Resolved
That the conclusion of the process for procuring actuarial services for the Fund and the appointment of Mercer as the Fund Actuary for a period of three years with the option to extend for a further three years be noted.
Pension Fund Committee noted this item on Friday 15 July 2011. Below is the council's own wording, with the papers it was decided on.
Resolved
That the conclusion of the process for procuring actuarial services for the Fund and the appointment of Mercer as the Fund Actuary for a period of three years with the option to extend for a further three years be noted.
The contract for provision of actuarial services to the Lancashire County Pension Fund has not been formally tendered for some time. As part of the ongoing work to establish collaborative working with neighbouring funds and to formalise the Fund's contractual relationships the Committee has previously approved the undertaking of a joint procurement with the Cumbria and Merseyside Funds. This process has been led by the Merseyside Fund and this report summarises the results of the process and recommends the appointment of the new Fund Actuary.
The Committee is asked to note the conclusion of the process for procuring actuarial services for the Fund and the appointment of Mercer as the Fund Actuary for a period of three years with the option to extend for a further three years.
Background and Advice
The current arrangements for the provision of actuarial services to the Lancashire County Pension Fund are less formal than would be desirable and have been due for exposure to competition for some time. As a result the Pension Fund Committee approved a joint procurement with the Cumbria and Merseyside Funds.
While the Merseyside Fund has led the procurement process all three funds have participated in the evaluation and scoring of the formal proposals and presentations and have come to a common recommendation which will be processed through the relevant decision making processes.
At an early stage the basis for evaluation was agreed as 65% quality and 35% price reflecting the fact that in this particular type of contract the quality of advice can have far greater financial consequences than the simple price of the service. The quality of provision was assessed based both on the tender submissions and a series of presentations by the staff who would be involved in delivering the contract. All four actuarial firms that are active in the local government market submitted bids, with the nature of the team's put forward and the pricing indicating the benefits of a collaborative procurement of this nature. Other than the successful bidder the firms are not identified below, as this report will be published prior to detailed feedback being provided to the unsuccessful firms.
The overall scores at the end of the procurement process were as set out in the table below:
Firm A Firm B Firm C Firm D Quality Score 51.01 44.69 60.92 65.00 Price Score 25.67 20.22 35.00 32.48 Total Score 76.68 64.90 95.92 97.48 Rank 3 4 2 1
The conclusion of the evaluation panel was that Firm D, Mercer should be appointed for a term of three years with the option to extend for a further three years. The County Treasurer approved this under the new arrangements for procurement on 15th June 2011. Following the approval by the Merseyside Fund, the standstill period required under EU law has now expired and the contract can commence.
The officers involved in the process have concluded that there is likely to be significant advantage for all three funds in managing this contract collectively, both to reduce the overall effort involved but also to ensure that all three funds gain the benefit of new developments as they occur.
Consultations
County Secretary and Solicitor in terms of procurement law.
Implications:
This item has the following implications, as indicated:
The procurement process led by the Merseyside Fund has been conducted in line with EU procurement law so as to mitigate the risk of challenge.
The implementation plans for the contract would have catered for the various risks which exist around the transition from one provider to another, although in the event this is unnecessary. Financial
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
PDF |
Award of the Contract for Actuarial ServicesReport | 64 KB | DownloadRead as text |
PDF |
View item 12. as DOC 150 KBReport | 2 pages | Download |
Follow Pension Fund Committee at Lancashire & Rossendale and we tell you when its next papers are published, before the meeting rather than after it.
| Meeting | Decision | Outcome | |
|---|---|---|---|
| 18 Sep 2026 | Minutes of the last meeting.That the Minutes of the meeting held on 19 June 2026 are confirmed as an accurate record and signed by the Chair | Decided | Open |
| 18 Sep 2026 | Lancashire County Pension Fund - Governance mattersi) That the updates set out in the report regarding training, oversight and governance of the Lancashire County Pensi... | Noted | Open |
| 18 Sep 2026 | Lancashire County Pension Fund - Conflicts of Interest PolicyThat, subject to any minor amendments that may be suggested by the Lancashire Local Pension Board, the draft Conflict... | Approved | Open |
| 18 Sep 2026 | Audit Assurance 2025/26That the summary of outcomes from internal audit work undertaken in relation to the Lancashire County Pension Fund in... | Noted | Open |
| 18 Sep 2026 | Independent Governance ReviewThat approval is given for an of the Lancashire County Pension Fund to be undertaken in Q1 of 2027/28 and for the Ind... | Approved | Open |
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Keeps you signed in and runs your free-paper allowance. Always on.
Counts visits and which pages are used. First-party only, no advertising, never shared.