RESOLVED – (i) that the closure of Page Moss Library with effect from April 2014, as set out at section 4.1 of the report, be approved; (ii) that a formal agreement be entered into with Hugh Baird College regarding the transfer of Whiston Library to the College with effect from 1 April 2014, as set out in Sections 4.2 and 4.3 of the report; and (iii) subject to resolution (ii) above, the Deputy Chief Executive, in consultation with the Cabinet Member with Portfolio for Leisure, Community and Culture, be authorised to finalise the relevant formal agreement.
Word for word from the decision Knowsley published for this meeting.Source: councillors.knowsley.gov.uk
This report updates the Cabinet on the progress made in assessing community interest in providing future library facilities in Page Moss and Whiston. The report summarises the current position and seeks approval in respect of the way forward for each Library.
Recommendations
Cabinet is recommended to:-
(i) Agree the closure of Page Moss Library with effect from 1 April 2014 as set out in section 4.1 of this report;
(ii) Agree to enter into a formal agreement with Hugh Baird College regarding the transfer of Whiston Library to the College with effect from 1 April 2014 as set out in sections 4.2 and 4.3 of this report; and,
(iii) Subject to (ii) above, authorise the Deputy Chief Executive in consultation with the Cabinet Member with Portfolio for Leisure, Community and Culture to finalise the relevant formal agreement. 3. BACKGROUND
3.1On 6 March 2013, the Council agreed the following actions in respect of the Library service as part of the Authority’s budget for 2013/14 and 2014/15:-
• No savings to be identified for the financial year 2013/14;
• The transfer to community use or closure of Page Moss and Whiston Libraries from the 2014/15 financial year; and,
• Reduced opening hours in the Borough’s remaining Libraries from the 2015/16 financial year.
3.2The total annual savings expected to be achieved via the above measures are £0.220m.
3.3The proposed closures of Page Moss and Whiston Libraries have also previously been identified as an element of the Council’s Corporate Property Plan, which was agreed by the Cabinet on 5 December 2012. The Cabinet report which accompanied the Corporate Property Plan stated clearly that, “Information and customer contact facilities (such as One Stop Shops, Libraries, Advice Centres etc) should be co-located and only be provided in Huyton, Kirkby, Halewood and Prescot to serve the Borough’s main urban areas.”
3.4With regard to the potential opportunities for the transfer of either library to community use/ownership, there are various models which the Council have explored. These include:-
• Totally Independent Community Libraries;
• Community Run with Council Support;
• Community Supported; and/or,
• Services Commissioned from External Community Organisations.
3.5Council officers examined how community-run libraries have been established in other local authority areas. Overall, there is no single model of community involvement in libraries. The best approach to community involvement in Knowsley would be the one that is most appropriate to the relevant local community’s needs, capacity and interest in being involved. 3.6 In order to comply with legal requirements and to ensure that all stakeholders had an opportunity to engage with the process, a consultation exercise involving library customers, employees, and other relevant groups, agencies and partner organisations was undertaken to inform the implementation and achievement of the savings proposals referred to in paragraph 3.1 above.
3.7Letters were issued to all Page Moss and Whiston Library users to inform them of the Council’s wish to explore the possibility of community-run libraries in both areas. The letters also contained the details of the planned public consultation meetings, which were also advertised on notice boards in both Libraries.
3.8Initially, four public consultation meetings were planned. Two further meetings subsequently took place. These meetings were added to the consultation timetable in response to comments made at the four scheduled meetings, whereby some attendees indicated that they believed that some members of the local communities may have been unaware of the meetings.
3.9In overall terms, the public meetings were not well attended as illustrated below:-
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Kirkby Town Centre Investment (*)RESOLVED – That:- (i) the grant of a new lease in Kirkby Town Centre on the headline commercial terms detailed at App...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.