Resolved
It was AGREED - ( i ) That the official ‘sign up’ to the troubled families programme be endorsed; and (ii) That the next steps to design and implement the programme set out in section 7 of the report now submitted be endorsed.
Knowsley Partnership Board agreed this item on Wednesday 23 May 2012. Below is the council's own wording, with the papers it was decided on.
Resolved
It was AGREED - ( i ) That the official ‘sign up’ to the troubled families programme be endorsed; and (ii) That the next steps to design and implement the programme set out in section 7 of the report now submitted be endorsed.
The purpose of this report is to update the Board on the progress of the Troubled Families Programme and to seek endorsement for proposed activity to take this work forward.
The Board is recommended to:
• Endorse the official ‘sign up’ to the troubled families programme. • Endorse the next steps to design and implement the programme set out in section 7 of this report.
3. BACKGROUND TO THE PROGRAMME AND GUIDANCE FROM THE GOVERNMENT
3.1The Prime Minister has given his public commitment to turning around the lives of 120,000 troubled families. In late 2011, a Troubled Families Team (TFT) was established in DCLG which is led by Louise Casey (Director General). The Team has been tasked with coordinating and delivering the multi-departmental approach to addressing the problem of Troubled Families. Departments across government have assembled £448m of resource to pump prime the work of local authorities. It is an expectation of the programme that services that work with families will be re- designed to ensure greater efficiency and effectiveness.
3.2Since its establishment, the Team has been negotiating across Whitehall to agree the definition of troubled families, to establish guidance for local authorities and to agree a payment by results mechanism. TFT have been uniquely open to the views of local areas in influencing their approach, some of which has been directly influenced by Knowsley officers.
3.3The Troubled Families’ Financial Framework, which details what is expected of participants, was officially launched on 28th March 2012. Details of this framework are provided in section 8 of this report.
3.4The financial framework guidance provides specific definitions of troubled families and an indication of what “turning around” these families means in practice. Additionally, advice and guidance was provided as to how to navigate barriers relating to the sharing of data between agencies, in particular data relating to worklessness and benefits. 3.5 The definition of a trouble family as per the guidance is:
‘Troubled families’ are households who:
• Are involved in crime and anti-social behaviour • Have children not in school • Have an adult on out of work benefits • Cause high costs to the public purse
We will undoubtedly already be aware of many of these families of which the TFT has estimated Knowsley has 620. The majority will be families who have been on different services’ radars for long periods, sometimes through generations. This programme, and the investment that accompanies it, represents an opportunity to take a systematic and strategic approach to these most challenging of families who have concerned services for years.
3.6A feature of the Troubled Families Programme is the focus on a Payment by Results (PbR) methodology. In brief, the PbR mechanism has been developed in recognition of the fact that developing new ways of working with these families is likely to incur initial extra costs in the short term to meet longer term objectives.
3.7The government estimates that the average cost of turning around a family is £10,000. Their model assumes that local agencies will meet 60% of this cost with the government making up the remaining 40% providing that there is a successful outcome.
3.8Once the 620 families are identified (517 of which are eligible for funding within the PbR element of the programme), there will be local discretion as to how they are processed through the new system.
4. PROGRESS IN KNOWSLEY
4.1In 2010, the government announced a number of pilots for what was then known as Community Budgets. Knowsley had provided them with initial indication that it wished to be a Wave 2 community budget authority.
4.2Since November, a multi-agency steering group has led the development of Knowsley’s approach. The steering group consists of:
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
PDF |
Working with Troubled Families in KnowsleyReport | 194 KB | DownloadRead as text |
Follow Knowsley Partnership Board at Knowsley and we tell you when its next papers are published, before the meeting rather than after it.
| Meeting | Decision | Outcome | |
|---|---|---|---|
| 27 Feb 2014 | Knowsley's Early Help System - A Strategy for Improvement 2014 - 2015It was AGREED – (i) That Knowsley’s Early Help System – A Strategy for Improvement be endorsed; and (ii) that the com... | Agreed | Open |
| 27 Feb 2014 | Stronger Families UpdateIt was AGREED that the update be noted. | Agreed | Open |
| 30 May 2013 | Knowsley Partnership Governance Arrangements 2013/14It was agreed at the meeting of Council on 17 May 2013 that the councillor representation on the Partnership Boards w... | Agreed | Open |
| 30 May 2013 | Stronger Families Programme Annual Report 2012/13It was AGREED that the Stronger Families Annual Report 2012/13 be noted. | Agreed | Open |
| 23 May 2012 | Area Partnership Boards Annual Review 2011/12It was AGREED that an Annual Review relating to the work of the Area Partnership Boards during 2011/12 be produced. | Agreed | Open |
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Keeps you signed in and runs your free-paper allowance. Always on.
Counts visits and which pages are used. First-party only, no advertising, never shared.