Knowsley Metropolitan Borough Council
Cabinet, Wednesday 18 July 2012 at 2.00pm

Management of Risk - 2011/12 Outturn Report

Noted Executive 2 papers

Cabinet noted this item on Wednesday 18 July 2012. Below is the council's own wording, with the papers it was decided on.

Item18

Resolved

RESOLVED – That (i) The progress made by Directorates during 2011/12 in managing Knowsley’s identified strategic risks as summarised at Appendix A to the report and the key issues arising as set out in paragraph 3.4 of the report be noted; (ii) the proposed closure of nine strategic risks, as illustrated in paragraph 4.1 of the report, be approved; (iii) the adoption of 13 new strategic risks for 2012/13, as set out in paragraph 5.2 of the report, be approved; and (iv) the Authority’s Strategic Risk Register for 2012/13, as set out at Appendix A to the report, be approved.
Word for word from the decision Knowsley published for this meeting. Source: councillors.knowsley.gov.uk

Follow this further

Built from Knowsley's papers

What the report saysPro

Report to Cabinet

Purpose of the report

The purposes of this report are to outline progress during 2011/12 in managing the Authority’s strategic risks, to identify the key issues to be progressed further as a result, and to recommend for approval the Strategic Risk Register for 2012/13.

Recommendations

Members of the Cabinet are recommended to:-

(i) Note the progress made by Directorates during 2011/12 in managing Knowsley’s identified strategic risks as summarised at Appendix A to this report and the key issues arising as set out in paragraph 3.4 of this report;

(ii) Approve the proposed closure of 9 strategic risks as illustrated in paragraph 4.1 of this report;

(iii) Approve the adoption of 13 new strategic risks for 2012/13 as set out in paragraph 5.2 of this report; and

(iv) Approve the Authority’s Strategic Risk Register for 2012/13 as set out at Appendix A to this report. 3. STRATEGIC RISK MANAGEMENT – 2011/12 PERFORMANCE

3.1Risk management is the identification, analysis and economic control of opportunities and risks which challenge the assets, reputation and objectives of the Authority and supports effective decision-making, service planning and delivery thus increasing the likelihood of achieving corporate and service objectives.

3.2Given the current economic environment, the potential impact of the Council’s ongoing Change and Transformation Programme, and the changing and challenging nature of the Council’s strategic agenda, it is essential that effective risk management is exercised alongside the Authority’s financial and performance management systems to enable the Council to demonstrate the adequacy of its governance arrangements and internal controls and maintain the effective use of resources.

3.3Identification, Prioritisation and Management of Strategic Risks

3.3.1 The Strategic Risk Register for 2011/12 was considered and agreed by Cabinet on 20 July 2011. In total, the Authority commenced 2011/12 with 38 strategic risks on the Register. The management of these risks was undertaken as part of the delivery of priorities within Directorate Business Plans with sufficient resources allocated to enable the identified controls to be implemented.

3.3.2 Reviews have been undertaken by Directorates of all risks during the year in order to monitor progress and to identify any emerging risks. A summary of the Council’s risk profile during 2011/12 (including those 9 risks proposed for closure in section 4 of this report below) is set out in the following table:-

Position at Position at Beginning of Risk Movement during 2011/12 End of 2011/12 2011/12 New Closed Reduced/Increased (Net Movement) High 10 1 -2 -4 5 Medium 23 3 -8 -1 17 Low 5 0 -4 +5 6 TOTAL 38 4 -14 0 28

3.4Key Issues

3.4.1 At the end of 2011/12, Directorates were requested each to provide an update on the current key issues in relation to the management of the relevant strategic risks. A detailed progress statement for all strategic risks managed during 2011/12 and still active is available at Appendix A to this report. Whilst no major concerns were raised which would leave the Authority vulnerable, some key comments on progress are set out below for Members’ information.

3.4.2 Developing the Performance Management Framework in Response to Changing National Policy [Lead Directorate: Chief Executive’s]

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
Management of Risk: 2011/12 Outturn ReportReport 122 KB DownloadRead as text
PDF
StrategicRisksQ4SummaryAppendix1CLEAREDBYMH appx finalAppendix 329 KB Download

At this meeting

Whole meeting

On this subject at Knowsley

Search all
  1. Management of Risk - 2011/12 Outturn ReportThis decision
  2. Risk Management Policy(*)Approved
  3. Strategic Risk Management 2017/18 and 2018/19Noted
  4. Strategic Risk Management 2017/18 and 2018/19Noted
  5. Strategic Risk Management 2016/17 and 2017/18Noted
  6. Strategic Risk Management 2016/17 and 2017/18Noted

More from Knowsley Cabinet

All decisions
MeetingDecisionOutcome
15 Jul 2026 Kirkby Town Centre Investment (*)RESOLVED – That:- (i) the grant of a new lease in Kirkby Town Centre on the headline commercial terms detailed at App... Agreed Open
15 Jul 2026 2026/27 Revenue Budget - Quarter 1 Monitoring Update (*)RESOLVED – That:- (i) the key issues affecting 2026/27 budget monitoring as set out in this report be noted; and, (ii... Noted Open
15 Jul 2026 Capital Programme: 2026/27 Monitoring (*)RESOLVED – That the revised three-year Capital Programme of £118.011m in total as set out in section 4 and detailed i... Approved Open
15 Jul 2026 Local Government Association (Corporate Peer Challenge) - Progress Update on Delivery of Action PlanRESOLVED – That the draft Action Plan (attached at Appendix A) which sets out progress made to address the recommenda... Agreed Open
4 Jun 2026 2025/26 Revenue Budget Monitoring - Final Outturn Position (*)RESOLVED - That:- (i) the final 2025/26 budget monitoring position for the Council as set out in this report be noted... Noted Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies