Decision on Appeal 16/00577/FUL Appeal against refusal of planning permission for the construction of 2 new 4 bed detached dwellings and relocation of existing parking provision for residential units on the site – Heyes Farm, Lower Road, Halewood L26 2XA. Appeal dismissed
Word for word from the decision Knowsley published for this meeting.Source: councillors.knowsley.gov.uk
by Andrew McGlone BSc MCD MRTPI an Inspector appointed by the Secretary of State for Communities and Local Government Decision date: 25 April 2017
Appeal Ref: APP/V4305/W/16/3167735 Hayes Farm, Lower Road, Halewood L26 2XA The appeal is made under section 78 of the Town and Country Planning Act 1990 against a refusal to grant planning permission. The appeal is made by [name removed] of MAC Roofing & Contracting Ltd against the decision of Knowsley Metropolitan Borough Council. The application Ref 16/00577/FUL, dated 23 August 2016, was refused by notice dated 15 December 2016. The development proposed is the Construction of 2 new 4 bed detached dwellings and relocation of existing parking provision for residential units on the site.
Decision
1. The appeal is dismissed.
Main Issues
2. The main issues are: (i) whether the proposed development would affect the comprehensive provision and delivery of infrastructure requirements for the East of Halewood Sustainable Urban Extension (EHSUE); and (ii) the effect of the proposed parking arrangement on the safety of vehicular and pedestrian traffic on Lower Road.
Reasons
Halewood SUE
3. The appeal site is a small part of the EHSUE off Lower Road. The site was previously allocated as Green Belt. However it was re-allocated as the EHSUE in the Knowsley Local Plan: Core Strategy (the Core Strategy). This was adopted in January 2017 to allow for a wider choice of housing and to meet the housing needs in south Knowsley.
4. The appellant accepts Core Strategy Policy SUE2 requires a comprehensive approach to development in the EHSUE. Nonetheless it is suggested by the appellant that the site could be developed without prejudicing the wider EHSUE for approximately 1,100 dwellings under the remit of Core Strategy Policy SUE2b, on the basis that the site is separated from the majority of the EHSUE by a fishing lake and open land covered with trees and shrubs.
5. Despite this Core Strategy Policy SUE2 is very clear that developments proposals within the EHSUE will only be granted planning permission where they are consistent with a single detailed master plan for the whole of the Appeal Decision APP/V4305/W/16/3167735
Sustainable Urban Extension which is approved by the Council. The master plan should accord with development plan policy and any associated Supplementary Planning Document and may be submitted prior to or with the application.
6. While the appellant considers this policy approach to be inflexible and crude, the Core Strategy has been justified through the examination process and has been subject to public consultation. Also, I understand that the Council is making progress with the Supplementary Planning Document (SPD) for the EHSUE and it intends to consult on this in May 2017, with the process being complete by the end of 2017. I also understand Bellway Homes are leading on the masterplan on behalf of the Council for the whole EHSUE. The Council would need to approve this in order to set out the spatial development framework for the site. Still, progress appears to be being made. Core Strategy Policies SUE2 and SUE2b also require that the whole EHSUE is brought forward comprehensively so site specific infrastructure provision for approximately 1,100 dwellings is delivered.
7. The proposal would be a relatively small part of the EHSUE. Thus it would be a piecemeal development which cannot be in accordance with a single detailed masterplan, as the SPD and master plan have yet to be approved by the Council, even with all landowners invited to take part in the process.
8. Central to the Council’s concern is part of the EHSUE being brought forward in a piecemeal manner. In the Council’s opinion this would mean that there is a significant risk to infrastructure provision not being comprehensively addressed and the full potential of the EHSUE being realised.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.