Resolved
RESOLVED – That the report be noted.
Council noted this item on Wednesday 28 June 2017. Below is the council's own wording, with the papers it was decided on.
Resolved
RESOLVED – That the report be noted.
The purpose of this report is to provide an update to the Council of the findings of a review of the multi-agency response to the fire at the Remondis site in Prescot on 4 December 2016 and to advise on the current position in respect of identifying the cause of the fire.
Members of the Council are recommended to note the report.
3.1The Remondis Waste Treatment Centre situated on Carr Lane in Prescot is regulated by the Health and Safety Executive and the Environment Agency. The site holds an Environmental Permit issued by the Environment Agency to enable the treatment, storage, transfer and disposal of hazardous waste materials.
3.2A fire broke out at the site just before 6.00am on Sunday 4 December 2016. The cause of the fire remains the subject of an ongoing investigation by the Health and Safety Executive and the Environment Agency (see paragraph 6.1 below). This report therefore relates to operations and activity once the fire was detected. 3.3 Initial notification of the incident was received from the Merseyside Fire and Rescue Service by the Council’s Emergency Duty Officer just before 7.00am. The fire was not declared a major incident by either Merseyside Police or the Merseyside Fire and Rescue Service and the local community was advised to “go/stay indoors and close windows and doors”.
3.4Throughout the day, the Council’s Emergency Duty Officer remained in regular contact with the Incident Commanders from both the Police and the Fire and Rescue Service, who were in turn in regular contact with Public Health England, the Environment Agency, NHS England and the Met Office. Public information was agreed and communicated through these channels.
3.5The Council’s Emergency Duty Officer sought to update Elected Members through a series of emails which followed the ongoing discussions with the Incident Commanders.
3.6At around lunchtime on the day, the Emergency Duty Officer was alerted to concerns being raised in the local media and on social media in relation to potential health and environmental risks from the fire.
3.7This prompted the Emergency Duty Officer to make further enquiries with the Emergency Services and with the relevant partner agencies. Those agencies again advised that the fire was not a major incident, that there were no significant longer term health risks from the fire, and that the advice to the public therefore remained as set out in paragraph 3.3 above.
3.8At around 5.00pm, the Police and the Fire and Rescue Service Incident Commanders advised the Council that they were scaling back their resources at the scene, although the fire would continue to burn for some time. This development was again communicated to Elected Members.
3.9On the following day (Monday 5 December 2016), the Emergency Duty Officer formed a multi-agency group to manage the ongoing response to and recovery from the fire. It was also agreed that a multi-agency review should take place with the involvement of all key partner agencies. It was agreed that this review should be facilitated by an independent person, and the Merseyside Resilience Forum Business Manager was approached to undertake the review as he is independent from any of the responding agencies in this incident. 3.10 As part of the review process and in accordance with views expressed by Members, the local Ward Councillors were approached for their views on the multi-agency response and on their sources of information on the day. As no response was received from the Ward Councilors, the review report was completed without their input and has now been shared with all partner agencies. The full report is attached at Appendix A and the key findings are discussed in section 4 below.
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
PDF |
Fire at Remondis Waste Treatment Centre: Appendix AAppendix | 555 KB | Download |
PDF |
Fire at the Remondis Waste Treatment Centre, Carr Lane, Prescot on 4 December 2016Report | 226 KB | DownloadRead as text |
Follow Council at Knowsley and we tell you when its next papers are published, before the meeting rather than after it.
| Meeting | Decision | Outcome | |
|---|---|---|---|
| 22 May 2026 | Election of Mayor 2026/27RESOLVED – That Councillor Edna Finneran be elected Mayor of the Borough of Knowsley for the Municipal Year 2026/27. ... | Decided | Open |
| 22 May 2026 | Vote of Thanks to Retiring MayorRESOLVED - That a Vote of Thanks be accorded to Councillor Ken McGlashan in appreciation of the excellent manner in w... | Decided | Open |
| 22 May 2026 | Election of Deputy Mayor 2026/27RESOLVED – That Councillor Joanne Burke be elected Deputy Mayor of the Borough for the Municipal Year 2026/27. The De... | Decided | Open |
| 22 May 2026 | Appointment of the Leader of the CouncilRESOLVED – That Councillor Graham Morgan be appointed Leader of the Council until the Annual Meeting of the Council i... | Decided | Open |
| 22 May 2026 | Vote of Thanks to Retiring MembersRESOLVED – That a Vote of Thanks be accorded to retiring Members – Denise Allen, Robert Austin, Dennis Baum, Harry Be... | Decided | Open |
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Keeps you signed in and runs your free-paper allowance. Always on.
Counts visits and which pages are used. First-party only, no advertising, never shared.