NORTH KIRKBY AGREEMENT 2008/09

Agreed Committee 2 papers

North Kirkby Partnership Board agreed this item on Thursday 19 June 2008. Below is the council's own wording, with the papers it was decided on.

Item5

Resolved

It was AGREED - Action ( i ) That the draft Agreement as detailed at Appendix A be noted; Area Relationship Director (ii) that the Local Area Priorities for North Kirkby as set out in Appendix A be noted; Area Relationship Director (iii) that Mark Ward be invited to participate in the Northwood Sub-Group; Area Relationship Director (iv) that a presentation on CONFIRM be presented to a future meeting of the Environment Sub-Group; Environmental Representative (v) That action plans from relevant board members and their working groups be commissioned; and Area Relationship Director (vi) That a tour of North Kirkby be organised for all Board Members. Area Relationship Director
Word for word from the decision Knowsley published for this meeting. Source: councillors.knowsley.gov.uk

Follow this further

Built from Knowsley's papers

What the report saysPro

Report to North Kirkby Partnership Board

Purpose of report

The purpose of this report is to introduce the draft 2008/9 North Kirkby Agreement.

Recommendations

The Partnership Board is recommended to:

(i) Note the draft Agreement and comment on areas for amendment or improvement; (ii) Note and agree Local Area Priorities for North Kirkby as set out in Appendix A. (iii) Commission action plans from relevant board members and their working groups; (iv) Consider how it wishes to promote the Agreement within the local community. LINKS TO AREA PRIORITIES/ AGREEMENT

The North Kirkby Agreement is the means of illustrating priorities for improvement within the area. Delivery against the Agreement will be managed by the board during the 2008/9 meeting cycle. A series of Partnership Board sub-groups have been identified to deliver against these priorities and report on progress to each Partnership Board.

Background

The 2008/9 North Kirkby Agreement builds upon the work of the board in 2007/8. It aims to balance borough wide priorities against those at the local level. At a recent Area Partnership Board Away Day (22 May), representatives from the Board received a presentation of the Knowsley Vitality Index. This index, although not exhaustive identified key spatial and issues priorities for the North Kirkby area and were asked to consider and comment on this data and identify the priorities for North Kirkby for 2008/9.

The board is presented with the draft Agreement, as available at the time of the agendas being distributed. This draft will continue to be refined prior to the July board meeting and shall incorporate comments received from members at the June Board meeting.

As reported during the previous year, this draft Agreement is built upon the principles of:

• Realism – the board is unable to monitor and manage everything that is delivered in its area. As such, the Agreement proposes a short-list of priorities that have been agreed by the Local Strategic Partnership (LSP) Executive and Government Office. • Added Value – the priorities included in the draft are those against which the board can add value by exerting local influence or by directing local resources. • Inclusive – the priorities for improvement include those agreed by the LSP Executive, the thematic partnership and the community. • Application of data and intelligence – The Area Relationship Directors for the borough have developed priorities for the 61 natural communities based on information supplied by the Partnership’s data and intelligence group. • Continuity – the priorities build upon those discussed by the board in its previous cycle and the projects already commissioned by the board are referenced within the draft Agreement. • Manageability – The priorities are those for which management information is available at the local level.

The board is recommended to note the draft Agreement and comment on any potential areas for amendment or improvement.

Local Area Agreement Reward Grant Priorities

The board will be aware that the Partnership has entered into a commitment with the Government to improve performance in ten key themes over the next three years. These are known as the LAA Reward Grant priorities. It is key to recognise that the thematic partnerships have committed to achieving these targets already. As such, borough-wide, and in some cases local delivery plans are in place.

Locally Identified Priorities

Within the Agreement, priorities have been proposed for the natural communities within the area. These have been identified by the local community or by the Area Relationship Director using available data and intelligence available at Ward level.

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
AppendixAppendix 991 KB Download
PDF
NORTH KIRKBY AGREEMENT 2008/09Report 120 KB DownloadRead as text

At this meeting

Whole meeting

On this subject at Knowsley

Search all
  1. NORTH KIRKBY AGREEMENT 2008/09This decision
  2. North Park Road and South Park Road Conservation Areas, KirkbyApproved
  3. Application for a Premises Licence - Fairways, Westhead Avenue, Northwood, Kirkby L33 0XEDecided
  4. North Kirkby Neighbourhood Agreement 2012/13Agreed
  5. North Kirkby Area Partnership Board Problem Solving GroupAgreed
  6. North Kirkby Neighbourhood Agreement 2011/12Agreed

More from Knowsley North Kirkby Partnership Board

All decisions
MeetingDecisionOutcome
14 Mar 2013 Problem Solving GroupIt was AGREED that the work of the in the North Kirkby area be noted. Agreed Open
14 Mar 2013 Informing the 2013-2014 Scrutiny WorkplansAGREED - (i) That the feedback provided on the issues put forward last year be noted; and (ii) that the following iss... Agreed Open
14 Mar 2013 Annual ReviewIt was AGREED – (i) That a greater use of photographs be included in the annual review; and (ii) that the completed d... Agreed Open
14 Mar 2013 Proposed Changes to Area Governance ArrangementsIt was AGREED – That the contents of the report be noted. Agreed Open
19 Jul 2012 Sustainable Community Strategy RefreshIt was AGREED that content of the presentation be noted. Agreed Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies