Resolved
RESOLVED – That the Council formally adopt the Code of Practice on Treasury Management in Local Authorities (2011) and the 2015/16 Treasury Management Strategy as set out at Appendix A to the report now submitted.
Governance and Audit Committee approved this item on Tuesday 20 January 2015. Below is the council's own wording, with the papers it was decided on.
Resolved
RESOLVED – That the Council formally adopt the Code of Practice on Treasury Management in Local Authorities (2011) and the 2015/16 Treasury Management Strategy as set out at Appendix A to the report now submitted.
This report presents the Council‟s 2015/16 Treasury Management Strategy, including the Prudential and Treasury Indicators, Minimum Revenue Provision Policy Statement, and Annual Investment Strategy.
Members of the Committee are recommended to request the Council to formally adopt the Code of Practice on Treasury Management in Local Authorities (2011) and the 2015/16 Treasury Management Strategy as set out at Appendix A to this report.
3.1In accordance with best practice, the Council‟s Treasury Management Strategy is based upon the Chartered Institute of Public Finance and Accountancy‟s Code of Practice on Treasury Management in the Public Services (the CIPFA Treasury Management Code).
3.2Under the Code, the Council is required to obtain approval of its Treasury Management Strategy before the start of each financial year. In addition, the Department for Communities and Local Government (DCLG) issued revised guidance on Local Authority Investments in March 2010 that also requires the Council to obtain approval of its investment strategy before the start of each financial year. 3.3 The Council has borrowed and invested substantial sums of money and is therefore exposed to financial risks including loss of invested funds and the revenue effect of changing interest rates. The successful identification, monitoring and control of these risks are therefore central to the Council‟s Treasury Management Strategy.
3.4The Governance and Audit Committee is responsible for ensuring the effective review of the Treasury Management Strategy and performance during the year. Consequently, the Treasury Management Strategy for 2015/16 should be scrutinised by the Committee prior to the Council‟s approval.
4. THE TREASURY MANAGEMENT STRATEGY
4.1The proposed Treasury Management Strategy is attached at Appendix A and sets out the Council‟s current treasury management position and outlines the overall plans for the management and control of the Council‟s cash income and expenditure for 2015/16. The Strategy takes into account updated forecasts on interest rates and covers various aspects of the treasury management function including:-
identifying the controls and limits in place to minimise the risk of the treasury activities of the Council;
determining the Council‟s borrowing requirements for the year;
establishing the strategy for borrowing in terms of sources and types of loans;
setting an approach to be followed in the event of any rescheduling of debt which may be required;
outlining the Council‟s Minimum Revenue Provision Policy in line with regulations; and,
detailing the Annual Investment Strategy to be adhered to when placing funds on deposit.
4.2The Strategy includes Prudential and Treasury Indicators (Appendix A - Annex 1) which meet the requirement of the Local Government Act 2003 to ensure that all capital expenditure is prudent, affordable, and sustainable. These Indicators will form the basis of the monitoring of treasury management performance throughout the year. 4.3 Approach to Borrowing
4.3.1 A key aim of the proposed Treasury Management Strategy is that the Council should seek to minimise the cost of its debt portfolio, whilst ensuring that the obligation to repay loans is spread over a period of time. The Council‟s debt portfolio therefore comprises a range of loans (predominantly from the Public Works Loan Board (PWLB)) which are repayable over periods ranging from under one year to beyond 50 years. Currently, the weighted average rate of interest on the Council‟s total debt portfolio is 4.436% (comprised of rates between 2.500% and 7.375% over a range of periods).
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
PDF |
Treasury Management Strategy 2015/16Report | 368 KB | DownloadRead as text |
Follow Governance and Audit Committee at Knowsley and we tell you when its next papers are published, before the meeting rather than after it.
| Meeting | Decision | Outcome | |
|---|---|---|---|
| 15 Jun 2026 | Grant Thornton UpdateRESOLVED – That the content of the report and the update be noted. | Noted | Open |
| 15 Jun 2026 | Fraud Risk AssessmentRESOLVED – That (i) the methodology outlined in the report be endorsed; (ii) the prioritised fraud risks outlined in ... | Decided | Open |
| 15 Jun 2026 | Internal Audit Quality Assurance and Improvement ProgrammeRESOLVED – That (i) The outcomes of the Programme form 2025/26 set out in section 5 of the report be noted; (ii) the ... | Noted | Open |
| 9 Mar 2026 | Grant Thornton UpdateRESOLVED - That the content of the Grant Thornton report and update be noted. | Noted | Open |
| 9 Mar 2026 | Accounting Policies for the 2025/26 Statement of AccountsRESOLVED – That the Council’s 2025/26 accounting policies as detailed in the report be endorsed. | Decided | Open |
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Keeps you signed in and runs your free-paper allowance. Always on.
Counts visits and which pages are used. First-party only, no advertising, never shared.