Resolved
Agreed: That the comments of the Forum in relation to the list of schemes approved for the 2014/15 capital programme be noted and where appropriate necessary action taken and further updates provided via the Action Sheet.
Chorley Three Tier Forum agreed this item on Tuesday 8 April 2014. Below is the council's own wording, with the papers it was decided on.
Resolved
Agreed: That the comments of the Forum in relation to the list of schemes approved for the 2014/15 capital programme be noted and where appropriate necessary action taken and further updates provided via the Action Sheet.
Appendix H 2014/15 Chorley Capital Programme Maintenance of Highway Assets Project Name Divisions Project Description Location of Scheme Total Cost Quarter Programme: A, B & C Roads Capital Allocation £486,245 B5252 Gillibrand and Miles Chorley South Surface Dressing A581 Foxhole Road to A6 Bolton Road £133,980 Q2 Standish Way Link Road Chorley Hall Road to Clifford Street - Preston Road Chorley West Low skid resistance and preventative maintenance £24,360 Q2 Southbound Dual Hartwood Hall roundabout to Clayton A6 Preston Road Chorley North Surface Dressing £143,724 Q2 Green Road
B6227 Railway Road, Adlington Chorley Rural East Surface Dressing A6 Church Street to A673 Chorley Road £24,360 Q2
B5256 Westwood Road to A675 B5256 Sandy Lane Chorley Rural North Surface Dressing £112,056 Q2 Hoghton Road A6061 Riley Green Switch Road, South Ribble boundary to A674 Chorley Rural North Surface Dressing £48,720 Q2 Hoghton Finnington Lane Forecast Outturn Capital Expenditure £487,200
Programme: Urban Unclassified Capital Allocation £113,846
Belmont Road, Adlington Chorley Rural East Carriageway Resurfacing, Micro Asphalt Peel Street to Mayfield Drive £22,046 Q3
Mayfield Drive, Adlington Chorley Rural East Carriageway Resurfacing, Micro Asphalt Railway Road to Belmont Road £8,282 Q3
Highfield Road, Adlington Chorley Rural East Carriageway resurfacing Railway Road to Chester Place £45,919 Q1 Park Road, Adlington Chorley Rural East Surface Dressing Chapel Street to Castle Drive £24,360 Q2 Highfield Road North, Adlington Chorley Rural East Surface Dressing Chester Place to Fairview £6,091 Q2 Forecast Outturn Capital Expenditure £106,698
Programme: Rural Unclassified Capital Allocation £86,715
Town Lane, Heskin Chorley West Footway Resurfacing Wood Lane to Barmskin Lane £22,001 Q3 The Green to Entrance New Bradley Hall Bradley Lane, Eccleston Chorley Rural West Footway Resurfacing £24,360 Q1 Farm Red Lane/Back Lane, Eccleston Chorley Rural West Footway Resurfacing Near Alder Hall £22,001 Q3
Whinney Lane, Euxton Chorley Rural West Surface Dressing Washington Lane to Euxton Lane £22,001 Q2 Forecast Outturn Capital Expenditure £90,363
Programme: Footways Capital Allocation £99,479 The warings, Heskin Chorley West Footway Resurfacing Full length £53,714 Q4 Smithy Close, Brindle Chorley Rural North Footway Resurfacing No.17 to No.43 £18,271 Q1 Letchworth Drive Chorley South Footway Resurfacing Collingwood Road to Lightfield Drive £27,405 Q1 Forecast Outturn Capital Expenditure £99,390
Local Priorities Response Fund Capital Allocation £153,216 Footpaths A674 Wheelton Chorley Rural East Footways improvement Sections along the southern side £24,360 Q3 Southdowns Road Chorley South Footways improvement Full length £29,232 Q3 Furness Close Chorley South Footways improvement Full length £6,091 Q3 Pilling Lane Chorley South Footways improvement Full length £88,500 Q4 Chorley East/Chorley Park Road Red Slurry Seal Entrance to Astley Park £5,900 Q3 West Forecast Outturn Capital Expenditure £154,083
Programme: Lighting Column Replacement Capital Allocation £62,725 Chorley Col Replace Various as necessary Column Replacement Chorley £62,725 Q4 Forecast Outturn Capital Expenditure £62,725
Programme: Flood Risk Management & Drainage Capital Allocation £90,417
Spendmore Lane Chorley West Drainage improvements/flood relief Spendmore Lane £30,030 Q3
Nell Lane, Clayton Le Woods Chorley Rural North Investigation and remedial works Nell Lane, Claton Le Woods £15,015 Q3
Town Lane, Heskin Chorley West New surface water drainage system Town Lane, Heskin £15,015 Q3
Chapel Lane, Coppull Chorley West Investigation works Chapel Lane, Coppull £22,523 Q3
Various in Chorley various as necessary CCTV works in various locations Chorley District £7,508 Q2
Forecast Outturn Capital Expenditure £90,091
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
PDF |
2014/15 Environment Capital Programme.Appendix | 113 KB | DownloadRead as text |
Follow Chorley Three Tier Forum at Lancashire & Rossendale and we tell you when its next papers are published, before the meeting rather than after it.
| Meeting | Decision | Outcome | |
|---|---|---|---|
| 8 Apr 2014 | Note of the Last Meeting.Agreed: That the Note of the meeting held on the 18 th November 2013 is confirmed as an accurate record and signed by... | Agreed | Open |
| 8 Apr 2014 | Action Sheet update from the last meeting.Agreed: That the comments of the Forum set out above be noted and where appropriate further updates provided via the ... | Agreed | Open |
| 8 Apr 2014 | Developing the 3 Tier ForumAgreed: That the new format of the Forum, as proposed by the Borough Council and set out in the draft Terms of Refere... | Agreed | Open |
| 8 Apr 2014 | Quarter 3 Environment Directorate Performance Dashboard.Agreed: 1. That the updates set out in the Dashboard for Quarter 3 (October/December 2013) be noted 2. That Officers ... | Agreed | Open |
| 8 Apr 2014 | Neighbourhood workingAgreed: That the report is noted and the information set out in the missing Appendices 1 and 2 regarding neighbourhoo... | Agreed | Open |
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Keeps you signed in and runs your free-paper allowance. Always on.
Counts visits and which pages are used. First-party only, no advertising, never shared.