RESOLVED – That:- ( i ) the Council be authorised to enter into a Grant Funding Agreement with the Liverpool City Region Combined Authority in relation to the Local Growth Fund Key Route Network scheme for Bank Lane Corridor in Kirkby; and (ii) the Head of Legal Services be authorised to finalise the terms of the Grant Funding Agreement referenced in ( i ) above and the addition of the Bank Lane Corridor scheme into the Council’s Highways and Transportation Capital Programme. (Note: That in accordance with Section 28(2) of the Localism Act 2011 and the Council’s Code of Conduct for Elected and Co-Opted Members, Councillor G Morgan declared a Disclosable Pecuniary Interest in the above item of business and left the meeting for the duration of its consideration. At the conclusion of the item Councillor G Morgan returned to the meeting and retook the Chair.) Councillor G Morgan Chairperson of the Cabinet ( in the Chair)
Word for word from the decision Knowsley published for this meeting.Source: councillors.knowsley.gov.uk
1.1In accordance with the Council’s Constitution, this report seeks approval to invest in the delivery of the Key Route Network scheme for Bank Lane Corridor in Kirkby and to authorise its addition to the Council’s Capital Programme following a grant funding award from the Liverpool City Region Combined Authority’s Local Growth Fund.
1.2The associated Grant Funding Agreement contains several conditions and clauses which place obligations on the Council. Successful delivery of the scheme will directly support the Council’s wider objective of regenerating Kirkby town centre, secure significant economic benefits, and improve traffic flow in the area.
Recommendations
Members of the Cabinet are recommended to:-
a) Authorise the Council to enter into a Grant Funding Agreement with the Liverpool City Region Combined Authority in relation to the Local Growth Fund Key Route Network scheme for Bank Lane Corridor in Kirkby; and,
b) Authorise the Head of Legal Services to finalise the terms of the Grant Funding Agreement referenced in (a) above and the addition of the Bank Lane Corridor scheme into the Council’s Highways and Transportation Capital Programme. 3. BACKGROUND
3.1Following a successful bid to Liverpool City Region Combined Authority, the Council has been awarded £2m to undertake a highway scheme to improve traffic flow and network resilience on the Bank Lane Corridor in Kirkby, which forms part of the Liverpool City Region Key Route Network. The Bank Lane Corridor scheme forms part of the Liverpool City Region Single Investment Fund Local Growth Fund 3 award.
3.2A description of the works is summarised in the table below and in the drawings attached at Appendices A, B and C to this report. A further overview drawing to illustrate how the proposed schemes are interlinked is attached at Appendix D to this report. It should be noted that the overview drawing at Appendix D also makes reference to the junction of Shevington’s Lane and Bank Lane – the latter is an aspirational scheme and not included as part of the project described in this report:-
Location Proposed Works Benefits Increase the number of northbound Improved junction capacity approach lanes by and traffic flow widening the carriageway Reduced maintenance and Upgrade traffic Signalised electrical power supply signals crossroad costs junction of Bank Provide residents with a Lane, Boyes place to park away from the Brow and main carriageway, currently Construct a layby on Headbolt Lane vehicles park on the traffic Boyes Brow signal detection loops which impacts on the operation of the traffic signals Improved carriageway Resurface condition, reduced future carriageway maintenance costs Increase the number of northbound and Improved junction capacity southbound approach Signalised and traffic flow lanes by widening the junction of Bank carriageway Lane and St Construct a Kevin’s Drive Improved pedestrian pedestrian island to accessibility across the the south of the junction junction Improved carriageway Resurface condition and reduced carriageway future maintenance costs Signalised Upgrade traffic Improved cyclists crossing on Bank signals from puffin accessibility across Bank Lane near Melling crossing to a toucan Lane Drive crossing Improved carriageway Resurface condition and reduced carriageway future maintenance costs
3.3To enable the works to be undertaken, it is proposed that the Council will utilise its existing construction contracts with Tarmac, Scottish Southern Energy, and Siemens, as well as using the Merseytravel framework contract as a method of procuring competitive tenders as and when required.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Kirkby Town Centre Investment (*)RESOLVED – That:- (i) the grant of a new lease in Kirkby Town Centre on the headline commercial terms detailed at App...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.