AI summaryKirklees Strategic Planning Committee approves discharge of condition for retaining wall at Birkenshaw housing site, subject to tinting, hedge and climbing plants. Vote 4-0.
Written from the decision and the officer reportPDF Pro
OutcomeApprovedOption F: tinting, hedge planting, climbing plants on trellis
MoneyNot stated
What happens nextHead of Planning and Development to issue decision notice
Who it affectsNot stated
What was decided
The committee voted 4-0 (Councillors Armer, Homewood, A Pinnock and Sokhal in favour) to delegate approval of the Discharge of Conditions application to the Head of Planning and Development.
Officers are authorised to issue the decision notice, accepting the applicant's option F proposal, which adds climbing plants to the previously considered hedge planting and tinting. Report 1.4, 2.29, P40, 13.1
Options B, C, D (other tinting and ivy schemes), a moss living wall, and stone cladding were not accepted; the committee approved the option F package recommended by officers. Report 2.32, P43
Why
Officers found that the wall as built, in plain grey concrete, is visually obtrusive and out of keeping with surrounding stone walls and lower boundary treatments at this main entry point to Birkenshaw. Report 12.11
With option F's buff tinting, native hedge planting and climbing plants on a wire trellis, the visual harm from the wall is reduced to an acceptable level; highway structures and neighbouring amenity are not harmed. Report 12.3, 12.18, 13.1
A moss wall is not feasible due to the south-facing, dry, sunny orientation of the wall, and ivy (option D) is opposed by officers because ivy hides defects, complicates inspection and could undermine the structure, plus would take 5-12 years to give dense cover. Report 2.3, 2.11
What happens next
The Head of Planning and Development will issue the decision notice formally discharging condition 5 of reserved matters approval 2022/91047. Report P1
The applicant must carry out the tinting and soft landscaping; the applicant was asked to provide a brief management strategy for ongoing wall inspection and maintenance, to be adhered to by the site's Management Company. Report 2.31, 12.20
If members are not satisfied that mitigation is effective, the council could consider further refusal and whether enforcement against the wall would be expedient, with the applicant able to appeal any such action.
Options considered
Chosen: Option F: buff tinting, native hedge planting and climbing plants on a wire trellis fixed with metal vine eyes into the wall. Officers judged it would give greater wall coverage and sufficiently soften the wall's visual impact, and the RediRock manufacturer indicated it is acceptable in principle Report 2.29, 2.30, 2.32, P40, P43
Rejected: Option A: previously submitted CGI with hedge planting and initial Artstone tinting. Not a new option and provides less wall coverage than option F Report 2.4, 2.5, 2.32
Rejected: Option B: darker / aged drystone tinting with hedge planting. Unlikely to convincingly look like weathered natural stone and would not match the artificial stone of nearby dwellings Report 2.7
Rejected: Option C: drystone plus green moss splatter tinting with hedge planting. Doubtful the tinting could convincingly look like moss cover, and would not match nearby artificial stone Report 2.9
Rejected: Option D: original grey wall with self-clinging evergreen ivy (Hedera species) and no hedge. Most ivy species would take 5-12 years to give dense cover, KC Highway Structures say ivy hides defects and complicates inspection, hedge planting would be lost Report 2.11, 2.12
Rejected: Moss living wall. Site is south facing, dry and sunny, not suitable for moss Report 2.2, 2.3, P11
Rejected: Stone cladding or wrapping the wall in natural stone. Applicant raised concerns about extra loads, drainage risks and warranty; officers said the option was not convincingly ruled out but a freestanding cladding structure would leave no space Report 2.24, P34
Implications
Legal: The wall was built before the previous Discharge of Conditions application 2023/92092 was determined, breaching the pre-commencement condition 5; Planning Enforcement drafted a notice but did not serve it pending negotiation. Report 7.4, 7.5, 7.6, P75
Risk: Climbing plants will be fixed to the wall via metal vine eyes; the RediRock manufacturer has said this is acceptable in principle, but maintenance and inspection responsibility will sit with the site's Management Company, not the council. Report 2.29, 2.31, 12.3, 12.20
Equalities: Ward Councillors Thompson and Sheard, and Cllr Smaje, object to the wall and argue enforcement should require its removal; ward members say the wall was built without permission and gives an inappropriate, fortified appearance at the entrance to Birkenshaw. Report 3.2, P48, P49, P50, 9.5, P104, P107
Other: By late December 2025, eight of the 12 dwellings behind or above the wall (plots 1, 2, 6, 7, 8, 9, 10 and 11) were occupied, so dismantling the wall would affect occupied homes and access.
Other: Biodiversity Net Gain of 10% does not apply because earlier planning applications for this site were approved before 2024.
Who and where
Residents of Birkenshaw, who the ward councillors say see the wall daily at a key entry point to the village Report 9.5, P104, P105
Occupants of plots 1, 2 and 6 to 11, whose homes and shared footpath sit behind the wall
The applicant (developer of the 91-dwelling scheme at Blue Hills Farm) Report 1.2, 5.1, 12.13
Ward Councillors for Birstall and Birkenshaw (Cllrs Smaje, Thompson and Sheard) Report 1.2, 3.2, 9.5
KC Highway Structures, which issued an Approval in Principle for the wall Report 10.1, 12.2
The site's Management Company, which will be responsible for ongoing maintenance of the wall and planting Report 2.31, 12.20
Timeline
27/09/2018: EIA Screening Opinion 2018/20382 issued, confirming no EIA required for up to 123 units Report 6.1
09/12/2019: Outline permission 2019/90527 granted for up to 127 dwellings with access details Report 6.2
30/06/2023: Reserved Matters approval 2022/91047 issued for 91 dwellings, with pre-commencement condition 5 on retaining walls Report 6.3
12/07/2023: Previous Discharge of Conditions application 2023/92092 submitted, but the wall was built before it was determined Report 7.4
02/07/2024: Application 2023/92092 refused because of the wall's height and stark materials Report 6.4, 7.6
05/06/2025: Post-refusal site meeting between case officer, Planning Enforcement, KC Highway Structures and the applicant team Report 7.7
19/08/2025: Current Discharge of Conditions application 2025/92335 submitted Report 7.8
26/08/2025: Cllr Smaje commented that she is sceptical about long-term maintenance and enforcement delay
02/12/2025: Cllr Smaje added that a stone wall in keeping with surroundings would be better
15/01/2026: Strategic Planning Committee resolved to defer and instructed officers to negotiate cladding and living wall options Report 1.4
18/03/2026: Applicant put forward option F (hedge planting plus climbing plants) and stated the RediRock manufacturer is content in principle with vine eyes and a wire trellis Report 2.28, 2.29
24/03/2026: Applicant submitted two versions of the option, with option E (ivy) and option F (climbing plants) as the preferred choice Report 2.29
02/04/2026: Strategic Planning Committee resolved to delegate approval to the Head of Planning and Development, with a recorded vote of 4-0
Plain English for the jargon
Discharge of Conditions: A planning application to seek approval for details that a previous planning permission required to be submitted and agreed before a stated step, such as construction, could begin.
Reserved Matters: Details of a development left to be approved after outline planning permission has been granted, such as layout, scale, appearance, landscaping and access.
Approval in Principle (AIP): A sign-off by the council's Highway Structures team that a structure near the highway is acceptable on structural and safety grounds.
RediRock: The proprietary pre-cast concrete block system used to build the retaining wall at this site.
BNG (Biodiversity Net Gain): A requirement for developments to deliver at least 10% more biodiversity than existed before, mandatory in England from 12/02/2024 but not applicable here because earlier approvals pre-date that.
TPO: Tree Preservation Order, a legal protection for specific trees.
What was decided, why, and what happens next
Pro reads every officer report for you and explains each decision in plain English: the money, the options, the risks, the timeline, each with the paragraph it came from.
Written by AI from the council's published papers. AI can get things wrong: the council's own wording below is the record.Report a problem
Item67
Resolved
RESOLVED - That authority be delegated to the Head of Planning and Development to approve the application and issue the decision notice. A Recorded Vote was taken in accordance with Council Procedure Rule 42 (5) as follows; For: Councillors Armer, Homewood, A Pinnock and Sokhal (4 votes) Against: (0 votes)
Word for word from the decision Kirklees published for this meeting.Source: democracy.kirklees.gov.uk
DELEGATE approval of the application and the issuing of the decision notice to the Head of Planning and Development.
1.0INTRODUCTION
1.1This is a Discharge of Conditions application relating to a retaining wall at a site currently being developed. The relevant condition (condition 5 of Reserved Matters approval 2022/91047) requires details of retaining walls at the site. The full wording of this pre-commencement condition is set out at paragraph 6.3 of this report.
1.2This application was previously brought to the Strategic Planning Committee on 15/01/2026 for determination under the terms of the Delegation Agreement following a request from Ward Councillor Elizabeth Smaje. Cllr Smaje’s grounds for requesting a committee decision were as follows:
The wall impacts on visual amenity, and it is not in keeping with the rest of the surrounding buildings – including the new houses. We have received no response on future maintenance questions, and it was built without planning permission.
1.3Cllr Smaje’s original request was accepted by the Chair of the Strategic Planning Committee.
1.4At the meeting held on 15/01/2026, the Strategic Planning Committee resolved to defer its decision, and instructed officers to negotiate with the applicant and explore other options such as cladding and green/living walls (including, for example, moss), to achieve a more acceptable solution in relation to the visual impact of the wall.
1.5Various options were subsequently discussed with the applicant. These are described and assessed in section 2 of this report. Section 3 of this report sets out ward Members’ responses to the post-committee options initially proposed by the applicant team. Section 4 (onwards) of this report is largely as per the report previously brought to committee on 15/01/2026, albeit updated where necessary.
Alternative options considered
2.1Subsequent to the Strategic Planning Committee meeting held on 15/01/2026, the following alternative options (for the retaining wall adjacent to Whitehall Road West) have been proposed by the applicant or suggested by officers. Living wall (moss)
2.2Members specifically requested that this solution be looked into. The applicant responded as follows:
We have also enquired with manufacturers to the feasibility of the moss option identified by planning committee as a possible solution, due to the South facing orientation of the Redi-rock wall the moss option was deemed unfeasible as it requires damp, shaded, and cool environments to thrive.
2.3Officers can confirm that the application site is not suitable for a moss wall. Given its southeast-facing orientation (and southwest-facing orientation at the wall’s side return), exposure to direct sunlight and dryness, it would not be a suitable location for moss to grow.
Applicant’s “option A”
2.4This option was described by the applicant as “The previously submitted CGI, showing the hedge planting and the initial Artstone tinting to the Redi-rock wall”.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.