Update on the Council's Action Plan response to the External Auditor Recommendations under paragraph 2 of Schedule 7 of the Local Audit and Accountability Act 2014

Decided Committee 2 papers

AI summaryLambeth Corporate Committee reviews progress on its Action Plan responding to the external auditor's statutory recommendations and agrees to close several completed actions, with a fuller financial update due in March 2026.

AI summaryIn plain English

Written from the decision and the officer reportPDF Pro
OutcomeDecidedClosed 9 actions from prior meeting's list
MoneyNot stated
What happens nextFull financial impact update in March 2026Timing limited by January Committee vs late February Cabinet
Who it affectsCouncil finances and Lambeth residentsEspecially users of temporary accommodation and social care services

What was decided

The Committee considered the Action Plan (Appendix A) showing progress against the external auditor Forvis Mazars' statutory recommendations and agreed to close the listed actions as implemented. Report P1, 2.11, P6

It noted that further financial impact from continued work will be reported at the March 2026 Committee, as this January meeting falls before the late February Cabinet. Report 2.10

The Action Plan update will remain a standing agenda item, with the Committee continuing to receive regular progress reports. Report P2

Why

Forvis Mazars issued written recommendations under section 24 and Schedule 7 of the Local Audit and Accountability Act 2014 in February 2025, after acknowledging the Council's extremely challenging financial situation and significant demand pressures, particularly on Temporary Accommodation and the Housing Revenue Account. Report P2

The Council has faced a real-terms funding cut of more than 28% since 2010, equating to £116m a year less for local services, alongside generational-high inflation and rising demand in adults' and children's social care. Report P2

An Exceptional Financial Support application has been submitted to Government, intended to be funded through asset disposals rather than borrowing over the medium term. Report P3

What happens next

A full update on the impacts of work to address the statutory recommendations will be reported to the Committee in March 2026. Report 2.10

A pipeline of asset disposals is being built to fund transformation work and any Exceptional Financial Support, alongside a flexible use of capital receipts policy. Report P3

Further actions from the remaining statutory recommendations will continue to be implemented and reported through the standing Action Plan item. Report 2.11

The money

  • £15m a year Plan to rebuild reserves through the Medium-Term Financial Strategy Report P3
  • more than 28% Real-terms cut in Council funding since 2010 Report P2
  • £116m a year Equivalent amount now less to spend on local services Report P2
  • circa £45m Target to increase General Fund Balances to 10% of net revenue expenditure over three years Report P6

Options considered

  • Chosen: Agree to close the listed actions as implemented. Committee previously assured of actions taken to implement them Report 2.11, P6
  • Rejected: Fund any Exceptional Financial Support through borrowing over the medium term. Council plans to fund it through the disposals programme rather than borrowing

Implications

  • Financial: Council is reporting an overspend for 2025-26 but it is significantly lower than the 2024-25 year-end position, and key demand-led areas are not increasing month on month. Report P3
  • Financial: A pause on the capital programme is in place to reduce borrowing costs, and a third party external review of the MTFS is being carried out for independent assurance. Report P3
  • Financial: Spend controls are fully operational, with stricter approval limits planned, and service-based panels cover Housing, Adult Social Care and Children's Services. Report P3, P6
  • Legal: The Committee retains the Constitutional power to monitor progress under its Terms of Reference, and there is no legal reason preventing adoption of the recommendation. Report P7
  • Equalities: An Equalities Impact Assessment is not required for this report; the Council has paid due regard to equalities under the Equality Act 2010 in its wider work. Report P10, P11
  • Risk: Risk implications will be addressed through the Council's existing risk management arrangements. Report P9
  • Staffing: Spending controls aimed at minimising avoidable staffing and non-staffing expenditure remain in place, with quarterly impacts reported. Report P3, P6
  • Other: There are no community safety or child-related implications arising from the report. Report P12

Who and where

  • Lambeth Council as a whole, particularly its General Fund and Housing Revenue Account Report P2
  • Households needing temporary accommodation, which has reached unprecedented demand across London Report P2, P3
  • Adults and children using social care services in Lambeth Report P2, P3
  • Council staff affected by spending controls and transformation work Report P3, P6

Timeline

  • Since 2010: Council funding reduced by more than 28% in real terms Report P2
  • February 2025: Statutory recommendations issued by Forvis Mazars under the Local Audit and Accountability Act 2014 Report P3, P2
  • July 2025: Updated MTFS report and early year-end forecast presented to Cabinet Report P6
  • January 2026: This Corporate Committee meeting reviews the Action Plan and closes listed actions Report P1, P16
  • Late February (Cabinet) and March 2026 (Corporate Committee): Further updates on financial impact to be reported Report 2.10

Plain English for the jargon

  • MTFS: Medium-Term Financial Strategy, the Council's multi-year financial planning framework
  • EFS: Exceptional Financial Support, additional government support for councils facing severe financial pressure
  • Statutory Recommendations (SR): Written recommendations issued by the external auditor under Schedule 7 of the Local Audit and Accountability Act 2014
  • Homes for Lambeth: The Council's housing delivery vehicle, whose financial implications are being brought in-house
What was decided, why, and what happens next

Pro reads every officer report for you and explains each decision in plain English: the money, the options, the risks, the timeline, each with the paragraph it came from.

Written by AI from the council's published papers. AI can get things wrong: the council's own wording below is the record.Report a problem
Item4

Resolved

Corporate Committee ... view the full minutes text for item 4.
Word for word from the decision Lambeth published for this meeting. Source: moderngov.lambeth.gov.uk

Follow this further

Built from Lambeth's papers

What the report saysPro

Report to Corporate Committee, 7 pages

Recommendations

1. To consider and review the progress set out in the Action Plan (Appendix A) and agree to close actions where indicated. 1. CONTEXT 1.1 As well as giving an opinion on the financial statements and assessing the arrangements for securing economy, efficiency, and effectiveness in the Council's use of resources, the external auditors have additional powers and duties under the Local Audit and Accountability Act 2014. These include powers to issue a public interest report, make written recommendations, apply to the Court for a declaration that an item of account is contrary to law, and to give electors the opportunity to raise questions about the Council's accounts and to raise objections received in relation to the accounts.

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
Action PlanAppendix A 15 pages Download
PDF
Update on the Council's Action Plan response to the External Auditor Recommendations under paragraph 2 of Schedule 7 of the Local Audit and Accountability Act 2014Report 7 pages DownloadRead as text

At this meeting

Whole meeting

On this subject at Lambeth

Search all
  1. Update on the Council's Action Plan response to the External Auditor Recommendations under paragraph 2 of Schedule 7 of the Local Audit and Accountability Act 2014This decision
  2. Annual Governance Statement 2024/25 Action Plan UpdateDecided
  3. Corporate Committee Effectiveness Review and Action PlanApproved
  4. Empty Homes and Voids Action PlanApproved
  5. IICSA Action Plan delivery updateNoted
  6. IICSA Action Plan Delivery UpdateAgreed

More from Lambeth Corporate Committee

All decisions
MeetingDecisionOutcome
26 Mar 2026 MinutesThe minutes of the meeting held on the 4 February 2026 were agreed unanimously as a correct record of proceedings, su... Agreed Open
26 Mar 2026 Work Programme and Action Monitoring Log 2025 - 2026that the Committee: Agreed the Audit and Risk Committee’s work programme for 2026 - 2027 (Appendix A). To consider an... Agreed Open
26 Mar 2026 Final Statement of Accounts 2024-25, update on 2025-26 Statement of Accounts and update on Closedown and Accounts Improvement Planthat the Committee: Considered the changes made to the final Statement of Accounts 2024/25 between the Corporate Comm... Decided Open
26 Mar 2026 Annual Governance Statement 2024/25 Action Plan Updatethat the Committee considered the progress made against the issues and challenges identified in the 2024/25 Annual Go... Decided Open
26 Mar 2026 Internal Audit Progress Report 2025-26that the Committee considered progress made against the 2025/26 Internal Audit plan as well as progress with the impl... Decided Open