Resolved

RESOLVED – (i) That the progress of submissions to the Secretary of State for sponsored Academy conversion of three Centres for Learning – Christ the King Centre for Learning, Huyton Arts and Sports College and Kirkby Sports College – be noted; (ii) that the timescales to progress these proposals be noted; and (iii) that the key messages proposed to inform key stakeholders on progress be agreed. (Note: In accordance with the provisions of Section 28(2) of the Localism Act 2011, Councillors G J Morgan and R J Round JP declared a personal interest in the above item, remained in the meeting, took part in the discussion and voted thereon.)
Word for word from the decision Knowsley published for this meeting. Source: councillors.knowsley.gov.uk

Follow this further

Built from Knowsley's papers

What the report saysPro

Report to Cabinet

Purpose of the report

The purpose of this report is to update Cabinet on development work that has been undertaken with the Department for Education (DfE) in relation to progress with the Academy sponsorship submissions to the Secretary of State and to consider the proposed communications strategy. The report also outlines the communications strategy and timescales for the proposals.

Recommendations

Cabinet is recommended to:

2.1Note the progress of submissions to the Secretary of State for sponsored Academy Conversion of three Centres for Learning – Christ the King Centre for Learning, Huyton Arts and Sports College and Kirkby Sports College;

2.2Approve the timescales to progress these proposals; and

2.3Agree the key messages proposed to inform key stakeholders on progress.

Background

3.1Current Department for Education policy requires any school whose pupil performance is below the national floor standard will be expected to become a sponsored academy. In 2012 the floor standard was 40% 5A*- C GCSE grades, including English and Mathematics. . 3.2 In September 2012 Ofsted introduced a new Inspection Framework which places a greater emphasis on pupil outcomes and pupil progress. The new framework applies greater rigour to school inspections which is likely to impact significantly on schools.

3.3On the 13th September 2012 the DfE visited the Council to discuss the three Centres for Learning whose performance in 2012 was below the 40% floor standard (Christ the King Centre for Learning, Huyton Arts and Sports College and Kirkby Sports College). The DfE’s expectation was that all three would need to become sponsored academies.

4. PROGRESS IN SECURING SECRETARY OF STATE APPROVAL FOR SPONSORED ACADEMIES

4.1The Council has worked with the governing body of each of the schools in identifying professional partners who have subsequently been providing external capacity in addressing school improvement priorities and pupil achievement. This additional capacity has been funded from the GCSE Pledge resources. The Governors of all three Centres have developed a professional relationship with their school improvement partners and have explored their potential as future Academy sponsors.

4.2Representatives from the DfE met with Governing Bodies during October 2012 in all three Centres. Governors passed a resolution that the governing body accepts that the best interest of the school and their pupils would be served by becoming a sponsored academy and asking the Secretary of State to issue an academy order to that effect with their named sponsor.

4.3All three Centres have been inspected since September 2012 and in each centre Ofsted judged that significant improvement was required. The DfE met with the Council again on the 26th November 2012 to progress the Academy submissions and documentation was presented for all three centres. The DfE representatives confirmed that they would be recommending to the Secretary of State that all three Centres become a sponsored academy in September 2013. The meeting with the Minister will take place week commencing 10th December 2012 and the outcome known during January 2013.

4.4Further reports will be brought to Cabinet as the timeline progresses in order to seek approval to the detailed steps within the sponsored academy conversion process. 5. RESOURCE IMPLICATIONS

5.1Financial

In a sponsored academy conversion, any budget deficit carried by the converting schools transfers to the Local Authority on conversion. The School Finance (England) Regulations 2012 (Regulation 3, Schedule 1, paragraph 40) clarifies the legal status in that expenditure on the writing-off of deficits of schools can be charged to the Dedicated Schools Grant (DSG).

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
Sponsored Academies Progress UpdateReport 83 KB DownloadRead as text

At this meeting

Whole meeting

On this subject at Knowsley

Search all
  1. Sponsored Academies Progress UpdateThis decision
  2. Sponsored Academies UpdateNoted

More from Knowsley Cabinet

All decisions
MeetingDecisionOutcome
15 Jul 2026 Kirkby Town Centre Investment (*)RESOLVED – That:- (i) the grant of a new lease in Kirkby Town Centre on the headline commercial terms detailed at App... Agreed Open
15 Jul 2026 2026/27 Revenue Budget - Quarter 1 Monitoring Update (*)RESOLVED – That:- (i) the key issues affecting 2026/27 budget monitoring as set out in this report be noted; and, (ii... Noted Open
15 Jul 2026 Capital Programme: 2026/27 Monitoring (*)RESOLVED – That the revised three-year Capital Programme of £118.011m in total as set out in section 4 and detailed i... Approved Open
15 Jul 2026 Local Government Association (Corporate Peer Challenge) - Progress Update on Delivery of Action PlanRESOLVED – That the draft Action Plan (attached at Appendix A) which sets out progress made to address the recommenda... Agreed Open
4 Jun 2026 2025/26 Revenue Budget Monitoring - Final Outturn Position (*)RESOLVED - That:- (i) the final 2025/26 budget monitoring position for the Council as set out in this report be noted... Noted Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies