RESOLVED – That (i) the progress made by services in 2013/14, as summarised at paragraph 3.3.2 of the report, be noted; (ii) the closure of the five strategic risks, as outlined in paragraph 3.4 of the report, be approved; (iii) the adoption of eleven new strategic risks, as outlined in paragraph 4.2 of the report, be approved; (iv) the Authority’s Strategic Risk Register for 2014/15, as outlined in paragraph 4.1 of the report and at Appendix A to the report, be approved; and (v) the key issues and progress at the 2014/15 mid-year stage, as outlined at paragraph 4.3 of the report and at Appendix A to the report, be noted. (Note: That, in accordance with Section 28(2) of the Localism Act 2011, and the Council’s Code of Conduct for Elected and Co-opted Members, Councillors E Connor, D Lonergan MRICS and R J Round declared a personal interest in the above item but remained in the meeting, took part in the discussion and voted thereon).
Word for word from the decision Knowsley published for this meeting.Source: councillors.knowsley.gov.uk
The purpose of this report is to outline the position at the end of 2013/14 in managing the Authority’s strategic risks, to recommend approval of the resulting Strategic Risk Register for 2014/15, and to note the key issues and risks as at the 2014/15 mid-year stage.
Recommendations
Members of the Cabinet are recommended to:-
(i) Note the progress made by services in 2013/14 as summarised at paragraph 3.3.2 of this report;
(ii) Approve the closure of the five strategic risks outlined in paragraph 3.4 of this report;
(iii) Approve the adoption of eleven new strategic risks as outlined in paragraph 4.2 of this report;
(iv) Approve the Authority’s Strategic Risk Register for 2014/15 as outlined in paragraph 4.1 of this report and at Appendix A to this report; and,
(v) Note the key issues and progress at the 2014/15 mid-year stage as outlined at paragraph 4.3 of this report and at Appendix A to this report. 3. BACKGROUND
3.1Risk management is an essential part of any organisation’s strategic management arrangements. It is the process whereby organisations methodically address the risks attached to their activities with the goal of achieving sustained benefit within each activity and across all activities. The focus of good risk management is the identification and treatment of these risks to reduce both the probability of failure and the uncertainty of achieving the organisation’s overall objectives.
3.2Given the current economic environment, the potential impact of the organisation’s ongoing Change and Transformation Programme, and the changing and challenging nature of the Authority’s strategic agenda, it is essential that effective risk management is practised alongside the Authority’s financial and performance management systems to enable the Council to demonstrate the adequacy of its governance arrangements and internal controls and maintain the effective use of its resources.
3.3Knowsley’s Strategic Risk Register - 2013/14 Outturn Position
3.3.1 The Strategic Risk Register for 2013/14 was approved by the Cabinet on 11 December 2013. In total, the Council started 2013/14 with 41 strategic risks on its Risk Register. The management of these risks was undertaken as part of the delivery of priorities within the relevant services’ business plans with sufficient resources allocated to enable the identified controls to be implemented.
3.3.2 Reviews were undertaken of all risks during the year in order to monitor progress and identify any emerging risks. A summary of the corporate risk profile during 2013/14 (before the proposed closures at outturn as outlined in paragraph 3.4) is set out in the table below:-
Opening Position at Position Risk Movement during 2013/14 Quarter 4 2013/14 2013/14 Reduced or Closed New Increased Risk Rating High 11 -3 1 0 9 Medium 24 -7 5 -1 21 Low 6 -1 0 +1 6 TOTAL 41 -11 6 0 36 3.4 Proposed Risk Closures
At the end of 2013/14, five risks (as detailed in the table below) have been proposed for closure either because they are no longer considered to represent risk to the Council or because it is proposed to replace them with new strategic risk descriptions which more accurately reflect the risks facing the Council at this point in time:-
Risk Director Risk Comment Rating Regeneration Stockbridge The Regeneration Programme Low and Housing Village has been delivered. Regeneration Programme
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Kirkby Town Centre Investment (*)RESOLVED – That:- (i) the grant of a new lease in Kirkby Town Centre on the headline commercial terms detailed at App...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.