Financial Planning Report: Allocating Resources to Outcomes

Agreed Key decision Executive 7 papers

Cabinet agreed this item on Monday 14 July 2014. Below is the council's own wording, with the papers it was decided on.

Item5

Resolved

RESOLVED : 1) To agree the approach to Resource Allocation being developed to support co-operative commissioning and to direct Outcome Panels to develop commissioning plans and capital investment proposals to deliver outcomes within the resource envelopes set out in Section 2. 2) To re-affirm the Council’s commitment to delivering the existing revenue savings plans for 2014/15 (£25.4m savings) and 2015/16 – 2016/17 (£37.6m savings) as set out in paragraphs 2.5 to 2.13. 3) To note the 2013/14 General Fund outturn of £332.45m against a budget of £332.66m. 4) To note the balanced outturn for the 2013/14 HRA. 5) To note the 2013/14 Capital Investment Programme outturn of £183.6m against a budget of £186.0m and note the overview of Capital Investment of £543m over the four years to 2013/14 in Appendix 6. 6) To note the key revenue risks for 2014/15 as set out in paragraph 4.27 onwards. 7) To recommend approval of the revenue virements set out in paragraphs 4.36 and 4.37. 8) To agree the ... view the full minutes text for item 5.
Word for word from the decision Lambeth published for this meeting. Source: moderngov.lambeth.gov.uk

Follow this further

Built from Lambeth's papers

What the report saysPro

Report to Cabinet, 31 pages

Cabinet 14 July 2014

Council 23 July 2014

Financial Planning Report – Allocating Resources to Outcomes

Wards: All

Report Authorised by: Strategic Director Enabling: Guy Ware

Portfolio: Deputy Leader (Finance & Investment) Investment): Councillor Paul McGlone:

Contact for enquiries: [email protected] Frank Higgins, Head of Financial Strategy, Strategic Finance, 020 7926 9316

Report summary

1.1Introduction - The February Budget Report outlined the Council’s need to find savings to address a 3 3- year funding deficit of £96m for the period 2014/15 2014/ to 2016/17. This was part of the rolling series of budget reductions that have been made since the Government began its its programme of public sector austerity in 2010. For the period 2010/11 to 2016/17, the Council estimated that core funding from Government would have reduced by approximately 50%. The Council has now extended its assumptions on core funding and unavoidabl unavoidable pressures to 2017/18 and has revised its saving requirement to cover this period.

1.2Of the original savings target of £96m, £25 £25.4m 4m has been delivered for 2014/15. The position has been updated to identify a funding deficit of £90.4m over the period 2015/16 to 2017/18. 2017/18 This report has requested that the indicative savings of £37.6m identified for 2015/16 and 2016/17 be confirmed, resulting in a remaining savings target of £52.8m .

1.3The Government plans to maintain this programme in order to achieve a balanced national budget by 2019.. Independent observers, including the Institute of Fiscal Studies, conclude that, while the cuts to date have been severe, we are only about a third of the way through the programme: we will see cuts at least as heavy as those ose already experienced over the next few years. With continuing relative protection of some budgets such as Health, Schools, and Pension-age Pension age welfare, there is no reason to suppose that Local Government will not continue to be amongst the hardest hit.

1.4In 2014/15 014/15 we introduced a new process of “Outcome-Based “Outcome Based Budgeting (OBB)” to help support the council’s commissioning approach and address the huge reduction in available resources. This process aligned resources to the thirteen outcomes identified in the Community Community Plan. Following the local elections, the council has the opportunity to set out a four-year four year view of its ambitions and the financial planning approach needed to underpin them. The new Cabinet has established three Outcome Panels to lead the work of commissioning mmissioning and delivering outcomes under three headline areas. We now need to build on the OBB process to help the Panels consider the total resources available – the Council’s gross revenue spend; its s capital assets and potential investment; and the resources res of our partners and communities – to secure the best possible deployment of the resources we will have available. At the same time, in order to set the budget each year, we need to ensure effective target-setting target and control of the Council’s net revenue enue spending. 1 1.5 Having set this year’s budget in February, Section 2 (Resource Allocation) of this report rolls forward our medium term financial view to 2017/18. It indicates a potential General Fund revenue funding deficit of £90.4m over the three years 2015/16 to 2017/18. However, the 2014/15 OBB process identified indicative savings for 2015/16 and 2016/17 which it is currently estimated will reduce that deficit by £37.6m, leaving a revised revenue deficit of £52.8m to 2017/18.

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
05b Appendix 1: Activities under each of the Outcome Panels: FP: ARAppendix 2 pages Download
PDF
05c Appendix 2: Commissioning Proposals and Revised Savings v10Appendix 12 pages Download
PDF
05d Appendix 3: Financial Management Strategy Update FPR v4Appendix 8 pages Download
PDF
05e Appendix 4: 3 Year Capital Investment Programme 2014-15: 2016-17Appendix 2 pages Download
PDF
05f Appendix 5: 2013-14 Capital Outturn and Explanation of VariancesAppendix 1 pages Download
PDF
05g Appendix 6: Overview of the Capital Programme 2010-11: 2013-14Appendix 1 pages Download
PDF
Financial Planning Report: Allocating Resources to OutcomesReport 31 pages DownloadRead as text

At this meeting

Whole meeting

On this subject at Lambeth

Search all
  1. Financial Planning Report: Allocating Resources to OutcomesThis decision
  2. Business and Financial Planning 2025/26 - Health and Care Plan ReviewNoted
  3. Financial Planning Report 2019/20 to 2023/24Decided
  4. Financial Planning and Medium Term Strategy Report 2019/20 to 2023/24Approved
  5. Financial Planning and Medium Term Strategy Report 2017/18 to 2019/20Agreed
  6. Financial Planning Report 2016/17 and 2019/20Agreed

More from Lambeth Cabinet

All decisions
MeetingDecisionOutcome
23 Sep 2026 Minutes of Previous MeetingUnanimously, that the minutes of the previous meeting held on 22 July 2026 be approved and signed by the Chair as a c... Approved Open
22 Jul 2026 Minutes of Previous MeetingRESOLVED : That the minutes of the previous meeting held on 1 July 2026 be approved and signed by the Chair as a corr... Approved Open
1 Jul 2026 Minutes of Previous MeetingIt was agreed that consideration would be given to whether an explanatory asterisk could be inserted. RESOLVED : That... Agreed Open
23 Mar 2026 Minutes of Previous MeetingRESOLVED : That the minutes of the previous meeting held on 23 February 2026 be approved and signed by the Chair as a... Approved Open
23 Feb 2026 Minutes of Previous MeetingRESOLVED : That the minutes of the previous meeting held on 02 February 2026 be approved and signed by the Chair as a... Approved Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies