RESOLVED – That: (i) the Merseyside Local Transport Plan 3 (LTP3) be endorsed; and (ii) the requirement for Knowsley to draft a local Implementation Plan, which will set out how transport funding will be used in Knowsley to deliver the aims and objectives of LTP3, be noted.
Word for word from the decision Knowsley published for this meeting.Source: councillors.knowsley.gov.uk
The purpose of this report is to seek the Cabinet’s endorsement of the Third Local Transport Plan for Merseyside, and to inform Members of the requirement to produce a Knowsley-specific supplementary document (known as an Implementation Plan).
Recommendations
Members of the Cabinet are recommended to:-
(a) Endorse the Merseyside Local Transport Plan 3 (LTP3); and,
(b) Note the requirement for Knowsley to draft a local Implementation Plan, which will set out how transport funding will be used in Knowsley to deliver the aims and objectives of LTP3.
Background
3.1The introduction of the Local Transport Act (2008) changed the way in which metropolitan areas are required to produce their Local Transport Plans (LTPs). 3.2 Prior to the Act, the five local authorities on Merseyside (Knowsley, Liverpool, St Helens, Sefton and Wirral) and Merseytravel were required by statute to work in partnership to produce a joint LTP. Two LTPs were produced under this system, spanning the period 2000 - 2011.
3.3However, since the Act, the responsibility is no longer jointly held, as the statutory duty now lies solely with the Integrated Transport Authority, which is the former Passenger Transport Authority element of Merseytravel. The Merseyside districts, including Knowsley, are now only consultees.
3.4This makes the local transport planning process very different, in that the policies and priorities relating to transport in the sub-region are now developed and adopted by Merseytravel with the intention that they should be endorsed by each of the five local authorities.
3.5It should be noted that the Council, in its role as a Highway Authority, retains its statutory responsibilities and powers in relation to the maintenance, improvement, safety and management of the highway network. Without the support of the Council, it will not therefore be possible to deliver many aspects the LTP. This position also applies to the other four Merseyside districts.
3.6The Structure of LTP3
The 2008 Act requires the LTP3 to contain a strategy and a separate implementation plan. LTP3 will therefore be presented in three parts, supplemented by a number of annexes:-
• Part One details the long-term strategy until 2024 and is due to be adopted by Merseytravel on 17 March 2011;
• Part Two presents detailed information on each of the six goals presented in Part One and sets out a detailed assessment of how they will be delivered. It is scheduled for this also to be adopted by Merseytravel on 17 March 2011; and,
• Part Three will be the Implementation Plan which will set out the indicative programmes of delivery for each of the five Merseyside districts and Merseytravel. The first implementation period will cover 2011-2015.
3.7District Implementation Plans and Funding
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Kirkby Town Centre Investment (*)RESOLVED – That:- (i) the grant of a new lease in Kirkby Town Centre on the headline commercial terms detailed at App...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.