Cabinet, Wednesday 5 June 2013 at 2.00pm

Knowsley Community College - Kirkby Campus

Noted Executive 1 paper

Cabinet noted this item on Wednesday 5 June 2013. Below is the council's own wording, with the papers it was decided on.

Item7

Resolved

RESOLVED – (i) that the economic case presented by Knowsley Community College and the College’s resulting recommendation to close its Kirkby campus be noted; (ii) that Knowsley Community College exists entirely independently from the Council and therefore that the College’s Governing Body is ... view the full minutes text for item 7.
Word for word from the decision Knowsley published for this meeting. Source: councillors.knowsley.gov.uk

Follow this further

Built from Knowsley's papers

What the report saysPro

Report to Cabinet

Purpose of the report

This report advises the Cabinet of Knowsley Community College’s latest plans in relation to the potential closure of its Kirkby campus. The report also outlines the activity undertaken by Council officers since the Authority became aware of the College’s intention to recommend closure of its Kirkby campus, and considers whether direct financial support from the Council could affect those plans and indeed whether such support could be made available.

Recommendations

Members of the Cabinet are recommended to:-

(a) Note the economic case presented by Knowsley Community College and the College’s resulting recommendation to close its Kirkby campus;

(b) Note that Knowsley Community College exists entirely independently from the Council and therefore that the College’s Governing Body is entitled and empowered to make the decision which it considers to be in the best interests of the College;

(c) Note that, in the continued absence of any firm support from the Department for Education, any direct support from the Council would need to be substantial, and that this would only guarantee the Kirkby campus being open for one more year; (d) Note that even an alternative option to maintain very limited education provision on the Kirkby campus would still need around £0.7m in direct support from the Council, and that this approach would also still not guarantee any long-term provision at the site;

(e) In the light of recommendations (a) to (d) above and the Council’s overall funding position, agree that the College should be informed that the Council is not in a position to provide direct financial support to the necessary level in this instance; and,

(f) Endorse the activity which the Council can undertake to support the College to ensure its long-term sustainability as a provider of education services in the Borough.

Background

3.1Knowsley Community College currently operates further education and training provision across three sites in Knowsley:-

• The Roby campus on Rupert Road (capacity 2,500);

• The Princess Drive facility in Huyton (capacity 500); and,

• The Kirkby campus on Cherryfield Drive (capacity 2,500).

3.2The provision is different at each site, and the configuration of each site has been established in order to support the type of courses offered. The Kirkby campus largely focuses on vocational training linked to the construction and engineering industries, and therefore comprises substantial workshop space. While also providing some vocational training (i.e. linked to service industries), the Roby campus focuses on academic and classroom-based courses.

3.3The College is under significant financial pressure due to a number of factors, including:-

(i) A loss in student numbers over the past couple of years following a negative OFSTED report;

(ii) Significant competition in the further education sector both within Knowsley and also outside of the Borough; and,

(iii) The impact of economic decline (most notably in relation to a reduced requirement for construction industry-related training). 3.4 The College’s financial position is particularly challenging in view of the fact that its funding is predominantly based on student numbers and rolls are continuing to fall. In this context, the long-term sustainability of the College is clearly at risk.

3.5The College therefore commissioned KPMG to undertake an independent review of its costs and operations with a view to ensuring future financial robustness and sustainability. The KPMG report reached a number of conclusions, perhaps the most fundamental of which is that:-

“The College is operating in a footprint that is significantly larger than it requires.”

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
Knowsley Community College: Kirkby CampusReport 118 KB DownloadRead as text

At this meeting

Whole meeting

On this subject at Knowsley

Search all
  1. Knowsley Community College - Kirkby CampusThis decision
  2. The Knowsley Community Fund (Round 2 - 2026/27) (*)Agreed
  3. Knowsley Community Safety Partnership Strategic Plan (2025-2028) (*)Decided
  4. Knowsley Community Safety Partnership Strategic Plan 2022-2025Decided
  5. Knowsley Community Safety Plan - Strategic Priorities 2017-2020 (*)Decided
  6. Community Infrastructure Levy Review: Questionnaire - Knowsley Council ResponseDecided

More from Knowsley Cabinet

All decisions
MeetingDecisionOutcome
15 Jul 2026 Kirkby Town Centre Investment (*)RESOLVED – That:- (i) the grant of a new lease in Kirkby Town Centre on the headline commercial terms detailed at App... Agreed Open
15 Jul 2026 2026/27 Revenue Budget - Quarter 1 Monitoring Update (*)RESOLVED – That:- (i) the key issues affecting 2026/27 budget monitoring as set out in this report be noted; and, (ii... Noted Open
15 Jul 2026 Capital Programme: 2026/27 Monitoring (*)RESOLVED – That the revised three-year Capital Programme of £118.011m in total as set out in section 4 and detailed i... Approved Open
15 Jul 2026 Local Government Association (Corporate Peer Challenge) - Progress Update on Delivery of Action PlanRESOLVED – That the draft Action Plan (attached at Appendix A) which sets out progress made to address the recommenda... Agreed Open
4 Jun 2026 2025/26 Revenue Budget Monitoring - Final Outturn Position (*)RESOLVED - That:- (i) the final 2025/26 budget monitoring position for the Council as set out in this report be noted... Noted Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies