Resolved
RESOLVED – That the observations and outcome from the inspection and particularly their positive comments on the improvements made since their previous assessment be noted.
Governance and Audit Committee noted this item on Tuesday 23 June 2015. Below is the council's own wording, with the papers it was decided on.
Resolved
RESOLVED – That the observations and outcome from the inspection and particularly their positive comments on the improvements made since their previous assessment be noted.
1.1The purpose of this report is to inform the Governance and Audit Committee of the findings of an inspection visit by the Care Quality Commission (CQC) of the Atkinson Grove Chance for Break Service.
2.1Members of the Governance and Audit Committee are recommended to note the observations and outcome from the inspection and particularly their positive comments on the improvements made since their previous assessment.
3.1By law providers of certain regulated health and social care activities must register with CQC. Providers must meet regulations under Health and Social Care Act 2008 (Regulated Activities) Regulations 2014 and Care Quality Commission (Registration) Regulations 2009.
3.2Knowsley Council has five Adult Social Care regulated activities, which include two adult respite homes. These homes support adults with a disability providing carer respite and also accommodate emergency referrals. There is one unit in Lydbury Crescent, Kirkby and one unit in Atkinson Grove, Huyton.
3.3On 13 March 2015 there was an announced inspection by CQC as part of their regulatory function of the Atkinson Grove Chance for Break Service. The inspection was planned to check whether the provider is meeting the legal requirements and regulations under Health and Social Care Act 2008, to look at the overall quality of the service and to provide a rating for the service under the Care Act 2014. The previous inspection on 27 September 2014 highlighted improvements required for two of the five areas:-
Providing Care, treatment and support to meet people’s needs. Quality and Suitability of management.
3.4Following this inspection, the service submitted an improvement plan to CQC. This plan did include the appointment of a new manager who registered with the Care Quality Commission in December 2014.
4. ASSURANCE VISIT PURPOSE AND FINDINGS
4.1The inspectors use professional judgement, supported by objective measures and evidence, to assess services against five key questions:-
Are they safe? Are they effective? Are they caring? Are they responsive to people’s needs? Are they well led?
4.2The inspection gathers evidence from a number of sources including:-
Intelligent Monitoring (including local information) On-site inspection Pre-inspection information gathering and, Speaking with the people who use the services, their families, carers and staff
4.3Services are rated on a traffic light system, as shown opposite:- 4.4 It is very pleasing to report that since the last visit in September 2014 the inspector found that the service has completed the improvements set out in the action plan and upgraded the rating from ‘requires improvement’ to ‘Good’ overall.
4.5The main feedback received was positive. Some of the inspectors comments are below:-
“People told us they felt safe and that they were treated well”
“People told us they liked the staff and that they were good at their job”
“People were treated with kindness and compassion”
“The service communicated well with people’s family members and other agencies to make sure people received the care and support they needed during their stay at the service”
“People who used the service and family members made positive comments about the registered manager and the way he managed the service”.
5. RESOURCE IMPLICATIONS
5.1Financial
There are no direct financial implications arising from this report.
5.2Human Resources
There are no direct human resource implications arising from this report.
5.3Information Technology
There are no direct information technology implications arising from this report.
5.4Physical Assets
There are no direct implications for the Council’s physical assets arising from this report.
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
PDF |
Appendix: Inspection Report: Matt Ashton CLEAREDAppendix | 241 KB | Download |
PDF |
Care Quality Commission Inspection (Atkinson Grove Chance For a BreakReport | 300 KB | DownloadRead as text |
Follow Governance and Audit Committee at Knowsley and we tell you when its next papers are published, before the meeting rather than after it.
| Meeting | Decision | Outcome | |
|---|---|---|---|
| 15 Jun 2026 | Grant Thornton UpdateRESOLVED – That the content of the report and the update be noted. | Noted | Open |
| 15 Jun 2026 | Fraud Risk AssessmentRESOLVED – That (i) the methodology outlined in the report be endorsed; (ii) the prioritised fraud risks outlined in ... | Decided | Open |
| 15 Jun 2026 | Internal Audit Quality Assurance and Improvement ProgrammeRESOLVED – That (i) The outcomes of the Programme form 2025/26 set out in section 5 of the report be noted; (ii) the ... | Noted | Open |
| 9 Mar 2026 | Grant Thornton UpdateRESOLVED - That the content of the Grant Thornton report and update be noted. | Noted | Open |
| 9 Mar 2026 | Accounting Policies for the 2025/26 Statement of AccountsRESOLVED – That the Council’s 2025/26 accounting policies as detailed in the report be endorsed. | Decided | Open |
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Keeps you signed in and runs your free-paper allowance. Always on.
Counts visits and which pages are used. First-party only, no advertising, never shared.