Internal Audit Progress Report

Noted Finance 8 papers

Audit, Risk and Governance Committee noted this item on Monday 30 April 2018. Below is the council's own wording, with the papers it was decided on.

Item4

Resolved

- That the report, now presented, be noted.
Word for word from the decision Lancashire & Rossendale published for this meeting. Source: council.lancashire.gov.uk

Follow this further

Built from Lancashire & Rossendale's papers

What the report saysPro

Report to Audit, Risk and Governance Committee

Internal Audit Service progress against plan 2017/18 Audit, Risk and Governance Committee meeting 30 April 2018

Matters arising from internal audit work completed during the period to 31 March 2018 1 Introduction 1.1 This report highlights the issues that the Audit, Risk and Governance Committee should be aware of in fulfilling its role of providing independent oversight of the adequacy of the council's governance, risk management and internal control framework. It sets out the issues arising from the work undertaken during the period to 31 March 2018 by the Internal Audit Service under the audit plan for 2017/18. 1.2 A full table of all the work on the audit plan for 2017/18 is included at Appendix B, setting out brief notes of the progress made and conclusions on each engagement. The audit work still in progress at this point will be finalised and reported to the Audit, Risk and Governance Committee on 30 July 2018. 1.3 The work completed to the end of March 2018 supports the overall opinion in the annual internal audit report which is set out in the separate annual report to this committee. 2 Progress as at the year end 2.1 Audit work has progressed well and is either complete or is very nearly so at the year-end; a number of engagements remain to be finalised and will be reported to the committee at its next meeting in July 2018. Of the 58 audit engagements on the audit plan agreed in June 2017 after work on 11 audits has been deferred or cancelled, 31 have been reported, 12 reports are being prepared and discussed with management and 15 are in progress and/ or already nearing completion. 3 The assurance available from completed audit work 3.1 A brief summary of the assurance provided for each of the audits relating to 2017/18 and completed by 31 March 2018 is provided in the table below. More information about the matters arising from each of the audits completed since December 2017 is set out in section 6 and progress reports in September 2017 and January 2018 provide more information about each of the audits completed earlier in the year. Control area Assurance Business effectiveness Preparation and use of the corporate risk register. Full Oversight of the Lancashire Pension Fund. Substantial Service delivery: adult services Complex case forums decision making process (formerly 'panel decision Limited making processes'). Direct payments to service users and their carers. Substantial Direct payment financial reviews. Substantial Service user financial assessments. Substantial Internal Audit Service progress against plan 2017/18 Audit, Risk and Governance Committee meeting 30 April 2018

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
Enc. 1 for Internal Audit progress reportReport 112 KB DownloadRead as text
PDF
Enc. 2 for Internal Audit progress reportReport 130 KB Download
PDF
Enc. 3 for Internal Audit progress reportReport 68 KB Download
PDF
Internal Audit Progress ReportReport 85 KB Download
PDF
View as DOCX (4./2) 41 KBReport 10 pages Download
PDF
View as DOCX (4./3) 58 KBReport 16 pages Download
PDF
View as DOCX (4./4) 25 KBReport 2 pages Download
PDF
View item 4. as DOC 144 KBReport 1 pages Download

At this meeting

Whole meeting

Who was there

8 of 8 attended
CA
CC A SchofieldChair, present
CE
CC E NashDeputy Chair, present
CP
CC P WilliamsonCommittee Member, present
CA
CC A VincentCommittee Member, present
CJ
CC J BerryCommittee Member, present
CE
CC E LewisCommittee Member, present
CM
CC M ParkinsonCommittee Member, present
CC
County Councillor John ShedwickCommittee Member, present

On this subject at Lancashire & Rossendale

Search all
  1. Internal Audit Progress ReportThis decision
  2. Internal Audit Annual Report 2025/26 and Progress ReportNoted
  3. Internal Audit Charter and MandateApproved
  4. Internal Audit Annual Report for the Year Ended 31 March 2026Noted
  5. Internal Audit Progress ReportNoted
  6. Internal Audit Progress ReportNoted

More from Lancashire & Rossendale Audit, Risk and Governance Committee

All decisions
MeetingDecisionOutcome
27 Jul 2026 Constitution, Membership and Terms of ReferenceThat the following be noted: i) The appointment of County Councillor G Mirfin as Chair and County Councillor R Edward... Noted Open
27 Jul 2026 Minutes of the Meeting held on 27 April 2026That the minutes of the Audit, Risk and Governance Committee meeting held on 27 April 2026 be confirmed as an accurat... Decided Open
27 Jul 2026 Statement of Accounts 2025/26That the 2025/26 statement of accounts for Lancashire County Council be noted. Noted Open
27 Jul 2026 External Audit: Lancashire County Council External Audit Plan 2025/26That the Lancashire County Council External Audit Plan 2025/26 be noted. Noted Open
27 Jul 2026 External Audit: Lancashire County Pension Fund External Audit Plan 2025/26That the Lancashire County Pension Fund External Audit Plan 2025/26 be noted. Noted Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies