Resolved
RESOLVED – ( i ) That the progress on the Street Lighting and Traffic Sign PFI Project be supported. (ii) that the Street Lighting and Traffic Sign PFI Project Update report be circulated to all Members of the Council.
Safer, Stronger Communities Scrutiny Committee decided this item on Thursday 1 April 2010. Below is the council's own wording, with the papers it was decided on.
Resolved
RESOLVED – ( i ) That the progress on the Street Lighting and Traffic Sign PFI Project be supported. (ii) that the Street Lighting and Traffic Sign PFI Project Update report be circulated to all Members of the Council.
The Street Lighting and Traffic Sign PFI project is a complex procurement project, which has been progressing through the procurement stages for some time. This project will procure a private sector company to deliver the street lighting and traffic sign services for a 25 year period utilising a standard form contract. It is worth scrutiny members noting that over a twenty five year period the contract value will be in the region of £150m+ and as such is the second largest procurement project to be undertaken by the Authority.
The scope of services provided will include the replacement of over 70% of the stock with new white light solution and will also include the replacement of the high masts on the M62 and the ongoing maintenance during the contract period. The new lighting will be innovative in that the Authority will have the ability, where appropriate, to dim and trim the lighting across the borough in order to reduce the CO2 emissions and the levels of electricity consumed. Key outcomes for the project will be the reduction in light pollution alongside the delivery of wider benefits such as the reduction in crime, perceptions of crime and road traffic accidents. Levels of crime and the perception of fear of crime are high in Knowsley. National research such as the Pease review in 1998 and research conducted in Stoke and Dudley has concluded that targeted improvements to street lighting in high crime areas have had a significant and positive impact on the levels of crime and the fear of crime in such areas. It is believed that similar benefits will be achieved within the authority following the replacement of the existing inefficient and unreliable street lighting with modern systems designed to current European standards.
Similarly, there is evidence to suggest that good modern street lighting can also be a contributory factor in reducing night time road accidents by up to 30%. In 2008 the Council identified, as part of it business case, that Road Traffic Accidents across the borough may be reduced by 10% in each area where the street lighting infrastructure had been upgraded.
The project is in the final stages of the procurement and intends to call for Final Tenders over the next few weeks and although a number of issues have been encountered such as, the credit crunch, the project team have undertaken protracted negotiations with the bidders and their associated banks in order to achieve the best solution for the best price.
In doing so the project team have driven the cost of the bids down significantly whilst increasing the quality of the solutions submitted. In the current fiscal climate this has been a key achievement as all projects in the current tranche have encountered significant delays due to the financial markets and have struggled to reach their key milestones and close affordable deals.
However, this project has just hit another milestone and is currently seeking endorsement from the Department for Transport (DfT) to progress to the Call for Final Tender stage, with a view to asking the remaining two bidders to submit their final bids in April 2010.
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
PDF |
Street Lighting and Traffic Sign PFI Project UpdateReport | 63 KB | DownloadRead as text |
Follow Safer, Stronger Communities Scrutiny Committee at Knowsley and we tell you when its next papers are published, before the meeting rather than after it.
| Meeting | Decision | Outcome | |
|---|---|---|---|
| 31 Mar 2011 | Forward Plan - April to July 2011RESOLVED – That the content of the item, which fell within the remit of the Committee and had been included in the la... | Noted | Open |
| 31 Mar 2011 | 2010/11 Quarter 3 PerformanceRESOLVED – (i) That the summary of Quarter 3 performance outturn for 2010/11, be noted; and (ii) that the action bein... | Noted | Open |
| 31 Mar 2011 | Review Report: Community EmpowermentRESOLVED - That the following 15 recommendations be endorsed and referred to the Council’s Cabinet for consideration:... | Approved | Open |
| 31 Mar 2011 | Update Report: Scrutiny Review of Behavioural ChangeRESOLVED – (i) That the progress to date on the implementation of the recommendations of the Working Group be endorse... | Decided | Open |
| 31 Mar 2011 | In-meeting Review: The Preliminary Flood Risk Assessment ReportRESOLVED – (i) That the action to be taken as set out in the Preliminary Flood Risk Assessment Report be endorsed; an... | Decided | Open |
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Keeps you signed in and runs your free-paper allowance. Always on.
Counts visits and which pages are used. First-party only, no advertising, never shared.