Resolved
RESOLVED – That the Knowsley Local Development Scheme – 3 rd Review 2012, as set out in Appendix 1 to the report now submitted be approved to come into effect on 30 th January 2012.
Cabinet approved this item on Wednesday 18 January 2012. Below is the council's own wording, with the papers it was decided on.
Resolved
RESOLVED – That the Knowsley Local Development Scheme – 3 rd Review 2012, as set out in Appendix 1 to the report now submitted be approved to come into effect on 30 th January 2012.
1.1This report seeks Cabinet approval to bring a revised Local Development Scheme (LDS) into effect for Knowsley. The LDS is a “programme plan”, setting out which documents will be prepared within the Local Development Framework and the role of each document.
Cabinet is recommended to:
2.1Approve the Knowsley Local Development Scheme – 3rd Review 2012 (see appendix 1) and resolve to bring this into effect on 30th January 2012.
3.1As previously reported to Members, the Local Development Framework (LDF) will be a folder of documents which will set out the Council’s strategic policies on the development of the Borough. It will include “Development Plan Documents”, “Supplementary Planning Documents” and other supporting documents.
3.2On 14 December 2011, Cabinet approved a report which provided an update on the preparation of the LDF Core Strategy for Knowsley. As identified in that report (section 7) the planning legislation requires the Council to prepare and maintain a separate document known as the Local Development Scheme (LDS). This is a published “programme plan” which sets out which documents the Council is to produce as part of its LDF, their subject matter and geographical area, and their timetable for production.
3.3The Council’s current LDS was published in January 2009 and covered a three year period. Since the 2009 LDS was published there have been several changes to the legislation. These have included: Ø Changes to the Town and Country Planning (Local Development) (England) Regulations 2004, which were amended in 2009; and Ø Section 111 (5) of the Localism Act 2011 (which comes into effect on 15th January 2012) removes a previous requirement that revisions to the LDS had to be submitted to the Secretary of State before being brought into effect. The Council will now be able to bring revisions to its LDS into effect without any prior submission to DCLG.
3.4In July 2011, the Government consulted on further changes to the regulations which will support the new provisions in the Localism Act, and which are expected to be in place by the time Cabinet considers this report.
3.5The changes have altered the detailed requirements concerning the content of the LDS, and it is now timely to publish a review of the Knowsley LDS. The legislation also specifies that any changes to the LDS must be brought into effect by a resolution of the local planning authority. This report seeks Cabinet approval for this formal resolution.
4. THE DRAFT KNOWSLEY LOCAL DEVELOPMENT SCHEME – THIRD REVIEW
4.1The draft third review of the Local Development Scheme is attached as appendix 1. The main changes compared to the previous LDS are as follows.
Simplification of the range of documents covered in the LDS
4.2As a result of changes to the regulations introduced in 2009, it is no longer necessary to list in the LDS the programme of “Supplementary Planning Documents” to be produced. The new LDS therefore does not list these in the proposed programme of document preparation. It focuses primarily on the proposed Development Plan Documents (DPDs). For Knowsley, these are the:
Ø Core Strategy DPD; Ø Joint Merseyside and Halton Waste DPD; and Ø Site Allocations and Development Policies DPD.
4.3This change will enable greater flexibility for the Council to produce Supplementary Planning Documents to deal with new or emerging issues, without them having had to be listed formally in the LDS beforehand. “Live” updates describing progress on Supplementary Planning Documents will be given on the Council’s website. Revised programme for document preparation
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
PDF |
Knowsley Local Development Scheme: 3rd Review 2012 (*)Report | 85 KB | DownloadRead as text |
Follow Cabinet at Knowsley and we tell you when its next papers are published, before the meeting rather than after it.
| Meeting | Decision | Outcome | |
|---|---|---|---|
| 15 Jul 2026 | Kirkby Town Centre Investment (*)RESOLVED – That:- (i) the grant of a new lease in Kirkby Town Centre on the headline commercial terms detailed at App... | Agreed | Open |
| 15 Jul 2026 | 2026/27 Revenue Budget - Quarter 1 Monitoring Update (*)RESOLVED – That:- (i) the key issues affecting 2026/27 budget monitoring as set out in this report be noted; and, (ii... | Noted | Open |
| 15 Jul 2026 | Capital Programme: 2026/27 Monitoring (*)RESOLVED – That the revised three-year Capital Programme of £118.011m in total as set out in section 4 and detailed i... | Approved | Open |
| 15 Jul 2026 | Local Government Association (Corporate Peer Challenge) - Progress Update on Delivery of Action PlanRESOLVED – That the draft Action Plan (attached at Appendix A) which sets out progress made to address the recommenda... | Agreed | Open |
| 4 Jun 2026 | 2025/26 Revenue Budget Monitoring - Final Outturn Position (*)RESOLVED - That:- (i) the final 2025/26 budget monitoring position for the Council as set out in this report be noted... | Noted | Open |
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Keeps you signed in and runs your free-paper allowance. Always on.
Counts visits and which pages are used. First-party only, no advertising, never shared.