Resolved
That the Committee noted the report.
Audit, Risk and Governance Committee noted this item on Monday 29 January 2018. Below is the council's own wording, with the papers it was decided on.
Resolved
That the Committee noted the report.
The Audit, Risk and Governance Committee received a report in June 2017 that set out the improvements made to the Liquid Logic system, the proposed next steps for the system and an update on how governance arrangements for system developments and implementations had been progressed.
At the request of the Committee, this report provides a further update outlining action taken in relation to the Liquid Logic System over the past 6 months.
The Audit, Risk and Governance Committee is recommended to consider the report and comment as appropriate.
Background and Advice
In June 2017, the Audit and Governance Committee received a report that set out the latest position on the Liquid Logic Social Care Systems for Children and Adult services and updated on progress made to date. The report set out the principle issues and the actions being put in place to resolve them. The report also outlined new governance arrangements which had been put in place to enable an improvement in the management and control of systems and the understanding of roles and responsibilities.
The principle issues reported were:
Misalignment of staff hierarchies and Liquid Logic Adult Services (LAS) and Liquid Logic Children's Services (LCS) and delays in keeping systems updated and accurate; Uncoordinated system changes requested and unclear ownership and responsibility for the systems requiring clearer governance arrangements; Quality and accuracy of data within the systems and a backlog in the required data cleansing process; Delay in updating 'Date of Death' information on LAS; Maintaining a consistent and sustainable BAU operating model to prevent the re-occurrence of issues; Management of providers still using paper invoices.
Whilst some actions were reported through the previous report presented in June 2017, this current report provides additional information.
Progress to Date
Misalignment of staff hierarchies and Liquid Logic Adult Services (LAS) and Liquid Logic Children's Services (LCS) and delays in keeping systems updated and accurate:
Work to ensure that social work structures, authorisation levels etc. are accurately reported within LCS is now complete. The maintenance of this information forms part of the Business as Usual (BAU) operating model. A similar process for LAS is nearing completion.
Uncoordinated system changes requested and unclear ownership and responsibility for the systems requiring clearer governance arrangements:
Strong governance arrangements continue to be in place across both LAS and LCS as detailed below:
System ownership for all systems has been transferred to the Core Systems/ Transformation team with dedicated, named resource attached to the system. This first line of contact will be crucial in ensuring a line of sight for the Director of Adult's Services and the Director of Children's Services on all system related activity.
Portfolio Review Boards are now in place for key service areas including LAS and LCS to enable the 'Business Users' to be actively engaged, make 'key decisions', understand and be more responsible/accountable in the systems they use. These have been developed with key managers across Adult and Children's Services.
System development roadmaps have been developed for both Adult and Children's Services. These provide the key monitoring document for senior managers within the service. The documents will require the agreement and approval of the Director of Adult Services and the Director of Children's Services.
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
PDF |
Liquid Logic System UpdateReport | 118 KB | DownloadRead as text |
PDF |
View item 10. as DOC 176 KBReport | 4 pages | Download |
Follow Audit, Risk and Governance Committee at Lancashire & Rossendale and we tell you when its next papers are published, before the meeting rather than after it.
| Meeting | Decision | Outcome | |
|---|---|---|---|
| 27 Jul 2026 | Constitution, Membership and Terms of ReferenceThat the following be noted: i) The appointment of County Councillor G Mirfin as Chair and County Councillor R Edward... | Noted | Open |
| 27 Jul 2026 | Minutes of the Meeting held on 27 April 2026That the minutes of the Audit, Risk and Governance Committee meeting held on 27 April 2026 be confirmed as an accurat... | Decided | Open |
| 27 Jul 2026 | Statement of Accounts 2025/26That the 2025/26 statement of accounts for Lancashire County Council be noted. | Noted | Open |
| 27 Jul 2026 | External Audit: Lancashire County Council External Audit Plan 2025/26That the Lancashire County Council External Audit Plan 2025/26 be noted. | Noted | Open |
| 27 Jul 2026 | External Audit: Lancashire County Pension Fund External Audit Plan 2025/26That the Lancashire County Pension Fund External Audit Plan 2025/26 be noted. | Noted | Open |
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Keeps you signed in and runs your free-paper allowance. Always on.
Counts visits and which pages are used. First-party only, no advertising, never shared.