Resolved

RESOLVED – (i) that the closure of Page Moss Library with effect from April 2014, as set out at section 4.1 of the report, be approved; (ii) that a formal agreement be entered into with Hugh Baird College regarding the transfer of Whiston Library to the College with effect from 1 April 2014, as set out in Sections 4.2 and 4.3 of the report; and (iii) subject to resolution (ii) above, the Deputy Chief Executive, in consultation with the Cabinet Member with Portfolio for Leisure, Community and Culture, be authorised to finalise the relevant formal agreement.
Word for word from the decision Knowsley published for this meeting. Source: councillors.knowsley.gov.uk

Follow this further

Built from Knowsley's papers

What the report saysPro

Report to Cabinet

Purpose of the report

This report updates the Cabinet on the progress made in assessing community interest in providing future library facilities in Page Moss and Whiston. The report summarises the current position and seeks approval in respect of the way forward for each Library.

Recommendations

Cabinet is recommended to:-

(i) Agree the closure of Page Moss Library with effect from 1 April 2014 as set out in section 4.1 of this report;

(ii) Agree to enter into a formal agreement with Hugh Baird College regarding the transfer of Whiston Library to the College with effect from 1 April 2014 as set out in sections 4.2 and 4.3 of this report; and,

(iii) Subject to (ii) above, authorise the Deputy Chief Executive in consultation with the Cabinet Member with Portfolio for Leisure, Community and Culture to finalise the relevant formal agreement. 3. BACKGROUND

3.1On 6 March 2013, the Council agreed the following actions in respect of the Library service as part of the Authority’s budget for 2013/14 and 2014/15:-

• No savings to be identified for the financial year 2013/14;

• The transfer to community use or closure of Page Moss and Whiston Libraries from the 2014/15 financial year; and,

• Reduced opening hours in the Borough’s remaining Libraries from the 2015/16 financial year.

3.2The total annual savings expected to be achieved via the above measures are £0.220m.

3.3The proposed closures of Page Moss and Whiston Libraries have also previously been identified as an element of the Council’s Corporate Property Plan, which was agreed by the Cabinet on 5 December 2012. The Cabinet report which accompanied the Corporate Property Plan stated clearly that, “Information and customer contact facilities (such as One Stop Shops, Libraries, Advice Centres etc) should be co-located and only be provided in Huyton, Kirkby, Halewood and Prescot to serve the Borough’s main urban areas.”

3.4With regard to the potential opportunities for the transfer of either library to community use/ownership, there are various models which the Council have explored. These include:-

• Totally Independent Community Libraries;

• Community Run with Council Support;

• Community Supported; and/or,

• Services Commissioned from External Community Organisations.

3.5Council officers examined how community-run libraries have been established in other local authority areas. Overall, there is no single model of community involvement in libraries. The best approach to community involvement in Knowsley would be the one that is most appropriate to the relevant local community’s needs, capacity and interest in being involved. 3.6 In order to comply with legal requirements and to ensure that all stakeholders had an opportunity to engage with the process, a consultation exercise involving library customers, employees, and other relevant groups, agencies and partner organisations was undertaken to inform the implementation and achievement of the savings proposals referred to in paragraph 3.1 above.

3.7Letters were issued to all Page Moss and Whiston Library users to inform them of the Council’s wish to explore the possibility of community-run libraries in both areas. The letters also contained the details of the planned public consultation meetings, which were also advertised on notice boards in both Libraries.

3.8Initially, four public consultation meetings were planned. Two further meetings subsequently took place. These meetings were added to the consultation timetable in response to comments made at the four scheduled meetings, whereby some attendees indicated that they believed that some members of the local communities may have been unaware of the meetings.

3.9In overall terms, the public meetings were not well attended as illustrated below:-

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
Page Moss and Whiston LibrariesReport 106 KB DownloadRead as text

At this meeting

Whole meeting

On this subject at Knowsley

Search all
  1. Page Moss and Whiston LibrariesThis decision
  2. The Pride In Place (Page Moss and Fincham) Programme and Pride in Place Impact FundApproved
  3. Connecting Communities - Page MossAgreed
  4. Connecting Communities Page MossAgreed

More from Knowsley Cabinet

All decisions
MeetingDecisionOutcome
15 Jul 2026 Kirkby Town Centre Investment (*)RESOLVED – That:- (i) the grant of a new lease in Kirkby Town Centre on the headline commercial terms detailed at App... Agreed Open
15 Jul 2026 2026/27 Revenue Budget - Quarter 1 Monitoring Update (*)RESOLVED – That:- (i) the key issues affecting 2026/27 budget monitoring as set out in this report be noted; and, (ii... Noted Open
15 Jul 2026 Capital Programme: 2026/27 Monitoring (*)RESOLVED – That the revised three-year Capital Programme of £118.011m in total as set out in section 4 and detailed i... Approved Open
15 Jul 2026 Local Government Association (Corporate Peer Challenge) - Progress Update on Delivery of Action PlanRESOLVED – That the draft Action Plan (attached at Appendix A) which sets out progress made to address the recommenda... Agreed Open
4 Jun 2026 2025/26 Revenue Budget Monitoring - Final Outturn Position (*)RESOLVED - That:- (i) the final 2025/26 budget monitoring position for the Council as set out in this report be noted... Noted Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies