Resolved
It was AGREED that the content of the update report be noted. Action
North Huyton Partnership Board agreed this item on Thursday 7 April 2011. Below is the council's own wording, with the papers it was decided on.
Resolved
It was AGREED that the content of the update report be noted. Action
HIGHLIGHT REPORT Ref: Version: Programme: Stockbridge Village Regeneration Project: Stockbridge Village Regeneration Author: Audra Ross/Paul Morris/Patrick Goodison Date: 28 March 2011 Reporting Period: From: To: 2 March 2011 28 March 2011
Overall Status Time (Amber) Cost (Green) Quality (Green) Summary
Section 1 – Physical Project Progress
Technical
§ Work on site is continuing to progress well and delays due to severe weather in previous months are being made up.
§ Scottish Power have completed the new supply to the new substation and existing substation will shortly be knocked down and removed from site.
§ Works to the retail unit are continuing at a good rate
§ The main drainage for the scheme requires the full closure of The Withens. This work is being carried out over three weekend periods from 18th March in order to not disrupt deliveries to the site. Residents have been informed as per the communication plan for any full closure of the road.
Programme
§ To date no official Extensions of Time have been received from Morgan Sindall. However, they have written to 2020 highlighting reasons for the potential time delay, which are currently being evaluated.
§ There is currently provision within the Morgan Sindall contract sum that would be able to support a degree of costs for extensions of time. However, whilst it is anticipated that this would be containable within the current budget, until any programme delays have been agreed this cannot be confirmed.
§ As highlighted previously work is progressing well on site at present and we are working closely with Morgan Sindall.
Communications
§ Regeneration update article published in Knowsley News (March 2011) and distributed to all households in Knowsley. HIGHLIGHT REPORT Ref: Version: § An information display is in the PCT health centre to keep residents informed of the progress of the regeneration programme.
§ Regular Stockbridge Village update newsletter being prepared for issue in April 2011.
Information and Communications Technology
§ Work is progressing well on this workstream.
Finance
§ A financial review of the programme has been undertaken and work is continuing to bring all funding budgets and expenditure for the programme under one cost code. This will be completed for the next quarterly capital report. This provides greater clarity for easier monitoring and control of the financial aspects of the programme.
§ At the present time, it is still anticipated that capital expenditure will be within the funding available to the programme and close budget monitoring will continue to ensure the early identification of any potential problems.
§ Linking into the work of the Operational Management Group, the revenue implications of the building are being assessed. It is anticipated that a clearer estimate of the financial position will be available in early April 2011 as options and proposals are currently being worked on.
Operational Management Group
§ Work has progressed on the operational management of the building. Indicative costs based on service levels and floor areas have been provided and work is continuing to establish all of the running costs for the facility and the budgets available.
Family Learning Centre
§ The school closure and decant planning is progressing with all parties – schools, children’s centre and the nursery provider. Continuity of provision during decant is being investigated.
Neighbourhood Centre
§ The OJEU for the procurement of the fitness equipment in ongoing and will be completed by the end of March.
§ The public art work project has been received well by stakeholders and development sessions have been held with residents and community groups. HIGHLIGHT REPORT Ref: Version: Other
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
PDF |
Stockbridge Village Regeneration Plan UpdateReport | 117 KB | DownloadRead as text |
Follow North Huyton Partnership Board at Knowsley and we tell you when its next papers are published, before the meeting rather than after it.
| Meeting | Decision | Outcome | |
|---|---|---|---|
| 21 Mar 2013 | Progress on Pledge PlansIt was AGREED – Action ( i ) That the progress made to date on each of the pledge delivery plans be noted; and (ii) t... | Agreed | Open |
| 21 Mar 2013 | Problem Solving GroupIt was AGREED – That the action taken to date, to address the priorities in key locations, be endorsed. | Agreed | Open |
| 21 Mar 2013 | Informing the 2013-2014 Scrutiny WorkplansIt was AGREED – Action ( i ) That the feedback provided on the issues put forward last year be noted; and (ii) that t... | Agreed | Open |
| 21 Mar 2013 | Annual ReviewAGREED – That the Area Relationship Director circulate a copy of the draft North Huyton Partnership Board Annual Repo... | Agreed | Open |
| 21 Mar 2013 | Proposed Changes to Area Governance ArrangementsIt was AGREED that the report be noted. | Agreed | Open |
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Keeps you signed in and runs your free-paper allowance. Always on.
Counts visits and which pages are used. First-party only, no advertising, never shared.