Resolved
RESOLVED – That the progression of the audit recommendations, as set out in the report, be noted.
Governance and Audit Committee noted this item on Monday 30 July 2018. Below is the council's own wording, with the papers it was decided on.
Resolved
RESOLVED – That the progression of the audit recommendations, as set out in the report, be noted.
The Internal Audit Service has reviewed progress on 67 audit recommendations that were due for implementation by March 2018. Good progress has been made, with all but two recommendations now implemented. The two recommendations still to be implemented now have revised implementation dates as shown in Appendix Two to this report.
The Committee is recommended to note the progress set out in this report.
3.1The Internal Audit Service undertakes a continuous review process to track the status of recommendations that have been made in audit reports. After each target date for implementation has passed, there is a follow-up period when Auditors contact service managers to request an update on progress.
3.2Any recommendations that remain outstanding at the end of the follow-up period are reported to this Committee until the recommendation is closed. This ensures that managers are accountable for taking the required action to strengthen internal controls. 3.3 Progress of recommendations
3.3.1 The Internal Audit Service has monitored the progress of recommendations due to be implemented by March 2018. Good progress has been made and all but two recommendations, both from the review of Deputeeship and Appointeeship Processes, are now implemented as shown below.
Priority Critical High Medium Total no. % no. % no. % no. % Implemented 4 67 21 100 40 100 65 97 Not implemented 2 33 0 0 0 0 2 3 Total 6 100 21 100 40 100 67 100
3.3.2 The two recommendations still to be implemented are both judged to be critical, and relate to the transfer of banking arrangements for Client Accounts to Barclays Bank. Discussions have been held with the Service Manager, Adult Social Care and Barclays Bank to identify what steps can be taken to accelerate these recommendations. This is detailed in Appendix 2.
3.3.3 The programme of follow-up work will now move on to reviews with recommendations to be implemented prior to June 2018 as shown below. Progress on these will be reported to this Committee in September 2018.
Audits with a final implementation date of June 2018 - to be reviewed between July and September 2018 Part Time Staff Leave Process Review Evelyn Community Primary School Park Brow School Business Rates Recruitment of Agency Staff and Consultants Budget Monitoring – Property Management Contract Compliance – Travel Support Awareness of Safeguarding Processes Financial Decision Making – Panel Process Halewood Holy Family Catholic Primary School Kirkby CE Primary School St Annes Catholic Primary School St Margaret Marys Catholic Infant School St Mary and St Paul CE Primary School Huyton Resource Centre Imprest Account Reconciliation Home to School Transport – Review of Costings
4. RESOURCE IMPLICATIONS
4.1Financial Resources
The improvements to the internal control environment as a result of the audit work will result in more effective stewardship of the Council’s resources. 4.2 Other Resources
There are no other resource implications arising from this report.
5. EQUALITY AND SOCIAL VALUE IMPACT
5.1Equality and Diversity
An Equality Impact Assessment (Appendix 2) has been completed which has identified that there are no implications arising from this report.
5.2Social Value
There are no Social Value outcomes arising from this report.
6. COMMUNICATION ISSUES
The results of the internal audit review of previous recommendations have been communicated to and discussed with the relevant officers.
KAREN HOGAN Chief Internal Auditor
Contact Officers: Steve Liptrot - 0151 443 3667 Karen Hogan – 0151 443 3646
Appendix:-
Appendix 1 – Recommendations still to be implemented Appendix 2 – Equality Impact Assessment
Background Documents:- None
Suggested Background Reading:- None
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
PDF |
Implementation of RecommendationsAppendix 1 | 372 KB | Download |
PDF |
EIA: Implementation of RecommendationsAppendix 2 | 274 KB | Download |
PDF |
Implementation of Internal Audit RecommendationsReport | 127 KB | DownloadRead as text |
Follow Governance and Audit Committee at Knowsley and we tell you when its next papers are published, before the meeting rather than after it.
| Meeting | Decision | Outcome | |
|---|---|---|---|
| 15 Jun 2026 | Grant Thornton UpdateRESOLVED – That the content of the report and the update be noted. | Noted | Open |
| 15 Jun 2026 | Fraud Risk AssessmentRESOLVED – That (i) the methodology outlined in the report be endorsed; (ii) the prioritised fraud risks outlined in ... | Decided | Open |
| 15 Jun 2026 | Internal Audit Quality Assurance and Improvement ProgrammeRESOLVED – That (i) The outcomes of the Programme form 2025/26 set out in section 5 of the report be noted; (ii) the ... | Noted | Open |
| 9 Mar 2026 | Grant Thornton UpdateRESOLVED - That the content of the Grant Thornton report and update be noted. | Noted | Open |
| 9 Mar 2026 | Accounting Policies for the 2025/26 Statement of AccountsRESOLVED – That the Council’s 2025/26 accounting policies as detailed in the report be endorsed. | Decided | Open |
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Keeps you signed in and runs your free-paper allowance. Always on.
Counts visits and which pages are used. First-party only, no advertising, never shared.