Annual Report 2011/2012

Agreed Committee 2 papers

North Huyton Partnership Board agreed this item on Thursday 21 June 2012. Below is the council's own wording, with the papers it was decided on.

Item5

Resolved

It was AGREED – (i) That last year’s priorities be carried forward; (ii) that the achievements made to date by partners be noted; (iii) that the progress made by the Problem Solving Group on the agreed key priorities, be noted.
Word for word from the decision Knowsley published for this meeting. Source: councillors.knowsley.gov.uk

Follow this further

Built from Knowsley's papers

What the report saysPro

Report to North Huyton Partnership Board

Purpose of report

The report aims to review the North Huyton Area Partnership Board achievements during 2011/12. It sets out the progress made against the Neighbourhood Agreement priorities and identifies key areas of work to be carried forward into next year. In addition it recognises the contribution of all board members and their organisations. The report will also highlight how the board has contributed to the social growth agenda.

Recommendations

The Area Partnership Board recommends:

• To carry forward last year’s priorities • To note the achievements to date of partners • To note the progress made by the problem solving group on the agreed key priorities.

Background

At the February 2011 meeting of the Knowsley Partnership Board, three significant risk factors were identified and agreed as short term priorities for the entire Knowsley Partnership. The Board agreed that focusing energy around these priorities would help to stabilise the Borough during a time of immense national change.

The three risk factors were: 1. A rise in levels of unemployment; 2. A rise in the levels of Personal Debt; and 3. The provision of first order needs, in particular an appropriate and affordable housing offer.

The Board considered these issues to be material threats to the Borough and its residents achieving their aspirations. If these issues were to get out of control, they would have an immediate and detrimental impact on all wider outcomes. The Board requested that all elements of the Knowsley Partnership consider these three areas as risk management priorities and these formed the basis of the Neighbourhood Agreement for 2011/12. Throughout the 2011/12 year, Area Partnership Boards have recognised the value in sharing best practice and have held a number of joint development days in order to further develop and deepen board members understanding of the issues in the area. These development days have focused on Social Growth and Personal Debt and enabled the Boards to improve and develop their action plans around these priorities.

4 Neighbourhood Agreement Priorities - Update

Personal Debt The board has been working to develop a more financially included community by providing early and effective advice for those at risk of falling into debt and those who are vulnerable through existing debt. Working with a range of agencies to target benefit take up, provide debt and money management advice and help people to cope with the changes in economic circumstances.

Community Money Advocates - In March 2012 the first of a series of training sessions was held in the GATE Community Centre for local volunteers to be trained up to the standard of ‘Generalist Debt Adviser’. This two part accredited scheme provides local volunteers with a qualification to give debt advice to those who request it through a designated centre . There already exists a framework for debt advice through local churches and this initiative intends to work within that structure to offer additional opportunities for local people to access debt advice. The training is being delivered through a recognised national charity ‘Community Money Advice’ and a dozen volunteers have already been through the first stages of the programme.

Employment Maintaining employment and tackling unemployment are key priorities for the Board. This requires targeting our actions to obtain an increase in employment through working with businesses to create growth, and with employers to identify job opportunities and any potential job losses early and then to work with the individuals affected to raise skills and find alternative employment.

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
Annual Report 2011/2012Report 170 KB DownloadRead as text
PDF
annual report appendixAppendix 761 KB Download

At this meeting

Whole meeting

More from Knowsley North Huyton Partnership Board

All decisions
MeetingDecisionOutcome
21 Mar 2013 Progress on Pledge PlansIt was AGREED – Action ( i ) That the progress made to date on each of the pledge delivery plans be noted; and (ii) t... Agreed Open
21 Mar 2013 Problem Solving GroupIt was AGREED – That the action taken to date, to address the priorities in key locations, be endorsed. Agreed Open
21 Mar 2013 Informing the 2013-2014 Scrutiny WorkplansIt was AGREED – Action ( i ) That the feedback provided on the issues put forward last year be noted; and (ii) that t... Agreed Open
21 Mar 2013 Annual ReviewAGREED – That the Area Relationship Director circulate a copy of the draft North Huyton Partnership Board Annual Repo... Agreed Open
21 Mar 2013 Proposed Changes to Area Governance ArrangementsIt was AGREED that the report be noted. Agreed Open