Resolved
The from the Audit and Risk Committee meeting held on the 22 June 2026, were agreed unanimously as an accurate record of proceedings.
Audit and Risk Committee agreed this item on Thursday 23 July 2026. Below is the council's own wording, with the papers it was decided on.
Resolved
The from the Audit and Risk Committee meeting held on the 22 June 2026, were agreed unanimously as an accurate record of proceedings.
AUDIT AND RISK COMMITTEE MINUTES
Monday 22 June 2026 at 5.30 pm Committee Room (B6) - Lambeth Town Hall, Brixton, London, SW2 1RW
Members Present: Councillor David Amos (Chair), Councillor Matt Wilcock, Councillor Judith Cavanagh and Councillor Matthew Bryant
Co-optees Present: Paula Mills
Apologies: Councillor Jacqueline Bond
Also present: Raymond Prince, Zena Cooke, Glenn Hammons, Paul Rock, Suresh Patel, Paddy Sadd, Michelle Rice, Andrew Eyres, Richard Sparkes, Chloe Morris and Kaya Small.
Present Online: Michael O`Reilly, Verdal McGowan, Kal Rai and James Rimmington.
1 Declaration of Pecuniary Interests There was none.
2 Minutes RESOLVED: The minutes from the Corporate Committee meeting held on 26 March 2026, were agreed unanimously as a correct record of proceedings.
3 Work Programme and Action Monitoring Log 2026 - 2027 The report was introduced by the Democratic Services Officer, who provided a brief update. The report comprised two key appendices: Appendix A, which outlined the Work Programme for 2026–2027, and Appendix B, which detailed the action monitoring log. At the time of the meeting, two actions remained outstanding. The Democratic Services Officer noted that these actions were being monitored by officers and that an update on their completion would be presented to the next Audit and Risk Committee meeting on 23 July 2026.
The Democratic Services Officer also noted that the Terms of Reference contained within the Work Programme (Appendix A) would be updated at the next Audit and Risk Committee meeting on 23 July 2026. Until that time, the full Terms of Reference could be found on the Council's website under the Constitution.
Committee Members queried why the six-month complaints update had not been included on the agenda, as it was a regular item for the Committee. Committee Members also queried why information related to the artificial intelligence work being conducted by the Council was absent from the Work Programme, while noting that issues relating to policy controls, risks and safeguards should be considered by the Committee. The Assistant Director of Internal Audit and Counter Fraud explained that officers had agreed to bring an annual complaints report to the Committee in July 2026 alongside other annual reports. A six-monthly update would then follow six months later, establishing an ongoing cycle of an annual report followed by a six-monthly update to provide a fuller picture of complaints activity over the year.
RESOLVED: That the Committee 1. Consider and agree the Audit and Risk Committees’ Work Programme for 2026 (Appendix A). 2. Consider and discuss the progress and/or completion of actions in Audit and Risk Committee’s actions monitoring log (Appendix B) and agree that completed actions can be closed.
4 Update on the Council's Action Plan response to the External Auditor Recommendations under paragraph 2 of Schedule 7 of the Local Audit and Accountability Act 2014 The Corporate Director of Resources introduced the report, noting that it was a regular standing item that would be brought to the Committee on an ongoing basis. An updated version of the report would be presented at the next Audit and Risk Committee meeting on 23 July 2026. The forthcoming report would include Quarter 4, whereas the current report referred to Quarter 3. Officers had completed the Quarter 4 year-end work, which was due to be published on 23 June 2026 in advance of Cabinet, enabling officers to provide an update on the staff recommendations report.
The Corporate Director of Resources further noted that the report had been agreed for closure at the last Corporate Committee meeting, and that this was reflected in the action plan. Officers continued to progress the work that had been agreed by the Committee.
In response to Committee Members questions, it was explained that:
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
PDF |
MinutesMinutes | 12 pages | DownloadRead as text |
Follow Audit and Risk Committee at Lambeth and we tell you when its next papers are published, before the meeting rather than after it.
| Meeting | Decision | Outcome | |
|---|---|---|---|
| 23 Jul 2026 | Work Programme and Action Monitoring Log 2026-2027That the Committee Consider and agree the Audit and Risk Committees’ work programme for 2026 (Appendix A). Consider a... | Agreed | Open |
| 23 Jul 2026 | Counter Fraud Annual Report 2025/26That the Committee Consider outcomes of Counter Fraud annual report for 2025/26. | Decided | Open |
| 23 Jul 2026 | Annual Governance Statement 2025/26That the Committee Consider the findings of the review of the internal control system, and Approve the Annual Governa... | Approved | Open |
| 23 Jul 2026 | Report on Regulation of Investigatory Powers Act 2000That the Committee Note the contents of the report. Approve the Policy appended to this report covering: (a) Directed... | Noted | Open |
| 23 Jul 2026 | Assurance on key Council risks held by the Growth and Environment DirectorateThat the Committee · Consider the key Growth and Environment Directorate risks and associated control measures, and t... | Decided | Open |
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Keeps you signed in and runs your free-paper allowance. Always on.
Counts visits and which pages are used. First-party only, no advertising, never shared.