Town Centre (and Districts) Committee, Wednesday 22 June 2011 at 4.30pm

Retail Development Halewood

Noted Committee 1 paper

Town Centre (and Districts) Committee noted this item on Wednesday 22 June 2011. Below is the council's own wording, with the papers it was decided on.

Item8

Resolved

RESOLVED – That the report be noted.
Word for word from the decision Knowsley published for this meeting. Source: councillors.knowsley.gov.uk

Follow this further

Built from Knowsley's papers

What the report saysPro

Report to Town Centre (and Districts) Committee

Purpose of the report

To update members of the Committee on the retail development at Raven Court, Halewood.

Recommendation

The Town Centre (and Districts) Committee is recommended to:-

Note the content of the report.

3. UPDATE

Progress continues to be made in an extremely difficult economic climate for such private sector commercial developments. It had been anticipated that a start on site may have taken place earlier this year but there have been some further issues that have developed requiring agreement, prior to a start on site.

The scheme details remains as previously reported to Members; 44,000 square feet of new retail floorspace with Aldi as anchor tenant. The mix of tenants remains the same despite some recent publicity about one potential tenant coming out of the scheme. However as the discussions progressed between Neptune Developments Limited and retailers as to their occupational requirements various amendments are required to the planning permission granted in November 2010. These are currently being negotiated with the Council as Local Planning Authority, in the usual way.

Neptune had identified a Funder for the development and the legal documentation entered into by the Council and Neptune, for the development, reflected the Funder’s requirements. The Funder withdrew from the transaction but Neptune has secured interest from another Funder. The new Funder requires some minor changes to the existing contractual arrangements. Officers are working through these with legal advisors and have reached agreement requiring further legal documentation. This process is underway and these discussions are taking place simultaneously with those on the outstanding planning issues.

In order to make sure development could start on site as soon as possible the Council, unusually for such a development, took action in the advanced demolition of the shopping centre. This was completed in March this year.

Substantial progress has been made on this scheme since inception to ensure that Halewood has a Neighbourhood Centre with both modern retail facilities and ready access to public services delivered from an attractive contemporary centre.

All the pre-scheme work for this complicated project involving site and property acquisitions, public consultation, developer selection, scheme design, planning, funding and legal work is drawing to a close with the final amendments to the planning permission and legal documents now being resolved. The Council has been undeterred in its commitment to seeing this scheme delivered and it is anticipated that, subject to resolving the final legal and planning issues, that a start on site is imminent.

4. RESOURCE IMPLICATION

There are no resource implications arising as a direct result of this report.

5. RISK ASSESSMENT

Not applicable

6. IMPACT ON POPULATION GROUPS

Not applicable

7. COMMUNICATIONS

As the development proceeds the Council will work with Neptune and Aldi to make appropriate public statements.

8. CONCLUSION

Despite the current economic climate which has adversely affected commercial property development across the region, the Council, through its continued efforts, has developers keen to make a start on this retail development as soon as possible.

MIKE HARDEN Deputy Chief Executive

Contact Officer: - Nic Fitzpatrick Tel. 443 2304

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
Retail Development HalewoodReport 50 KB DownloadRead as text

At this meeting

Whole meeting

On this subject at Knowsley

Search all
  1. Retail Development HalewoodThis decision
  2. Kirkby Town Centre Retail Development - Phase 2Approved

More from Knowsley Town Centre (and Districts) Committee

All decisions
MeetingDecisionOutcome
11 Jul 2013 Feasibility Study for a Cinema in PrescotRESOLVED – That the presentation and comments raised be noted. Noted Open
11 Jul 2013 Kirkby Regeneration ProgrammeRESOLVED – That the presentation be noted. Noted Open
11 Jul 2013 Kirkby Market UpdateRESOLVED – (i) That the report be noted; (ii) that the designation of 6 and 4 day trade be endorsed; and (iii) that t... Noted Open
20 Mar 2013 Prescot Town CentreRESOLVED – that the content of the presentation and comments raised be noted. Minutes 14 to 17 received as a correct ... Noted Open
20 Jun 2012 Kirkby Market ProposalsRESOLVED – That the update on Kirkby Market be noted. Noted Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies