RESOLVED - ( i ) That the updated position relating to resources available for neighbourhood management initiatives as set out in section 3 of the report now submitted, be noted; (ii) that an allocation of £0.200m from available resources to fund specific costs associated with the Housing Improvement Programme as set out in section 4.1 of the report now submitted, be approved; (iii) that an allocation of £1.000m from available resources to fund development costs associated with the regeneration of Kirkby Town Centre as set out in section 4.2 of the report now submitted, be approved; and (iv) that the Knowsley Partnership Executive Team be commissioned to monitor and evaluate the impact of these investments and report back to the Cabinet in due course.
Word for word from the decision Knowsley published for this meeting.Source: councillors.knowsley.gov.uk
This report provides an update on the resources available to the Knowsley Partnership for neighbourhood management initiatives. The resources included within this report are derived from the Working Neighbourhoods Fund, the residual Neighbourhood Renewal Fund, Local Authority Business Growth Incentive funding, the Safer Stronger Communities Fund and partner contributions. The report also recommends allocations of £0.200m towards the Housing Improvement Programme and £1.000m towards the regeneration of Kirkby Town Centre.
Recommendations
Members of the Cabinet are recommended to:-
(a) Note the updated position relating to resources available for neighbourhood management initiatives as set out in section 3 of this report;
(b) Approve an allocation of £0.200m from available resources to fund specific costs associated with the Housing Improvement Programme as set out in section 4.1 of this report;
(c) Approve an allocation of £1.000m from available resources to fund development costs associated with the regeneration of Kirkby Town Centre as set out in section 4.2 of this report; and, (d) Commission the Knowsley Partnership Executive Team to monitor and evaluate the impact of these investments and report back to the Cabinet in due course.
Background
The overall level of resources available to the Partnership for allocation to neighbourhood management initiatives for the three-year period from 2008/09 to 2010/11 as reported to the Cabinet on 21 April 2010 was £41.884m. At that meeting, the Cabinet approved allocations amounting to £1.619m, which took the total level of allocations to £36.329m. This resulted in the availability of £5.555m in unallocated resources. The overall resource position is shown at Appendix A to this report.
4. PROPOSALS FOR ALLOCATING RESOURCES
4.1Housing Improvement Programme
4.1.1 On 27 April 2010, the Knowsley Partnership Executive Team agreed to ask the Cabinet to approve an allocation of £0.200m to fund specific costs associated with the Housing Improvement Programme prior to the Borough’s Strategic Housing Inspection, which is due to take place in September 2010. These costs are summarised as follows:-
• Homelessness Service Review - £0.015m;
• Homeless Strategy Development and Consultation - £0.007m;
• Allocations Policy Development and Consultation - £0.004m;
• Gypsy and Traveller Site Location and Development Consultation - £0.020m;
• Mock Housing Inspection - £0.020m;
• Developing and Printing a Full Suite of Customer Literature – £0.012m;
• Single year funding for 2 Environmental Health Officers (Housing Enforcement) - £0.080m; and,
• Single year fund to develop Housing Options Service - £0.042m. 4.1.2 These activities will constitute the Housing Improvement Programme in 2010/11, which is a priority for the Borough not only in response to the Audit Commission’s ‘Red Flag’ assessment of aspects the Housing service but also in terms of the overall aspiration to deliver quality housing options for all Knowsley residents.
4.1.3 The ongoing development and continuous improvement of the Strategic Housing Service is expected to be achieved through existing and future funding streams.
4.2Kirkby Town Centre Regeneration
4.2.1 On 17 May 2010, the Knowsley Partnership Executive Team agreed to ask the Cabinet to approve an allocation of £1.000m to fund costs associated with the regeneration of Kirkby Town Centre. Specifically the funding will support the enabling costs associated with the social housing relocation which is required to ensure the physical growth of the town centre. Further support to fund the Council’s development costs associated with the overall regeneration scheme will also be covered.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Kirkby Town Centre Investment (*)RESOLVED – That:- (i) the grant of a new lease in Kirkby Town Centre on the headline commercial terms detailed at App...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.