £61.370m and for the overall programme from £136.983m to £139.983m. (ii) the potential revenue implications of the operation of the Food Hall, taking into account the current offer and using the latest available PWLB rates for borrowing be noted. 6) That in relation to Agreements and Executing Documents authority be delegated to the Service Director – Legal, Governance and Commissioning to negotiate, agree, enter into all agreements and enter into and execute any documents necessary to enable the delivery of the Our Cultural Heart food hall.
Word for word from the decision Kirklees published for this meeting. Source: democracy.kirklees.gov.uk

Follow this further

Built from Kirklees's papers

What the report saysPro

Report to Cabinet, 15 pages

Purpose of report

This report builds on the approvals and delegations previously given by Cabinet, most recently in September 2025, and seeks permissions associated with the food hall in Phase 1 including drawing down further funding for the fit out.

Recommendations

1. Phase 1 Food Hall Tenant/Operator That Cabinet delegate authority to the Executive Director of Place, in consultation with the Service Director Finance, the Service Director – Legal, Governance and Commissioning and the Portfolio Holder for Finance & Regeneration to conclude the food hall tenant/operator selection process (options are lease, management agreement or direct operation by the council) to determine the best outcome for the council. Where third parties are to be used under a lease to negotiate and agree the terms of the lease or if there is a management agreement procure (for a management agreement), negotiate the contract terms and award the contract(s). This delegation shall include any grant of a lease at an undervalue if appropriate.

2. Phase 1 Food Hall Contract That Cabinet delegate authority to the Executive Director or Place, in consultation with the Service Director – Legal, Governance and Commissioning and the Portfolio Holder for Finance and Regeneration to approve the commencement and award of a concession contract or a management services contract under the Procurement Act 2023 in accordance with the Council’s Procedure Rules.

3. Phase 1 Food Hall Fit Out That Cabinet delegate authority to the Executive Director of Place, in consultation with the Service Director Finance, the Service Director – Legal, Governance and Commissioning and the Portfolio Holder for Finance & Regeneration to procure and award the necessary contract(s) to complete the food hall fit out.

4. SDP, Architect and Engineer Services, Extension of Appointments Subject to agreement on fees and in line with the council’s procurement process and Contract Procedure Rules, Cabinet approve the extension of the services being provided by the external Client construction delivery team (SDP, architect and the engineer) to progress the Phase 1 food hall fit out. The same delivery team is 1 providing the necessary services on Phase 1, Phase 2, the retail demolition and the rest of the feasibility work on the master plan.

5. Our Cultural Heart Committed Expenditure That Cabinet approve the further draw down of £3.0m from later phases of the OCH programme to fund the food hall fit out thereby increasing the committed expenditure for Phase 1 from £58.370m to £61.370m and for the overall programme from £136.983m to £139.983m. Cabinet is asked to note the potential revenue implications of the operation of the Food Hall, as described in the Private cabinet report, taking into account the current offer and using the latest available PWLB rates for borrowing.

6. Agreements and Executing Documents That Cabinet delegate authority to the Service Director – Legal, Governance and Commissioning to negotiate, agree, enter into all agreements and enter into and execute any documents necessary to enable the delivery of the Our Cultural Heart food hall.

Reasons for recommendations

At the outset of the Our Cultural Heart programme it was determined that at key points in the development delivery process the programme would be brought back to Cabinet to consider the recommendations and decide the future direction.

The delegations have been recommended so that progress can be maintained and the operating model selected so that the Phase 1 food hall that is an integral part of the overall master plan can become operational in a timely manner.

Resource Implications:

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
Phase 1 & Boundary with Phase 2 :Appendix 1 1 pages Download
PDF
IIA stage-2 :Appendix 6 15 pages Download
PDF
Our Cultural Heart: Phase 1 Food HallReport 15 pages DownloadRead as text

At this meeting

Whole meeting

More from Kirklees Cabinet

All decisions
MeetingDecisionOutcome
3 Nov 2026 8RESOLVED – 1) That the outcome of the Regulator of Social Housing inspection be noted. 2) That the Regulatory Improve... Noted Open
3 Nov 2026 10RESOLVED – 1) That the rent and service charge policy be approved. 2) That authority be granted to the Executive Dire... Approved Open
3 Nov 2026 12RESOLVED – 1) That approval be given to the Kirklees Employment Skills Framework 2026-2030 as the district-wide strat... Approved Open
6 Oct 2026 8RESOLVED – That the report be referred to the Meeting of Council on 21 October 2026 with the recommendations that Cou... Noted Open