CouncilMonitor
194 principal councils 228,996 meetings since 2000 2.8 million official papers archived Straight from each council's own publication system
Knowsley Metropolitan Borough Council
North Kirkby Partnership Board, Tuesday 26 February 2008 at 10.00am

TOWER HILL REGENERATION PROJECT REPORT

Agreed Committee 1 paper

North Kirkby Partnership Board agreed this item on Tuesday 26 February 2008. Below is the council's own wording, with the papers it was decided on.

Item40

Resolved

It was AGREED that the progress on the Tower Hill Regeneration Project be endorsed
Word for word from the decision Knowsley published for this meeting. Source: councillors.knowsley.gov.uk

Follow this further

Built from Knowsley's papers

What the report saysPro

Report to North Kirkby Partnership Board

Purpose of report

This report will provide the Board with an update on developments and progress of The Tower Hill Regeneration Project.

Recommendations

The Partnership Board is asked to:

(I) Note and endorse the progress on Tower Hill Regeneration Project

LINKS TO AREA PRIORITIES/ AGREEMENT

The Tower Hill Regeneration Project is identified as a key priority within the North Kirkby Area Agreement. TOWER HILL REGENERATION PROJECT UPDATE

A brief background:-

The vision for the Tower Hill Regeneration Project is:- • To recreate a village centre that serves the original estate as well as the surrounding area. • To create a sustainable environment for future generations. • To deliver a high quality, secure environment that has a unique identity. • To achieve a sustainable and mixed community, one where income, tenure and age groups are significantly diversified. • To provide a ladder of employment and training opportunities for the Tower Hill community that are appropriate to the community, achievable by the community and local to the community.

Progress to date:- • Developer selection commenced in April 2006. One preferred developer selected, Miller Regeneration (part of Miller Homes Ltd). • Scoring and evaluation of developer bids undertaken based on value for money and quality of design. • Tower Hill Steering Group to link with Area Partnership Board to facilitate two way communication and monitoring. ARD for North Kirkby invited to attend Internal Officer Group from May 2007, to receive regular updates. • Miller Regeneration has undertaken site investigations throughout the whole site from July-September 2007. This included some secondary site investigations on previously developed land to quantify anomalies. • A joint selling agreement to progress the land sale between the Council and KHT is now in place. • Pre-planning consultation has been undertaken by Miller Regeneration in September and October 2007, to enable Miller to revise project design and prepare for submission of planning application. • The provision of a Boxing Club is still identified for Tower Hill. However, as discussions are now ongoing between Council's DND and existing clubs to assess the size and scale of the club, this has been removed from the Developer's remit, as it would have severely delayed their ability to undertake pre-planning consultation, as the exact club specification was not known. • Legal support for the council, KHT and Miller Regeneration have progressed the Developer Agreement. • A programme of community engagement has been delivered at Tower Hill, including:-

Summer 2006 and 7 visits by Tower Hill residents to open space and parks in Knowsley, and North West, to enable residents to visualise and shape the design of the new park at Tower Hill. From November 2007 - Collage Marketing and Community engagement team delivered visioning events to allow community to design the park at Tower Hill, linked to the above activity.

September 2007, 5 members of Tower Hill community attended a residential course focussing on community regeneration, to support ongoing consultation and engagement.

• 2007 - acquisition of former Tenterhook public house site completed by Council, as part of the Regeneration project.

THE NEXT STEPS

Miller Regeneration anticipated submitting a planning application prior to Christmas 2007, however have been subject to delay due to design works and revision of project costings following Site Investigations. This is not unusual. we now await submission of their planning application.

A submission has been made to English Partnerships for funding to support the purchase of the old health centre at Tower Hill, and we awaiting the outcome.

CONCLUSION

The Board is asked to endorse the progress made on the project to date, whilst acknowledging the current situation. Additional progress reports will be presented to the Board as the project continues.

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
TOWER HILL REGENERATION PROJECT REPORTReport 112 KB DownloadRead as text

At this meeting

Whole meeting

On this subject at Knowsley

Search all
  1. TOWER HILL REGENERATION PROJECT REPORTThis decision
  2. 18/00288/REM - Reserved Matters Application pursuant to 15/00570/HYB for the erection of 158 no. dwellings and associated works - approval sought for access, layout, scale, appearance and landscaping - Land between Shevingtons Lane and Headbolt Lane, Moorfield, Tower Hill Kirkby L33 1XD.Approved
  3. Application for a Premises Licence - Stretford News, 1 Stretford Close, Tower Hill, Kirkby L33 1WEApproved
  4. Review of premises licence - the farmer's arms public house, moorfields, tower hill, kirkby, l33 1xdDecided
  5. Application for grant of a Premise Licence - J K Wines, 5 Loweswater Way, Towerhill, Kirkby, L33 2DLRefused
  6. Tower Hill RegenerationAgreed

More from Knowsley North Kirkby Partnership Board

All decisions
MeetingDecisionOutcome
14 Mar 2013 Problem Solving GroupIt was AGREED that the work of the in the North Kirkby area be noted. Agreed Open
14 Mar 2013 Informing the 2013-2014 Scrutiny WorkplansAGREED - (i) That the feedback provided on the issues put forward last year be noted; and (ii) that the following iss... Agreed Open
14 Mar 2013 Annual ReviewIt was AGREED – (i) That a greater use of photographs be included in the annual review; and (ii) that the completed d... Agreed Open
14 Mar 2013 Proposed Changes to Area Governance ArrangementsIt was AGREED – That the contents of the report be noted. Agreed Open
19 Jul 2012 Sustainable Community Strategy RefreshIt was AGREED that content of the presentation be noted. Agreed Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies