CouncilMonitor
194 principal councils 228,996 meetings since 2000 2.8 million official papers archived Straight from each council's own publication system
Knowsley Metropolitan Borough Council
Cabinet, Wednesday 22 June 2011 at 2.00pm

Finance and Performance Outturn 2010/11 (*)

Noted Executive 1 paper

Cabinet noted this item on Wednesday 22 June 2011. Below is the council's own wording, with the papers it was decided on.

Item10

Resolved

RESOLVED – That:- (i) the overall cash limit surplus of £1.915m (as discussed in section 4.1 of the report submitted) after contributions to Portfolio reserves be noted; (ii) the non-cash limit surplus of £0.660m (as discussed in section 4.2 of the report submitted) be noted; (iii) the balance of unallocated contingency budgets of £1.048m (as discussed in paragraph 4.3.3 of the report submitted) be noted; (iv) the balance of unallocated transformation funding of £0.653m (as discussed in paragraph 4.3.4 of the report submitted) be noted; (v) the allocation of the overall revenue surplus of £4.276m as set out in section 4.4 of the report submitted be approved; (vi) the uncommitted Working Neighbourhoods Funds of £0.294m be set aside as additional risk management resources as detailed in section 4.5.4 of the report submitted; (vii) the position on Portfolio reserves at 31 March 2011 as detailed in section 4.6 of the report submitted be noted, and the Borough Treasurer continue to review all reserves and balances to determine whether they should be used for the originally planned purposes or be reallocated to other Council priorities; (viii) the allocation of £0.315m capital receipts to the Prescot Co-location Project as proposed in paragraph 5.1.3 of the report submitted be approved; (ix) the revised capital programme at 31 March 2011 of £125.804m as identified in paragraph 5.1.1 of the report submitted be noted; (x) the total expenditure in 2010/11 of £67.304m as identified in paragraph 5.2.1 of the report submitted be noted; (xi) the rephasing of capital expenditure of £15.531m as summarised in paragraph 5.2.1 of the report submitted be noted; (xii) the rephased items over £1.000m which require Cabinet approval as summarised in paragraph 5.2.2 of the report submitted be approved; and (xiii) the performance outturn for 2010/11 set out in section 6 ... view the full minutes text for item 10.
Word for word from the decision Knowsley published for this meeting. Source: councillors.knowsley.gov.uk

Follow this further

Built from Knowsley's papers

What the report saysPro

Report to Cabinet

Purpose of the report

This report presents the Council’s financial and performance outturn positions for 2010/11. It sets out the key issues arising from the Council’s revenue and capital budget monitoring for the year, and proposes options for the allocation of revenue resources which are available. It also includes a summary of key issues arising from service performance during 2010/11.

Recommendations

The Cabinet is recommended to:-

(a) Note the overall cash limit surplus of £1.915m (as discussed in section 4.1 of the report) after contributions to Portfolio reserves;

(b) Note the non-cash limit surplus of £0.660m (as discussed in section 4.2 of the report);

(c) Note the balance of unallocated contingency budgets of £1.048m (as discussed in paragraph 4.3.3 of the report);

(d) Note the balance of unallocated transformation funding of £0.653m (as discussed in paragraph 4.3.4 of the report);

(e) Approve the allocation of the overall revenue surplus of £4.276m as set out in section 4.4 of the report; (f) Agree that the uncommitted Working Neighbourhoods Funds of £0.294m be set aside as additional risk management resources as detailed in section 4.5.4 of this report;

(g) Note the position on Portfolio reserves at 31 March 2011 as detailed in section 4.6 of the report and agree that the Borough Treasurer should continue to review of all reserves and balances to determine whether they should be used for the originally planned purposes or be reallocated to other Council priorities;

(h) Approve the allocation of £0.315m capital receipts to the Prescot Co-location Project as proposed in paragraph 5.1.3;

(i) Note the revised capital programme at 31 March 2011 of £125.804m as identified in paragraph 5.1.1;

(j) Note the total expenditure in 2010/11 of £67.304m as identified in paragraph 5.2.1;

(k) Note the rephasing of capital expenditure of £15.531m as summarised in paragraph 5.2.1 of the report;

(l) Approve the rephased items over £1.000m which require Cabinet approval as summarised in paragraph 5.2.2 of the report; and

(m) Note the performance outturn for 2010/11 set out in section 6 of the report.

Background

3.1Portfolio Holders have received full details of the 2010/11 financial and performance outturn positions relating to their individual Portfolios through separate Portfolio Outturn reports during May and Early June 2011. This report presents the consolidated position for the Council and continues the approach to linking performance and resources. Although no direct cause and effect is implied between the financial and performance information, the joint reporting helps to highlight issues regarding the outputs and outcomes and the value for money that the Council achieves from its resources.

3.2The approach set out in this report reflects the Council’s continued commitment to sound financial management. The recommendations should be considered in the context of the Council’s medium term financial forecasts (reported to the Council on 2 March 2011) which set out extremely challenging financial targets for the next three years. 4. REVENUE OUTTURN POSITION

4.1Portfolio Cash Limits

4.1.1 In February 2011, the Cabinet received forecasts from Portfolios which estimated that there would be a Council-wide surplus position of £0.092m at outturn. Within this overall total a number of significant individual variances were reported, and it was reported that a combination of management actions and significant savings arising from the early implementation of early retirement and voluntary severance savings would improve the overall position.

4.1.2 As a result of these actions, at outturn there is a final surplus on cash limits of £1.915m (see table below). This represents just 1.2% of total cash limits. .

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
Finance and Performance Outturn 2010/11 (*)Report 305 KB DownloadRead as text

At this meeting

Whole meeting

On this subject at Knowsley

Search all
  1. Finance and Performance Outturn 2010/11 (*)This decision
  2. Finance and Performance Outturn 2009/10Agreed
  3. Finance and Performance Outturn 2008/09Agreed
  4. Finance and Performance Outturn 2007/08 (*)Agreed

More from Knowsley Cabinet

All decisions
MeetingDecisionOutcome
15 Jul 2026 Kirkby Town Centre Investment (*)RESOLVED – That:- (i) the grant of a new lease in Kirkby Town Centre on the headline commercial terms detailed at App... Agreed Open
15 Jul 2026 2026/27 Revenue Budget - Quarter 1 Monitoring Update (*)RESOLVED – That:- (i) the key issues affecting 2026/27 budget monitoring as set out in this report be noted; and, (ii... Noted Open
15 Jul 2026 Capital Programme: 2026/27 Monitoring (*)RESOLVED – That the revised three-year Capital Programme of £118.011m in total as set out in section 4 and detailed i... Approved Open
15 Jul 2026 Local Government Association (Corporate Peer Challenge) - Progress Update on Delivery of Action PlanRESOLVED – That the draft Action Plan (attached at Appendix A) which sets out progress made to address the recommenda... Agreed Open
4 Jun 2026 2025/26 Revenue Budget Monitoring - Final Outturn Position (*)RESOLVED - That:- (i) the final 2025/26 budget monitoring position for the Council as set out in this report be noted... Noted Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies