That i. a maximum funding allocation of £4.9m be approved to the North West Burnley Growth Corridor scheme subject to the conditions agreed by the Growth Deal Management Board ii. the retention of £2.1m of the original £7m allocation be approved for the North West Burnley Growth Corridor scheme for a period of four months and, in the event that the £2.1m is not required for the scheme, agree that it will be subject to the LEP's approval process for redistributing any unallocated funds within the Growth Deal programme iii. the changes to the Growth Deal unallocated funding approval process as set out in the report be approved iv. the process for approving Growth Deal quarterly reporting submissions to the Cities and Local Growth Unit be approved, including providing retrospective approval for the Quarter 3 2017/18 Quarterly Reporting Summary Dashboard.
Word for word from the decision Lancashire & Rossendale published for this meeting.Source: council.lancashire.gov.uk
This report requests that the LEP Board approves a funding allocation for the North West Burnley Growth Corridor scheme.
The report also provides the LEP Board with an updated approval process for the redistribution of unallocated Growth Deal funds and provides an update on the overall performance of the Growth Deal programme, including the new requirement from Government for the LEP Board to sign-off Growth Deal claims.
Recommendation
The LEP Board is asked to:
(i) Approve a maximum funding allocation of £4.9m to the North West Burnley Growth Corridor scheme subject to the conditions agreed by the Growth Deal Management Board;
(ii) Approve the retention of £2.1m of the original £7m allocation for the North West Burnley Growth Corridor scheme for a period of four months and, in the event that the £2.1m is not required for the scheme, agree that it will be subject to the LEP's approval process for redistributing any unallocated funds within the Growth Deal programme;
(iii) Approve the changes to the Growth Deal unallocated funding approval process as set out in this report; and
(iv) Approve the process for approving Growth Deal quarterly reporting submissions to the Cities and Local Growth Unit, including providing retrospective approval for the Quarter 3 2017/18 Quarterly Reporting Summary Dashboard. Background and Advice
North West Burnley Growth Corridor
At the meeting of the Growth Deal Management Board in December, Genecon Consulting Ltd presented their independent appraisal findings of the North West Burnley Growth Corridor business case. The scheme, which was seeking a £7m Growth Deal funding approval recommendation, would deliver infrastructure works at three sites in Padiham and Burnley, to unlock employment and housing growth.
The scheme focused on three main elements:
Raised flood defences along the River Calder and Green Brook through Padiham to enable housing growth delivery; Public Realm Improvements aimed at boosting the vitality of Padiham Town Centre; and Junction Improvements at the A6068/A678 Blackburn Road junction, which would enable the development of the proposed Shuttleworth Meade Employment Site.
The Growth Deal Management Board resolved that a funding approval for a maximum £7m of Growth Deal funding be recommended to the next meeting of the LEP Board subject to the conditions precedent identified in the independent appraisal report.
In January, the scheme applicant, Burnley Borough Council, requested that the presentation of the scheme to the January meeting of the LEP Board to seek a funding approval be deferred.
In July 2017, Burnley Borough Council had submitted a full Local Plan for examination with public hearings taking place in November and December 2017. The Local Plan included a proposed change to land use at the Shuttleworth Meade and Baxi Sites, to enable the sites to come forward for employment and housing uses.
The Inspector is proposing a main modification to reduce the employment land allocation from 90ha to 66 ha and the removal of two employment sites, including Shuttleworth Meade, from the plan. The Inspector's proposed modifications are currently being consulted on and once the consultation has been completed the Inspector will make a final decision and issue a report.
The change of land use for the Baxi Site was accepted by the Inspector.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Follow Lancashire Enterprise Partnership at Lancashire & Rossendale and we tell you when its next papers are published, before the meeting rather than after it.
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.