35 – 43 Bondway London (Vauxhall) 25/02795/FUL

Agreed Planning 1 paper

AI summaryLambeth Planning Applications Committee unanimously grants permission to change 35 to 43 Bondway from a hostel for single homeless men to a 209 bed space visitor hostel, subject to a Section 106 deed.

AI summaryIn plain English

Written from the decision and the officer reportPDF Pro
OutcomeAgreedUnanimous, subject to Section 106 agreement
MoneyNot stated
What happens nextSection 106 deed within six monthsOr director may refuse by delegated authority
Who it affects35 to 43 Bondway, VauxhallFour storey building in Vauxhall Conservation Area

What was decided

The committee resolved unanimously to grant conditional planning permission for a change of use from hostel for single homeless men to hostel for visitor accommodation, providing 209 bed spaces, with associated external works for cycle parking and a refuse store. Report P1, P2, P9, P41

Authority was delegated to the Director of Planning and Sustainability to finalise conditions and to negotiate, agree and complete the Section 106 planning obligations. Report P2

If a satisfactory Section 106 deed is not completed within six months of the committee meeting, delegated authority is given to the Director of Planning and Sustainability to refuse planning permission. Report P2

Why

The existing hostel for single homeless men has been vacant for around seven years and housing colleagues consider that equivalent provision for single homeless men exists nearby at Martha Jones House and the Lambeth Assessment Centre at 11 Bondway, so the loss is considered to meet the tests in policies H8 and H9. Report P150, P151, P152, P153, P154

The proposed visitor hostel supports the Central Activities Zone, the Vauxhall Cross retail cluster and the Vauxhall, Nine Elms and Battersea Opportunity Area, and no other hostel of this type exists in Vauxhall, so it would add to the mix of uses. Report P10, P158, P163, P164, P170

Noise, agent of change and management measures are judged sufficient to protect neighbouring amenity and to allow the adjacent nightclub to continue without unreasonable restrictions, supported by a Hostel Management Plan, Noise Impact Assessment and Delivery and Servicing Plan. Report P11, P12, P193, P201, P206, P207, P211, P212

What happens next

The applicant must complete a Section 106 deed within six months of 23 June 2026, securing car parking permit free status, the Be Seen energy monitoring obligation, and any other obligations the Director considers necessary. Report P2, P181, P220

Conditions require a final Operational Management Plan, a Construction Environmental Management Plan, a Delivery and Servicing Plan, cycle and waste storage details, noise and vibration attenuation, a lighting scheme, an energy strategy, and a wheelchair accessibility statement, to be discharged before or after occupation as specified. Report P7, P12, P40, P41, P182, P194, P199, P200, P203, P210, P224, P225, P226

If the Section 106 deed is not completed within six months, the Director of Planning and Sustainability may refuse the application under delegated authority. Report P2

Options considered

  • Chosen: Grant conditional planning permission subject to a Section 106 deed, as recommended by officers. Loss of existing hostel justified by long vacancy and nearby alternative provision, and the proposed visitor hostel complies with policy ED14 and other relevant policies. Report P2, P153, P154, P171
  • Rejected: Refuse planning permission. Officers found the application compliant with the development plan subject to conditions and obligations. Report P14, P171

Implications

  • Legal: A Section 106 deed under the Town and Country Planning Act 1990 is required, and a range of planning conditions must be finalised and discharged. Report P2
  • Climate: The development would achieve a 22 percent on site improvement over baseline regulated CO2 emissions, below the 35 percent policy target but considered proportionate for a change of use, with an all electric heating system. Report P13, P25, P177, P179, P182
  • Other: A Hostel Operational Management Plan, Delivery and Servicing Plan and Construction Environmental Management Plan are required to manage impacts on neighbours and the transport network. Report P11, P12, P201, P203, P225, P226
  • Equalities: The application was considered under the equality duty; the proposal meets building regulations accessibility requirements and a condition secures wheelchair accessibility. Report P9, P159, P7
  • Risk: Fire exits onto the neighbouring site are to be alarmed to prevent inappropriate use and protect the security of the adjacent nightclub, applying the agent of change principle. Report P72, P211, P212
  • Staffing: The hostel is to be managed, supervised and secured 24 hours a day, 7 days a week, with a staffed reception and code of conduct for operators. Report P156, P202, P204
  • Financial: The hostel will be secured as car parking permit free under the Section 106 deed, and the Be Seen energy monitoring obligation is to be secured by planning obligation. Report P105, P181, P220

Who and where

  • The applicant, Macro Investments Ltd Report P1
  • Future guests of the 209 bed space visitor hostel Report P9, P41
  • The neighbouring Fire Nightclub, whose operations must not be unreasonably restricted Report P31, P206, P212
  • Residents of nearby properties, with 47 properties consulted and 2 objections received Report P30, P63, P64, P65
  • Transport for London as highway authority for the adjacent red route and Vauxhall Bus Station Report P31, P82, P108
  • Users of the Vauxhall Conservation Area Report P16, P32

Timeline

  • 19 September 2025: Initial site notice and press notice posted Report P63
  • 10 October 2025: Initial statutory public consultation ended Report P63
  • 12 March 2026: Description of development amended to specify visitor accommodation Report P43, P44, P45
  • 16 March 2026: Re consultation site notice posted Report P64
  • 20 March 2026: Re consultation press notice posted Report P64
  • 10 April 2026: Re consultation statutory period ended Report P64
  • 21 May 2026: Legal services cleared the report Report P28
  • 23 June 2026: Planning Applications Committee resolved to grant conditional permission
  • Within six months of 23 June 2026: Section 106 deed to be completed, otherwise delegated refusal Report P2

Plain English for the jargon

  • Sui Generis: A planning use class for uses that do not fall within any standard defined use class.
  • Section 106 deed: A legal agreement under Section 106 of the Town and Country Planning Act 1990 used to secure planning obligations from a developer.
  • PTAL: Public Transport Accessibility Level, a score from 0 to 6b indicating access to public transport.
  • CAZ: Central Activities Zone, a London Plan designation covering central London's main commercial core.
  • Agent of change: The principle that a new noise sensitive development must put in place measures to protect itself from existing noise generating uses nearby.
  • Be Seen: The London Plan energy stage requiring monitoring and reporting of energy performance in use.
  • CPZ: Controlled Parking Zone, an area where on street parking is regulated by permits.
  • CEMP: Construction Environmental Management Plan, setting out how construction impacts will be controlled.
  • DSP: Delivery and Servicing Plan, setting out how deliveries and servicing will be managed.
  • BREEAM: Building Research Establishment Environmental Assessment Method, a sustainability rating for buildings.
  • LCDS: London Cycle Design Standards, TfL guidance on cycle parking design.
What was decided, why, and what happens next

Pro reads every officer report for you and explains each decision in plain English: the money, the options, the risks, the timeline, each with the paragraph it came from.

Written by AI from the council's published papers. AI can get things wrong: the council's own wording below is the record.Report a problem
Item5

Resolved

RESOLVED Unanimously, To grant conditional planning permission subject to the completion of a satisfactory deed under Section 106 of the Town and Country Planning Act 1990 containing the planning obligations as set out in this report, addenda and/or PAC minutes. Agree to delegate authority to the Director of Planning and Sustainability to: (a) Finalise the conditions incorporating those set out in this report, addenda and/or PAC minutes; and (b) Negotiate, agree and finalise the planning obligations as set out in this report, addenda and/or PAC minutes pursuant to Section 106 of the Town and Country Planning Act 1990. In the event that a satisfactory Section 106 deed is not completed within six months of the date of the Committee meeting (or such extended period as may be agreed in writing by the Local Planning Authority), delegated authority is given to the Director of Planning and Sustainability to refuse planning permission for failure to enter into a satisfactory Section 106 165 - 212 deed securing the obligations considered necessary to make the development acceptable in planning terms as identified in this report, addenda and/or the PAC minutes.
Word for word from the decision Lambeth published for this meeting. Source: moderngov.lambeth.gov.uk

Follow this further

Built from Lambeth's papers

What the report saysPro

Report to Planning Applications Committee

Application for Planning Permission Application ref: 25/02795/FUL Site: 35 – 43 Bondway London SW8 1SJ Ward: Vauxhall Description: Change of use from hostel for use by single homeless men (Sui Generis) to hostel for use as visitor accommodation (Sui Generis) and associated external works including cycle parking and a refuse store. Applicant: Macro Investments Ltd Agent: Turley Case officer: Jo Broadbent Drawing nos. See appendix 2 Reason for PAC referral: 2.5.1(b) the construction or alteration of a building or buildings where the floorspace (measured by gross internal area) to be provided is 1,000 square metres or more, or a change of use of land and/or a building/buildings amounting to 1,000 square metres or more

Recommendations: 1. Resolve to grant conditional planning permission subject to the completion of a satisfactory deed under Section 106 of the Town and Country Planning Act 1990 containing the planning obligations as set out in this report, addenda and/or PAC minutes. 2. Agree to delegate authority to the Director of Planning and Sustainability to: (a). Finalise the conditions incorporating those set out in this report, addenda and/or PAC minutes; and (b). Negotiate, agree and finalise the planning obligations as set out in this report, addenda and/or PAC minutes pursuant to Section 106 of the Town and Country Planning Act 1990. 3. In the event that the Committee resolves to refuse planning permission and there is a subsequent appeal, delegated authority is given to the Director of Planning and Sustainability, having regard to this report, addenda and/or PAC minutes, to propose planning conditions and to negotiate and complete a deed securing obligations pursuant to Section 106 of the Town and Country Planning Act 1990 in order to meet the requirements of the Planning Inspector. 4. In the event that a satisfactory Section 106 deed is not completed within six months of the date of the Committee meeting (or such extended period as may be agreed in writing by the Local Planning Authority), delegated authority is given to the Director of Planning and Sustainability to refuse planning permission for failure to enter into a satisfactory Section 106 deed securing the obligations considered necessary to make the development acceptable in planning terms as identified in this report, addenda and/or the PAC minutes. CONTENTS

Section no. Section description

1 Summary of application 1.1 Executive summary 1.2 Relevant designations 1.3 Key information 1.4 Summary of consultation

2 Site context and proposal 2.1 Site description 2.2 Proposal description 2.3 Relevant planning history

3 Consultation and engagement 3.1 Application consultation – public consultation 3.2 Application consultation – external, internal and other consultees

4 Application assessment 4.1 Planning policies 4.2 Main planning considerations 4.3 Other planning considerations 4.4 Planning obligations and CIL 4.5 Equality duty and human rights 4.6 Planning balance and conclusion 4.7 Recommendations

5 Appendices 1 – Draft Decision Notice i. – List of main planning policies ii. – List of consultees 4 – Site photographs 1. Summary of application 1.1 Executive summary 1.1.1 Macro Investments Limited have applied for planning permission for the change of use of an existing vacant hostel for use by single homeless men (sui generis) to a hostel for use as visitor accommodation (sui generis).

1.1.2 The proposed change of use would take place at basement, ground, first, second and third floor levels and will comprise 209 bed spaces. The proposed development will provide acceptable standard of accommodation, providing building regulations compliant levels of accessibility.

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
35: 43 Bondway London (Vauxhall) 25/02795/FULReport 1.2 MB DownloadRead as text

At this meeting

Whole meeting
3MinutesApproved 490-96 Norwood High Street London (Knight’s Hill) 24/03306/FULAgreed
535 – 43 Bondway London (Vauxhall) 25/02795/FULThis decision

Who was there

7 of 8 attended
KO
Councillor Kita OgdenChair, present
JS
Councillor Joanne SimpsonVice-Chair, apologies
VW
Councillor Viktor WesterdahlCommittee Member, present
EF
Councillor Elizabeth FraserCommittee Member, present
JB
Councillor Jacqueline BondCommittee Member, present
DF
Councillor David FordCommittee Member, present
DC
Councillor Diogo CostaCommittee Member, present
JE
Councillor John-Paul EnnisSubstitute, present as substitute

More from Lambeth Planning Applications Committee

All decisions
MeetingDecisionOutcome
8 Sep 2026 MinutesThat the minutes of the previous meetings held on Tuesday 7 July 2026 and Tuesday 28 July 2026 be approved and signed... Approved Open
28 Jul 2026 MinutesThat the minutes of the previous meeting held on Tuesday 23 June 2026 be approved and signed by the Chair as a correc... Approved Open
28 Jul 2026 Mahatma Gandhi Industrial Estate (Herne Hill and Loughborough Junction) 26/01850/RG3RESOLVED Unanimously, To grant conditional planning permission. To delegate authority to the Director of Planning and... Decided Open
7 Jul 2026 Clapham Common, London (Clapham Common and Abbeville) 25/03979/RG4RESOLVED Unanimously, 1. To grant conditional planning permission. 2. Agree to delegate authority to the Director of ... Agreed Open
23 Jun 2026 MinutesThat the minutes of the previous meeting held on Tuesday 14 April and Tuesday 28 April 2026 be approved and signed by... Approved Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies