Item8
Resolved
RESOLVED – That (i) The outcomes of the Quality Assurance and Improvement Programme from 2022/23 as summarised in section 4 of the report be noted; (ii) The actions arising from the Internal Audit Peer Review as detailed in Appendix E to the report be noted; and (iii) The proposals for the 2023/24 Quality Assurance and Improvement Programme outlined in section 5 of the report be endorsed.
Word for word from the decision Knowsley published for this meeting.
Source: councillors.knowsley.gov.uk